2012-00009 |
I-5 Reinforcement Project crossing Columbia River - Longview and Troutdale van Dijk, Richard
Date Received: 10/22/2011 Date Due: 11/8/2011 Date Completed: 11/5/2011
Comments: Records sent. Ex 5. CLOSED.
|
|
2012-00089 |
BPA's current energy/capacity contracts with Whatcom County and Chelan Findley, Bethany
Date Received: 10/14/2011 Date Due: 11/14/2011 Date Completed: 10/24/2011
|
|
2012-00163 |
Consult on van Dijk request US Army Corps of Engineers
Date Received: 1/20/2013 Date Due: 2/28/2012 Date Completed: 3/5/2012
Comments: Ex 5 & 6. CLOSED.
|
|
2012-00176 |
Check that paid for easement with City of Chehalis Obsborn, Joyce
Date Received: 10/24/2011 Date Due: 11/22/2011 Date Completed: 10/28/2011
Comments: Records sent in its entirety. CLOSED
|
|
2012-00180 |
Gather documents related to commemorative items DOE
Date Received: 5/45/2012 Date Due: 5/18/2012 Date Completed: 5/16/2012
Comments: Records sent to DOE FOIA. CLOSED
|
|
2012-00183 |
Document review for Richard van Dijk request US Army Corps of Engineers
Date Received: 5/7/2012 Date Due: 6/5/2012 Date Completed: 6/4/2012
Comments: Records sent. Ex 5 & 6. CLOSED
|
|
2012-00185 |
SF-50s for FOIA personnel DOE/Sutter
Date Received: 5/17/2012 Date Due: 6/1/2012 Date Completed: 5/18/2012
Comments: Records sent. Ex 6. CLOSED
|
|
2012-00189 |
Review of documents on Richard van Dijk appeal DOE
Date Received: 5/31/2012 Date Due: 6/28/2012 Date Completed: 6/4/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-00194 |
Augsperger Mountain Radio Station Fiber Upgrade Johnson, Benjamin
Date Received: 10/21/2011 Date Due: 11/29/2011 Date Completed: 1/9/2012
Comments: Records sent. Ex 5. CLOSED.
|
|
2012-00195 |
Contract with TerrAqua, Inc. Nadeau, Mark
Date Received: 10/27/2011 Date Due: 11/29/2011 Date Completed: 2/17/2012
Comments: Records sent. Ex 4. CLOSED.
|
|
2012-00196 |
Implementation of Job Family Standards for IT Program Manager position Warren, Richard
Date Received: 6/15/2012 Date Due: 7/16/2012 Date Completed: 6/27/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-00224 |
Review BPA document for release Sulfur Creek 2010 Fisheries Report DOI
Date Received: 8/13/2012 Date Due: 9/11/2012 Date Completed: 8/29/2011
Comments: Sent in its entirety. CLOSED
|
|
2012-00235 |
I-5 emails - Baskerville van Dijk, Richard
Date Received: 11/7/2011 Date Due: 12/7/2011 Date Completed: 12/9/2011
Comments: Records sent. Ex 5 & 6. CLOSED
|
|
2012-00236 |
I-5 emails - Klumpp van Dijk, Richard
Date Received: 11/7/2011 Date Due: 12/7/2011 Date Completed: 2/1/2012
Comments: Records sent. Ex 5 & 6. CLOSED
|
|
2012-00238 |
I-5 emails - Wittpenn van Dijk, Richard
Date Received: 11/7/2011 Date Due: 12/7/2011 Date Completed: 1/27/2012
Comments: Records sent. Ex 5 & 6. CLOSED
|
|
2012-00243 |
Albeni Falls Dam Flexible Winter Operations Environmental Assessment Drumheller, Susan
Date Received: 11/7/2011 Date Due: 12/7/2011 Date Completed: 2/22/2012
Comments: Records sent. Ex 5. CLOSED.
