Proposed Pavement Widening (User defined superelevation)

Adhoc Name: Prop. Pavement
Description: Proposed Pavement Widening (User defined superelevation)

Typical Section showing variables

ADHOC DESCRIPTIONS

Begin Super Rate” - Cross slope super elevation rate to use when utilizing the user defined pavement widening. Specified in a percent format, represents the beginning location of the widening line location. Must never start before the beginning of the proposed baseline. Do not include the percent sign.

End Super Rate” - Cross slope super elevation rate to use when utilizing the user defined pavement widening. Specified in a percent format, represents the ending location of the widening line location. If no tapering is desired, set this value to equal the same value as the Begin Super Rate adhoc attribute. Must never end past the end of the proposed baseline. Do not include the percent sign.

CADD Support  |  GEOPAK Typicals  |  Top