Brumlow Avenue Improvements
Project Information
The current Brumlow Avenue widening project will widen approximately 1400 linear feet of Brumlow by expanding the existing road to a four lane undivided road with a central turn lane in order to accommodate the TxDOT construction of dual left turns for SH 26 to north bound Brumlow. A future project, currently unfunded, will widen the remainder of Brumlow Avenue extending north to the existing roundabout at Continental Blvd.
Project Details
Engineering Consultant: |
Teague Nall and Perkins, Inc. |
Construction Contractor: |
TBD |
Current Budget: |
$745,000 ($200,000 to be reimbursed by Tarrant County) |
Future Budget: |
$3,500,000 est. |
Construction Start Date: |
2014 |
Anticipated Completion Date: |
TBD |
Southlake 2030 Comprehensive
Master Plan Item:
|
MT14 |
Status: |
City and franchise utility relocation is underway |
Staff Contact: |
Alex Ayala, P.E. |
Title: |
Civil Engineer |
Phone Number: |
(817) 748-8274 |
For a more detailed description of this project, please see the "
Public Works Capital Projects Update" quarterly report.
Return to the