|
|
2102-00294 |
I-5 public comments after October 2010 van Dijk, Richard
Date Received: 11/17/2011 Date Due: 12/6/2011 Date Completed: 12/5/2011
Comments: Records sent. Ex 6. CLOSED.
|
|
2012-00330 |
all documentation or materials submitted by Biomark Minutillo, Daniel
Date Received: 12/5/2011 Date Due: 1/3/2012 Date Completed: 5/16/2012
Comments: Records sent. Ex 3 & 4. CLOSED
|
|
2012-00364 |
Asotin wildlife area contracts, communications 2010-2011 Kavanaugh, Rob
Date Received: 12/6/2011 Date Due: 1/5/2012 Date Completed: 1/30/2012
Records sent. Ex 5 & 6. CLOSED
|
|
2012-00399 |
amount paid to Tek-Systems for telecom tech position Privacy Act
Date Received: 12/12/2011 Date Due: 1/11/2012 Date Completed: 12/15/2011
Comments: Sent in its entirety. CLOSED
|
|
2012-00412 |
Tek-Systems Rice, Michael
Date Received: 12/13/2011 Date Due: 1/12/2012 Date Completed: 12/15/2011
Comments: Sent in its entirety. CLOSED
|
|
2012-00476 |
I-5 Reinforcement Project Pearl substation van Dijk, Richard
Date Received: 12/29/2011 Date Due: 1/30/2012 Date Completed: 3/8/2012
Comments: Ex 5 & 6. CLOSED
|
|
2012-00477 |
I-5 Reinforcement Project Troutdale substation van Dijk, Richard
Date Received: 12/29/2011 Date Due: 1/30/2012 Date Completed: 3/8/2012
Comments: Ex 5 & 6. CLOSED
|
|
2012-00478 |
I-5 Reinforcement Project/Port of Portland purchase Troutdale land van Dijk, Richard
Date Received: 12/29/2011 Date Due: 1/30/2012 Date Completed: 3/8/2012
Comments: Ex 6. CLOSED
|
|
2012-00479 |
I-5 Reinforcement Project - listening meeting agenda, notes, presentation van Dijk, Richard
Date Received: 12/29/2011 Date Due: 1/30/2012 Date Completed: 3/8/2012
Comments: Ex 6. CLOSED
|
|
2012-00507 |
Montana 500 kv transmission Hofland, Kory
Date Received: 1/4/2012 Date Due: 2/2/2012 Date Completed: 2/22/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-00551 |
I-5 Reinforcement Project e-mails, correspondence from or to Golder Associates Constance, Terry
Date Received: 1/11/2012 Date Due: 2/9/2012 Date Completed: 5/31/2012
Comments: Records sent. Ex2,5&6
|
|
2012-00552 |
Supplemental labor posting for telecommunication support technician Weisberg, Michael
Date Received: 1/11/2012 Date Due: 2/9/2012 Date Completed: 2/3/2012
Comments: Records sent. Ex 6. CLOSED.
