Fermi, Unit 3 Application
|
Who: |
Detroit Edison Company
|
What: |
Application for a combined license (COL) for an Economic Simplified Boiling Water Reactor (ESBWR) designated as Fermi Unit 3
|
When: |
September 2008 (date of application submittal)
|
Where: |
Detroit Edison Company's Fermi site near Newport City in Monroe County, Michigan |
|
On this page:
The following links on this page are to documents in our Agencywide
Documents Access and Management System (ADAMS). ADAMS documents are provided
in either Adobe Portable Document Format (PDF) or Tagged Image File Format
(TIFF).
To obtain free viewers for displaying these formats, see our Plugins,
Viewers, and Other Tools. If you have problems
with viewing or printing documents from ADAMS, please contact the Public
Document
Room staff.
Reference Documents
Applicant Documents
Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.
- Detroit Edison Company transmittal letter for Fermi Unit 3 COLA (September 18, 2008)
- Part 1 – General and Administrative Information
- Part 2 – Final Safety Analysis Report (FSAR)
- Part 3 – Environmental Report
- Part 4 – Technical Specifications
- Part 5 – Emergency Plan
- Part 6 – Part not used in this application
- Part 7 – Departures (Variances, Supplemental Information) from the ESBWR Design Control Document (DCD)
- Part 8 – Security Plan [This Part contains safeguards information which is withheld from public availability]
- Part 9 – Part not used in this application
- Part 10 – Tier 1/Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC)
Application Review Schedule
Key Milestones |
Completion Date Actual - A Target - T |
Application Tendered |
|
Acceptance Review |
Acceptance Review Start |
09/22/08 - T |
Docketing Decision Letter Issued/Acceptance Review Complete |
11/21/08 - T |
Review Schedule Established/Schedule Letter Issued to Applicant |
|
Safety Review |
Phase 1 –Requests for Additional Information (RAIs) Issued to Applicant |
|
Phase 2 – SER with Open Items issued |
|
Phase 3 – ACRS Review of SER with Open Items Complete |
|
Phase 4 – Advanced SER with no Open Items Issued |
|
Phase 5 – ACRS Review of SER with no Open Items Complete |
|
Phase 6 – Final SER Issued |
|
Environmental Review |
Phase 1 – Environmental impact statement (EIS) summary report issued |
|
Phase 2 – Draft EIS issued to EPA |
|
Phase 3 – Response to public comments on draft EIS issued |
|
Phase 4 – Final EIS issued to EPA |
|
Hearing |
Commission or ASLB hold mandatory hearing |
|
License |
Commission decision on issuance of COL application |
|
Information on Federal Register Notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found at NRC’s Website on Hearing Opportunities.
NRC Documents
Public Meetings
Date |
Description |
08/20/08 |
Public Outreach
|
Contacts
Contacts for the Fermi COL Application |