skip navigation links 
 
 Search Options 
Index | Site Map | FAQ | Facility Info | Reading Rm | New | Help | Glossary | Contact Us blue spacer  
secondary page banner Return to NRC Home Page
Combined License Applications for New Reactors
Bellefonte Units 3 & 4
Callaway Unit 2
Calvert Cliffs Unit 3
Comanche Peak Units 3 & 4
Fermi Unit 3
Grand Gulf Unit 3
Levy County Units 1 & 2
North Anna Unit 3
River Bend Station Unit 3
Shearon Harris Units 2 & 3
South Texas Project Units 3 & 4
Victoria County Station Units 1 & 2
Virgil C. Summer Units 2 & 3
Vogtle Units 3 & 4
William States Lee III Units 1 & 2

North Anna, Unit 3 Application

North Anna
Who:   Dominion Virginia Power (Dominion)

What:   Application for a combined license (COL) for an Economic Simplified Boiling Water Reactor (ESBWR) designated as North Anna Unit 3

When:   November 27, 2007 (date of application submittal)

Where:   Dominion's North Anna site near Richmond in Louisa County, Virginia

On this page:

The following links on this page are to documents in our Agencywide Documents Access and Management System (ADAMS). ADAMS documents are provided in either Adobe Portable Document Format (PDF) or Tagged Image File Format (TIFF). To obtain free viewers for displaying these formats, see our Plugins, Viewers, and Other Tools. If you have problems with viewing or printing documents from ADAMS, please contact the Public Document Room staff.

Reference Documents

To top of page

Applicant Documents

Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.

To top of page

Application Review Schedule

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 11/27/07 - A
Acceptance Review
Acceptance Review Start
12/03/07 - A
Docketing Decision Letter Issued/Acceptance Review Complete
01/28/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
02/27/08 - A
Safety Review
Phase 1 –Requests for Additional Information (RAIs) Issued to Applicant
08/29/08 - T
Phase 2 – SER with Open Items issued
04/20/09 - T
Phase 3 – ACRS Review of SER with Open Items Complete
07/28/09 - T
Phase 4 – Advanced SER with no Open Items Issued
03/10 - T
Phase 5 – ACRS Review of SER with no Open Items Complete
07/10 - T
Phase 6 – Final SER Issued
08/10 - T
Environmental Review
Phase 1 – Environmental impact statement (EIS) summary report issued
09/05/08 - T
Phase 2 – Draft EIS issued to EPA
12/08 - T
Phase 3 – Response to public comments on draft EIS issued
06/09 - T
Phase 4 – Final EIS issued to EPA
12/09 - T
Hearing
Commission or ASLB hold mandatory hearing
 
License
Commission decision on issuance of COL application
 

Information on Federal Register Notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found at NRC’s Website on Hearing Opportunities.

To top of page

NRC Documents

To top of page

Requests for Additional Information

Category RAI Date RAI Letter No. and Subject Applicant Response
Safety 03/20/08 RAI Letter No. 01 SRP Section 12.02 04/28/08
03/28/08 RAI Letter No. 02 SRP Section 2.3.2.3 04/25/08
04/01/08 RAI Letter No. 03 SRP Section 2.3.4.3 05/12/08
05/19/08 RAI Letter No. 04 SRP Sections 11.02, 11.04, and 11.05 06/30/08
06/04/08 RAI Letter No. 05 SRP Sections 17.04, 17.06, and 19 07/14/08
06/05/08 RAI Letter No. 06 SRP Sections 06.02.01, 06.02.04, 10.03.06, and 14.02 07/14/08
06/11/08 RAI Letter No. 07 SRP Sections 09.03.02, 11.02, 11.03, 11.04, 11.05, and 13.05.02.01 07/23/08
06/11/08 RAI Letter No. 08 SRP Section 09.05.01 07/23/08
06/13/08 RAI Letter No. 09 SRP Section 08.02 07/28/08
06/17/08 RAI Letter No. 10 SRP Sections 2.05.04 and 02.05.05 07/14/08
06/19/08 RAI Letter No. 11 SRP Sections 02.05.04, 08.03.02, 09.02.05, 12.02, 13.01.02-13.01.03 08/04/08
06/23/08 RAI Letter No. 12 SRP Sections 05.02.05, 10.04.05, and 14.02 08/07/08
06/24/08 RAI Letter No. 13 SRP Sections 09.01.04, 09.01.05, 09.05.04, and 17.5 08/04/08
06/27/08 RAI Letter No. 14 SRP Sections 03.07.01, 03.07.02, and 05.02.04 08/12/08
07/07/08 RAI Letter No. 15 SRP Section 13.03 Rescheduled
07/09/08 RAI Letter No. 16 SRP Sections 08.02, 09.05.04, and 12.02 08/21/08
07/15/08 RAI Letter No. 17 SRP Sections 02.01.02, 02.03.01, 02.03.02, 02.03.05, 09.02.01, and 14.02 08/28/08
07/18/08 RAI Letter No. 18 SRP Sections 13.03 and 14.03.10 Rescheduled
07/21/08 RAI Letter No. 19 SRP Sections 02.03.05, 03.09.03, 05.03.01, and 14.03.10 09/03/08
07/27/08 RAI Letter No. 20 SRP Sections 09.05.01, 11.04 09/04/08
07/28/08 RAI Letter No. 21 SRP Sections 05.02.01.01, 05.02.01.02, 13.01.01, 13.01.02-13.01.03, 13.02.01, 13.02.02, 13.05.02.01, and 14.02 09/11/08
08/01/08 RAI Letter No. 22 SRP Sections 03.09.06 and 03.11  
08/06/08 RAI Letter No. 23 SRP Sections 03.02.01 and 03.02.02  
08/08/08 RAI Letter No. 24 SRP Sections 02.04.12, 12.02, 12.03-12.04, 12.05, 14.02, and 14.03.03  
08/12/08 RAI Letter No. 25 SRP Sections 02.02.03, 03.05.01.05, 12.02, and 15.06.05  
08/19/08 RAI Letter No. 26 SRP Sections 02.04.13, 03.09.02, 05.03.02, and 11.05  
08/21/08 RAI Letter No. 27 SRP Sections 12.01 and 12.03-12.04  
08/21/08 RAI Letter No. 28 SRP Sections 01 and 02.04.02  
Environmental 06/18/08 RAI Letter Regarding the Environmental Review of the Combined License Application 07/17/08

To top of page

Public Meetings

Date Description
04/16/08 Environmental Scoping
12/13 - 14/07 Meeting regarding the technical content of the North Anna 3 COLA
11/29/07 North Anna 3 COLA Orientation
10/24/07 Public Outreach Meeting

To top of page

Contacts

Contacts for the North Anna COL Application
Safety Project Manager Thomas Kevern
Environmental Project Manager Alicia Williamson
Contact a Public Affairs Officer

To top of page



Privacy Policy | Site Disclaimer
Thursday, September 25, 2008