|
|
2012-00624 |
Corona & Field Effects Version 3.0 (2011-00167-F) Bajda, Ryszard
Date Received: 1/23/2012 Date Due: 2/21/2012 Date Completed: 1/26/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-00625 |
Amount paid to TEK-SYSTEMS for Network Technician Level 1 Privacy Act
Date Received: 1/26/2012 Date Due: 2/24/2012 Date Completed: 2/2/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-00656 |
Corona & Field Effects Version 3.0 Dauhinais, James
Date Received: 1/31/2012 Date Due: 2/29/2012 Date Completed: 1/31/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-00659 |
PO or itemize payment amounts for six BPA catalog items from 2009 to 2011 Engberg, James
Date Received: Date Due: 2/29/2012 Date Completed: 2/17/2012
Comments: Records sent. Ex 4. CLOSED
|
|
2012-00676 |
BPA Substation Design related to direct stroke lightning shieldking of substations Carvalho, Francisco
Date Received: Date Due: 3/1/2012 Date Completed: 2/2/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-00718 |
Latest Ciber contract Simpson, Janella
Date Received: Date Due: 3/8/2012 Date Completed: 3/7/2012
Comments: Withdrawn
|
|
2012-00740 |
line item budget of BPA aviation dept, include contract pilots, aircraft Burns, Robert
Date Received: Date Due: 3/12/2012 Date Completed: 2/23/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-00793 |
BPA boilerplate hydro power purchase agreement Clark, George
Date Received: Date Due: 3/21/2012 Date Completed: 2/23/2012
Comments: Records sent. Ex 6
|
|
2012-00805 |
Sole source justifications from 8-1-10 to 11-30-11 Ivory, Danielle
Date Received: Date Due: 3/23/2012 Date Completed: 3/5/2012
Comments: Notified by DOE of withdrawal
|
|
2012-00810 |
Use of Friends of the Columbia Gorge settlement agreement funds Drummond, Susan
Date Received: Date Due: 3/26/2012 Date Completed: 2/27/2012
Comments: No responsive documents
|
|
2012-00860 |
Hyundai Heavy Industries contract for 230kv transformers Johnson, Scott
Date Received: Date Due: 4/4/2012 Date Completed: 11/30/2012
Comments: Records sent. Ex 4
|
|
2012-00862 |
HICO contract for 525kv transformers Johnson, Scott
Date Received: Date Due: 4/4/2012 Date Completed: 7/24/2012
Comments: Ex 4. CLOSED
|
|
2012-00940 |
Contract #28333 Release 19 Geotechnical Report Tapio, Peter
Date Received: Date Due: 4/18/2012 Date Completed: 4/6/2012
Comments: Records sent. CLOSED
|
|
2012-00941 |
Wilson Construction bid Tapio, Peter
Date Received: Date Due: 4/18/2012 Date Completed: 6/21/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-00942 |
Contract #28333 Release 19 Inspection reports, photos, records Tapio, Peter
Date Received: Date Due: 4/18/2012 Date Completed: 5/31/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01025 |
Use of Friends of the Columbia Gorge settlement agreement funds Drummond, Susan
Date Received: Date Due: 5/1/2012 Date Completed: 4/3/2012
Comments: No responsive documents
|
|
2012-01066 |
Hydro Optimization Team meeting materials from 4/10 - 4/12 Albright, Douglas
Date Received: Date Due: 5/8/2012 Date Completed: 4/27/2012
Comments: Records sent. CLOSED. FAILURE TO PAY FEES
|
|
2012-01119 |
Settlement agreement with tribes related to Big Eddy-Knight project Sexton, Joseph
Date Received: Date Due: 5/18/2012 Date Completed: 4/23/2012
Comments: No responsive documents
|
|
2102-01121 |
2008 Tradiitional Cultural Property Monitoring in the Lower Reaches of the Nch'i-wa'na Sexton, Joseph
Date Received: Date Due: 5/20/2012 Date Completed: 5/21/2012
Comments: Records sent. CLOSED
|
|
2012-01135 |
Use of Friends of the Columbia Gorge settlement agreement funds Drummond, Susan
Date Received: Date Due: 5/23/2012 Date Completed: 4/25/2012
Comments: No responsive documents
|
|
2012-01172 |
list of all grants, contracts in contracting database Doran, Peter
Date Received: Date Due: 5/30/2012 Date Completed: 5/14/2012
Comments: Sent in its entirety. CLOSED
|
|
2102-01173 |
ARAMARK contract Marshall, Art
Date Received: Date Due: 6/15/2012 Date Completed: 6/19/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01258 |
Procedure for use of Friends of the Columbia Gorge settlement agreement funds Drummond, Susan
Date Received: Date Due: 6/27/2012 Date Completed: 7/17/2012
Comments: Records sent. Ex 5 & 6. CLOSED
|
|
2012-01311 |
