Combined License Applications for New Reactors
Bellefonte Units 3 & 4
Callaway Unit 2
Calvert Cliffs Unit 3
Comanche Peak Units 3 & 4
Fermi Unit 3
Grand Gulf Unit 3
Levy County Units 1 & 2
North Anna Unit 3
River Bend Station Unit 3
Shearon Harris Units 2 & 3
South Texas Project Units 3 & 4
Victoria County Station Units 1 & 2
Virgil C. Summer Units 2 & 3
Vogtle Units 3 & 4
William States Lee III Units 1 & 2

Vogtle Nuclear Site, Units 3 and 4 Application

Vogtle Nuclear Site
Who:   Southern Nuclear Operating Company (SNC)

What:   Application for a combined license (COL) for two Westinghouse Advanced Passive 1000 (AP1000) Pressurized Water Reactors (PWRs) designated as Vogtle Units 3 & 4.

When:   March 31, 2008 (date of application submittal)

Where:   SNC's Vogtle site near Augusta in Burke County, Georgia

On this page:

The following links on this page are to documents in our Agencywide Documents Access and Management System (ADAMS). ADAMS documents are provided in either Adobe Portable Document Format (PDF) or Tagged Image File Format (TIFF). To obtain free viewers for displaying these formats, see our Plugins, Viewers, and Other Tools. If you have problems with viewing or printing documents from ADAMS, please contact the Public Document Room staff.

Reference Documents

To top of page

Applicant Documents

Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.

SNC's transmittal letter for Vogtle Units 3 & 4 COLA (March 31, 2008)

To top of page

Application Review Schedule

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 03/31/08 - A
Acceptance Review
Acceptance Review Start
04/07/08 - A*
Docketing Decision Letter Issued/Acceptance Review Complete
05/30/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
06/27/08 - A
Safety Review
Phase 1 –Requests for Additional Information (RAIs) Issued to Applicant
01/14/09 - T
Phase 2 – SER with Open Items issued
07/22/09 - T
Phase 3 – ACRS Review of SER with Open Items Complete
11/20/09 - T
Phase 4 – Advanced SER with no Open Items Issued
07/10 - T
Phase 5 – ACRS Review of SER with no Open Items Complete
11/10 - T
Phase 6 – Final SER Issued
12/10 - T
Environmental Review
Phase 1 – Environmental impact statement (EIS) summary report issued
N/A**
Phase 2 – Draft EIS issued to EPA
04/17/09 - T
Phase 3 – Response to public comments on draft EIS issued
08/20/09 - T
Phase 4 – Final EIS issued to EPA
01/15/10 - T
Hearing
Commission or ASLB hold mandatory hearing
 
License
Commission decision on issuance of COL application
 

* Acceptance review start date is consistent with the guidance provided in RIS 2008-01.

**10 CFR 51.26(d) states that scoping is not required for a supplement to an EIS for a COL application that is submitted following a submittal of an early site permit application.

Information on Federal Register Notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found at NRC’s Website on Hearing Opportunities.

To top of page

NRC Documents

To top of page

Public Meetings

Date Description
07/17/08 Southern Nuclear - Vogtle Units 3 and 4 COL Application Meeting on Technical Content.
04/17/08 Southern Nuclear - Vogtle Units 3 and 4 COL Application Meeting on Technical Content.

To top of page

Contacts

Contacts for the Vogtle Nuclear Site COL Application
Safety Project Manager Christian Araguas
Sr. Environmental Project Manager Mark Notich