Finalize Plan-in-Hand (70%) line and grade
Make the final changes to the line and grade:
- Incorporate comments from previous review (30% or 50%)
- Develop responses to (30% or 50%) review comments
- Finalize typical sections
- Finalize roadway geometric design
- Develop final wall alignments, profiles and cross-sections for structures and geotech to complete wall designs.
Step 1: Incorporate comments from previous review (30% or 50%)
Instructions | Resources | References |
|
|
|
Step 2: Develop responses to (30% or 50%) review comments
Instructions | Resources | References |
|
|
|
Step 3: Finalize typical sections
Instructions | Resources | References |
complete roadway templates (lane, shoulder, curve widening, foreslope, ditch, median, curbs, etc.) |
GEOPAK Adhoc Index |
|
AASHTO Green Book 2011 |
GEOPAK, Proposed Cross-Section Help |
|
|
GEOPAK, Cross Section Movie |
|
|
GEOPAK, Curve Widening: Introduction |
|
|
GEOPAK, Curve Widening: Methodology |
Curve widening, 2004 Green Book |
|
complete the typical section limits (clear zone, topsoil, seeding, clearing, construction) |
GEOPAK, Generate Slope Stake Limits |
|
|
update all misc typicals (superelevation, guardrail, paved ditch, curb, pullouts, parking areas, and subexcavation) |
GEOPAK Adhoc Index |
Maximum Relative Gradient Checker |
|
GEOPAK, Make the Superelevation Shapes (Automatic Mode) |
|
|
update typical section details (transitions, curve widening table, cut and fill slopes, etc.) |
GEOPAK Adhoc Index |
|
Sample Plans |
GEOPAK, Curve Widening: Draw Transition |
|
|
Step 4: Finalize roadway geometric design
Step 5: Develop final wall alignments, profiles and cross-sections for structures and geotech to complete wall designs.
Instructions | Resources | References |
For Structures and Geotech to complete their wall designs. |
|
|
|
Highway Design Process | Top