Technology & Innovation Project #88 - Telemetry Demonstration Project Adams, Greg
Date Received: Date Due: 6/27/2012 Date Completed: 7/29/2013
Comments: Sent. Ex 6. CLOSED
|
|
2012-01336 |
MOAs between BPA Power & Transmission and payments Neale, Ryan
Date Received: Date Due: 6/13/2012 Date Completed: 6/23/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01350 |
Documents on BPA property in Walton, OR Swartzlander, Mary
Date Received: Date Due: 6/29/2012 Date Completed: 6/28/2012
Comments: Records sent. CLOSED
|
|
2012-01355 |
Documents on BPA property in Washington County, OR Kim, Christina
Date Received: Date Due: 7/2/2012 Date Completed: 8/22/2012
Comments: Ex 4 & Ex 6. CLOSED
|
|
2012-01387 |
phone records Qualls, John
Date Received: Date Due: 6/27/2012 Date Completed: 6/27/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01411 |
Use of Friends of the Columbia Gorge settlement agreement funds Drummond, Susan
Date Received: Date Due: 6/26/2012 Date Completed: 5/30/2012
Comments: No responsive documents
|
|
2012-01412 |
Documents re: change from Rock grouted footings to Plate footings Tapio, Peter
Date Received: Date Due: 7/12/2012 Date Completed: 7/5/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01416 |
Documents re: change from Drilled Pier foundation to Grillage Tapio, Peter
Date Received: Date Due: 7/13/2012 Date Completed: 7/5/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01466 |
All documents related to the projects for Contracts 32501 & 20546 Shaw, David
Date Received: Date Due: 7/12/2012 Date Completed: 8/7/2012
Comments: Records sent. Ex 6. CLOSED
|
|
2012-01483 |
emails between Robin Furrer, Garry Brower, Darrel Underwood re: maintenance crew at Port Angeles sub Qualls, John
Comments: Withdrawn
|
|
2012-01592 |
All documents related to the North Steens 230 Kv line project Ruether, Kristin
Date Received: Date Due: 8/16/2012
Comments: Documents in review.
|
|
2012-01616 |
Use of Friends of the Columbia Gorge settlement agreement funds Drummond, Susan
Date Received: Date Due: 8/2/2012 Date Completed: 7/27/2012
Comments: No responsive documents
|
|
2012-01617 |
Washington2Advocates contracts, communications, invoices & work product Seligman, Dan
Date Received: Date Due: 8/8/2012 Date Completed: 8/3/2012
Comments: Records sent. Ex 4 & 6. CLOSED
|
|
2012-01627 |
email from him requesting records from Kassandra Brown Qualls, John
Date Received: Date Due: 8/9/2012 Date Completed: 7/17/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01628 |
communications with Congress re: Sec. Chu 3-16-12 memo to PMAs Seligman, Dan
Date Received: Date Due: 8/10/2012 Date Completed: 8/1/2012
|
|
2012-01631 |
EMTP source code and Rule Book Khandelwal, Tanuj
Date Received: Date Due: 8/13/2012 Date Completed: 7/20/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01658 |
list of all sole source contracts in contracting database Seligman, Dan
Date Received: Date Due: 8/13/2012 Date Completed: 7/20/2012
Comments: Withdrawn
|
|
2012-01683 |
contracting dataase pull of all personal services/consultant contracts over $100,000 Seligman, Dan
Date Received: Date Due: 8/27/2012 Date Completed: 8/16/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01695 |
Recorded easements of private landowners along Big-Eddy/Knight transmission line Zornes, Robert
Date Received: Date Due: 8/27/2012
Comments: Withdrawn |
|
2012-01700 |
Agreements/docs for USEC, Energy NW, BPA, TVA, & DOE Seligman, Dan
Date Received: Date Due: 8/29/2012 Date Completed: 10/4/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01715 |
Recorded easements of private landowners along Big-Eddy/Knight transmission line Zornes, Robert
Date Received: Date Due: 9/4/2012 Date Completed: 8/8/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01716 |
Record of condemnation/eminent domain proceeds since January 2000 Baude, William
Date Received: Date Due: 8/31/2012 Date Completed: 8/14/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01752 |
structural drawings of new double circuit and single circuit towers Balvin, Russel
Date Received: Date Due: 9/12/2012 Date Completed: 8/21/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01776 |
LDD customer information Nivison, Benjamin
Date Received: Date Due: 9/17/2012 Date Completed: 9/13/2012
Comments: CLOSED. Failure to address fees.
