Home > Nuclear Reactors > New Reactors > Combined License Applications > Victoria County Station, Units 1 and 2 Application
Victoria County Station, Units 1 and 2 Application
|
Who: |
Exelon Nuclear Texas Holdings, LLC (Exelon)
|
What: |
Application for a combined license (COL) for two Economic Simplified Boiling Water Reactors (ESBWR) designated as Victoria County Station, Units 1 and 2
|
When: |
September 2008 (date of application submittal)
|
Where: |
Exelon's Victoria County Station site near Victoria City in Victoria County, Texas |
|
On this page:
The following links on this page are to documents in our Agencywide
Documents Access and Management System (ADAMS). ADAMS documents are provided
in either Adobe Portable Document Format (PDF) or Tagged Image File Format
(TIFF).
To obtain free viewers for displaying these formats, see our Plugins,
Viewers, and Other Tools. If you have problems
with viewing or printing documents from ADAMS, please contact the Public
Document
Room staff.
Reference Documents
Applicant Documents
Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.
Exelon transmittal letter for Victoria County Station COLA (September 2, 2008)
- Part 1 – General and Administrative Information
- Part 2 – Final Safety Analysis Report (FSAR)
- Part 3 – Environmental Report
- Part 4 – Technical Specifications
- Part 5 – Emergency Plan
- Part 6 – [Part not used in this application]
- Part 7 – Departures (Variances, Supplemental Information) from the ESBWR Design Control Document (DCD)
- Part 8 – [This Part contains safeguards information which is with-held from public availability]
- Part 9 – [This Part contains other information which is with-held from public availability]
- Part 10 – Tier 1/Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC)
- Part 11- Enclosures
Application Review Schedule
Key Milestones |
Completion Date Actual - A Target - T |
Application Tendered |
|
Acceptance Review |
Acceptance Review Start |
09/04/08 - A |
Docketing Decision Letter Issued/Acceptance Review Complete |
11/06/08 - T |
Review Schedule Established/Schedule Letter Issued to Applicant |
|
Safety Review |
Phase 1 –Requests for Additional Information (RAIs) Issued to Applicant |
|
Phase 2 – SER with Open Items issued |
|
Phase 3 – ACRS Review of SER with Open Items Complete |
|
Phase 4 – Advanced SER with no Open Items Issued |
|
Phase 5 – ACRS Review of SER with no Open Items Complete |
|
Phase 6 – Final SER Issued |
|
Environmental Review |
Phase 1 – Environmental impact statement (EIS) summary report issued |
|
Phase 2 – Draft EIS issued to EPA |
|
Phase 3 – Response to public comments on draft EIS issued |
|
Phase 4 – Final EIS issued to EPA |
|
Hearing |
Commission or ASLB hold mandatory hearing |
|
License |
Commission decision on issuance of COL application |
|
Information on Federal Register Notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found at NRC’s Website on Hearing Opportunities.
NRC Documents
Public Meetings
Date |
Description |
09/24/08 |
COLA Orientation/Technical Content Meeting
|
08/07/08 |
Public Outreach Meeting
|
Contacts
Contacts for the Victoria County Station COL Application |
Safety Project Manager |
Mark Tonacci |
Environmental Project Manager |
Paul Michalak |
Contact a Public Affairs Officer |
|