Combined License Applications for New Reactors
Bellefonte Units 3 & 4
Callaway Unit 2
Calvert Cliffs Unit 3
Comanche Peak Units 3 & 4
Fermi Unit 3
Grand Gulf Unit 3
Levy County Units 1 & 2
North Anna Unit 3
River Bend Station Unit 3
Shearon Harris Units 2 & 3
South Texas Project Units 3 & 4
Victoria County Station Units 1 & 2
Virgil C. Summer Units 2 & 3
Vogtle Units 3 & 4
William States Lee III Units 1 & 2

Calvert Cliffs, Unit 3 Application

Calvert Cliffs
Who:   Calvert Cliffs 3 Nuclear Project, LLC. and UniStar Nuclear Operating Services, LLC.

What:   Application for a combined license (COL) for an AREVA U.S. Evolutionary Power Reactor (EPR) designated as Calvert Cliffs Nuclear Power Plant Unit 3

When:   July 13, 2007 (date of initial application of Part 1 which included the Environmental Report)

Where:   Unistar's Calvert Cliffs site near Lusby in Calvert County, Maryland

On this page:

The following links on this page are to documents in our Agencywide Documents Access and Management System (ADAMS). ADAMS documents are provided in either Adobe Portable Document Format (PDF) or Tagged Image File Format (TIFF). To obtain free viewers for displaying these formats, see our Plugins, Viewers, and Other Tools. If you have problems with viewing or printing documents from ADAMS, please contact the Public Document Room staff.

Reference Documents

To top of page

Applicant Documents

Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.

To top of page

Application Review Schedule

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 07/13/07 &
03/14/08 - A
Acceptance Review
Acceptance Review Start
07/16/07 &
04/01/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
01/25/08 &
06/03/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
07/24/08 - T
Safety Review
Phase 1 –Requests for Additional Information (RAIs) Issued to Applicant
06/16/09 - T
Phase 2 – SER with Open Items issued
02/17/10 - T
Phase 3 – ACRS Review of SER with Open Items Complete
05/10 - T
Phase 4 – Advanced SER with no Open Items Issued
02/11 - T
Phase 5 – ACRS Review of SER with no Open Items Complete
06/11 - T
Phase 6 – Final SER Issued
08/11 - T
Environmental Review
Phase 1 – Environmental impact statement (EIS) summary report issued
10/06/08 - T
Phase 2 – Draft EIS issued to EPA
02/09/09 - T
Phase 3 – Response to public comments on draft EIS issued
11/10/09 - T
Phase 4 – Final EIS issued to EPA
03/01/10 - T
Hearing
Commission or ASLB hold mandatory hearing
 
License
Commission decision on issuance of COL application
 

Information on Federal Register Notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found at NRC’s Website on Hearing Opportunities.

To top of page

NRC Documents

To top of page

Requests for Additional Information

Category RAI Date RAI Letter No. and Subject Applicant Response
Safety 06/27/08 RAI Letter No. 1, 2, 3, 4, 5 FSAR Ch 2 04/25/08
07/17/08 RAI Letter No. 6 COLA Part 1 08/04/08
08/11/08 RAI Letter No. 7 CQVP 769 09/10/08
Environmental 05/13/08 Updated Response to Calvert Cliffs Nuclear Power Plant, Unit 3, Environmental Request for Additional Information 09/19/08
05/13/08 Submittal of Response to Requests for Additional Information for the Calvert Cliffs Nuclear Power Plant, Unit 3 06/12/08

To top of page

Public Meetings

Date Description
03/19/08 Public Environmental Scoping Meeting
08/14/07 Public Outreach

To top of page

Contacts

Contacts for the Calvert Cliffs COL Application
Safety Project Manager John Rycyna
Environmental Project Manager Thomas Fredrichs
Laura Quinn
Contact a Public Affairs Officer