Develop Final (95%) design
Proceed with finalizing the design so that it is substantially complete:
- Incorporate comments from 70% review
- Develop responses to 70% review comments
- Finalize approach road design
- Finalize pullouts and parking area design
- Complete Final Road Safety Evaluation
- Complete major structure design support
- Finalize drainage design
- Finalize permanent traffic control
- Finalize temporary traffic control
- Finalize plan and profile sheets
- Finalize project specific plan/detail sheets
Step 1: Incorporate comments from 70% review
Step 2: Develop responses to 70% review comments
Step 3: Finalize approach road design
Instructions | Resources | References |
Finalize plan and profile sheets |
Proposed Pavement Widening, Adhoc Help |
WFLHD Supplement 9.6.5-1, Standard Format for Plans |
|
Finalize major intersection plans |
GEOPAK, Approach Road Match line |
WFLHD Supplement 9.6.5-1, Standard Format for Plans |
|
Finalize cross sections for earthwork, clearing and seeding reports |
Cross Section Sheets, GEOPAK V8i |
|
|
GEOPAK, Plot Cross Section Sheets |
|
|
GEOPAK, Calculating Earthwork |
|
|
GEOPAK, Earthwork Manipulation Tool |
|
|
GEOPAK, Clearing Notes |
|
|
GEOPAK, Generate Clearing Limits |
|
|
GEOPAK, Slope Stake Notes, FHWA Version 2 |
|
|
GEOPAK, XYZ Report |
|
AKA, Blue Tops and Rep Tops |
GEOPAK, Printing reports |
|
|
GEOPAK, Seeding Notes |
|
|
Step 4: Finalize pullouts and parking area design
Step 5: Complete Final Road Safety Evaluation
Step 6: Complete major structure design support
Instructions | Resources | References |
Provide support for final bridge plans. |
|
|
|
Finalize all wall layout sheets |
Proposed Cut Wall, Adhoc Help |
|
Structures to provide data for final wall profiles |
Proposed Fill Wall, Adhoc Help |
|
|
GEOPAK, Wall link |
|
|
Proposed Mechanically Stablized Earth, Adhoc Help |
|
|
Proposed Shored Mechanically Stabilized Earth, Adhoc Help |
|
|
WFL Proposed Parapet Wall, Adhoc Help |
|
|
Proposed Gabion Faced Mechanically Stablized Earth, Adhoc Help |
|
|
Proposed Going To The Sun Road, Adhoc Help |
|
|
Proposed Soil Nail Wall, Adhoc Help |
|
|
Proposed Rockery Wall, Adhoc Help |
|
|
QA/QC Checklist |
|
|
PS&E Review Comment Spreadsheet |
|
|
Step 7: Finalize drainage design
Step 8: Finalize permanent traffic control
Step 9: Finalize temporary traffic control
Step 10: Finalize plan and profile sheets
Step 11: Finalize project specific plan/detail sheets
Highway Design Process | Top