|
|
2012-10784 |
All documents related to property Zornes, Robert
Date Received: Date Due: 9/11/2012 Date Completed: 8/27/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01801 |
Use of Friends of the Columbia Gorge settlement agreement funds Drummond, Susan
Date Received: Date Due: 9/24/2012 Date Completed: 9/25/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01802 |
All travel records for employee travel paid by private parties Peebles, Jennifer
Date Received: Date Due: 9/25/2012 Date Completed: 9/10/2012
Comments: Duplicate - CLOSED. DOE to answer
|
|
2012-01815 |
All documents for I-5 Corridor Reinforcement Project meeting on 5/31/12 at the Corps of Engineers Brantley, Cheryl
Date Received: Date Due: 9/25/2012 Date Completed: 9/10/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01829 |
EMTP Primer, Field Test Comparisons, Application Guide, Source Code documentation Khandelwal, Tanuj
Date Received: Date Due: 10/2/2012 Date Completed: 10/4/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01842 |
May 1995 letter from ID state rep Helen Chenoweth re: Dworshak Dam mitigation Erdey, Tabitha
Date Received: Date Due: 10/3/2012 Date Completed: 9/27/2012
Comments: No responsive documents
|
|
2012-01868 |
Locations of GIC monitoring devices installed, data from those devices Popik, Thomas
Date Received: Date Due: 10/5/2012 Date Completed: 10/19/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01869 |
GS-9 or higher series 0193 on staff. Masters vs. Phd Clark, Amelia
Date Received: Date Due: 10/9/2012 Date Completed: 9/25/2012
Comments: Records sent. Ex 6. CLOSED
|
|
2012-01870 |
RFO #935. Invoices against contract #36191 Seligman, Dan
Date Received: Date Due: 10/23/2012 Date Completed: 11/6/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01879 |
Contracts for legal services concerning FERC-excluding prices Seligman, Dan
Date Received: Date Due: 10/25/2012 Date Completed: 12/13/2013
Comments: Sent in its entirety. CLOSED
|
|
2012-01880 |
All docs regarding RTO West/Grid West from 1999-2005 Shwartz, Jacob
Date Received: Date Due: 10/11/2012
Comments: Withdrawn
|
|
2012-01885 |
All communications between BPA an FERC since 12/7/2011 concerning Docket EL11-44 Seligman, Dan
Date Received: Date Due: 10/11/2012 Date Completed: 9/27/2012
Comments: No responsive documents
|
|
2012-01927 |
Administrator's calendar 9-1-11 to 8-31-12 Seligman, Dan
Date Received: Date Due: 10/19/2012 Date Completed: 10/24/2012
Comments: Records sent. Ex 6. CLOSED
|
|
2012-01928 |
Documents given to FERC Chairman from 1/2012 to present Seligman, Dan
Date Received: Date Due: 10/16/2012 Date Completed: 10/16/2012
Comments: Sent in its entirety. CLOSED
|
|
2012-01929 |
Documents support BPA submission to WA DNR application #51-087560 Zornes, Robert
Date Received: Date Due: 10/16/2012
Comments: Withdrawn
|
|
2012-01948 |
Corona & Field Effect/Advanced Tower Analysis & Design Software Tharnish, Albert
Date Received: Date Due: 10/25/2012 Date Completed: 10/4/2012
Comments: Sent in its entirety. CLOSED
|
|