Home > Nuclear Reactors > New Reactors > Combined License Applications > Calvert Cliffs, Unit 3 Application
Calvert Cliffs, Unit 3 Application
|
Who: |
Calvert Cliffs 3 Nuclear Project, LLC. and UniStar Nuclear Operating Services, LLC.
|
What: |
Application for a combined license (COL) for an AREVA U.S. Evolutionary Power Reactor (EPR) designated as Calvert Cliffs Nuclear Power Plant Unit 3
|
When: |
July 13, 2007 (date of initial application of Part 1 which included the Environmental Report)
|
Where: |
Unistar's Calvert Cliffs site near Lusby in Calvert County, Maryland |
|
On this page:
The following links on this page are to documents in our Agencywide
Documents Access and Management System (ADAMS). ADAMS documents are provided
in either Adobe Portable Document Format (PDF) or Tagged Image File Format
(TIFF).
To obtain free viewers for displaying these formats, see our Plugins,
Viewers, and Other Tools. If you have problems
with viewing or printing documents from ADAMS, please contact the Public
Document
Room staff.
Reference Documents
Applicant Documents
Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.
- Submittal of the Published UniStar Nuclear Topical Report "Quality Assurance Program Description," Revision 1 (September 11, 2008)
- Submittal of Corrected Revision 3 to the Combined License Application for the Calvert Cliffs Nuclear Power Plant, Unit 3 (August 20, 2008)
- Submittal of Supplemental Information - Design Parameters for Category I Structure Foundation Dimensions (August 19, 2008)
- Submittal of Supplemental Information - Seismic Lateral Earth Pressure Analysis (August 18, 2008)
- Submittal of Supplemental Information, Updated Information for Ground Motion Response Spectrum (July 31, 2008)
- Submittal of Supplemental Information, Detailed Ground Water Dewatering Plan (June 20, 2008)
- Submittal of Supplemental Information, Seismic Catalog (May 30, 2008)
- May 15, 2008 supplement (Emergency Plan (Part 5) and State and Local Emergency Plans (Part 11H)) [This Part contains information which is withheld from public availability.]
- March 14, 2008 supplement (Information Associated with Soil Hazard Curves at Additional Annual Exceedence Frequencies)
- UniStar transmittal letter for Calvert Cliffs Unit 3 COLA, Part II ( March 14, 2008)
- Part 1 – General and Administrative Information
- Part 2 – Final Safety Analysis Report (FSAR)
- Part 3 – Environmental Report
- Part 4 – Technical Specifications
- Part 5 – Emergency Plan
- Part 6 – Limited Work Authorization (LWA) [Part not used in this application]
- Part 7 – DCD Departures
- Part 8 – Security Plan [This Part contains safeguards information which is withheld from public availability]
- Part 9 – Proprietary and Sensitive Unclassified Non-Safeguards Information [This Part contains information which is withheld from public availability.]
- Part 10 – Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) and ITAAC Closure
- Part 11A – Quality Assurance Program Description
- Part 11B – AREVA Design Control Document
- Part 11C – DCD Supplements
- Part 11D – NEI Reference Documents [This Part contains information which is withheld from public availability.]
- Part 11E – Process Control Program
- Part 11F – Offsite Dose Calculation Manual
- Part 11G – Fuel Racks Report
- Part 11H – State and Local Emergency Plans [This Part contains information which is withheld from public availability.]
- March 3, 2008 supplement (Electronic Data Associated with the Probabilistic Seismic Hazards Analysis)
- January 14, 2008 revision to partial COL application
- December 14, 2007 revision to partial COL application
- October 30, 2007 response to acceptance review letter
- September 11, 2007 supplement (General Information Binder)
- August 2, 2007 supplement (ER Chapters 4 - 10)
- Calvert Cliffs COLA, Part I, July 13 and July 16, 2007 (FSAR Chapter 2, ER Chapters 1 - 3, Administrative Information)
Application Review Schedule
Key Milestones |
Completion Date Actual - A Target - T |
Application Tendered |
07/13/07 & 03/14/08 - A |
Acceptance Review |
Acceptance Review Start |
07/16/07 & 04/01/08 - A |
Docketing Decision Letter Issued/Acceptance Review Complete |
01/25/08 & 06/03/08 - A |
Review Schedule Established/Schedule Letter Issued to Applicant |
07/24/08 - T |
Safety Review |
Phase 1 –Requests for Additional Information (RAIs) Issued to Applicant |
06/16/09 - T |
Phase 2 – SER with Open Items issued |
02/17/10 - T |
Phase 3 – ACRS Review of SER with Open Items Complete |
05/10 - T |
Phase 4 – Advanced SER with no Open Items Issued |
02/11 - T |
Phase 5 – ACRS Review of SER with no Open Items Complete |
06/11 - T |
Phase 6 – Final SER Issued |
08/11 - T |
Environmental Review |
Phase 1 – Environmental impact statement (EIS) summary report issued |
10/06/08 - T |
Phase 2 – Draft EIS issued to EPA |
02/09/09 - T |
Phase 3 – Response to public comments on draft EIS issued |
11/10/09 - T |
Phase 4 – Final EIS issued to EPA |
03/01/10 - T |
Hearing |
Commission or ASLB hold mandatory hearing |
|
License |
Commission decision on issuance of COL application |
|
Information on Federal Register Notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found at NRC’s Website on Hearing Opportunities.
NRC Documents
Requests for Additional Information
Category |
RAI Date |
RAI Letter No. and Subject |
Applicant Response |
Safety |
06/27/08 |
RAI Letter No. 1, 2, 3, 4, 5 FSAR Ch 2
|
04/25/08
|
07/17/08 |
RAI Letter No. 6 COLA Part 1
|
08/04/08
|
08/11/08 |
RAI Letter No. 7 CQVP 769
|
09/10/08
|
Environmental |
05/13/08 |
Updated Response to Calvert Cliffs Nuclear Power Plant, Unit 3, Environmental Request for Additional Information
|
09/19/08
|
05/13/08 |
Submittal of Response to Requests for Additional Information for the Calvert Cliffs Nuclear Power Plant, Unit 3
|
06/12/08
|
Public Meetings
Date |
Description |
03/19/08 |
Public Environmental Scoping Meeting
|
08/14/07 |
Public Outreach
|
Contacts
Contacts for the Calvert Cliffs COL Application |
Safety Project Manager |
John Rycyna |
Environmental Project Manager |
Thomas Fredrichs Laura Quinn |
Contact a Public Affairs Officer |
|