Schedule of Proposed NEPA Actions

NOTE: This report contains the most accurate information available at time of publication.

Browse by Office:

 

Regional Office

<RO> <DKAO> <ECAO> <MTAO> <NKAO> <OTAO> <WYAO> <Regional Archive> <Back to Top>

Project Name Project Location NEPA Phase Dates of Phase Project Sponsor and/or Partners Public Contact
Crow MR&I Water System (EA) Crow Indian Reservation, Montana Draft EA Now accepting public comments Crow Tribe, Water Resources Department Christina Gomer
(406) 247-7753
cmgomer@usbr.gov

Additional Information: Public Law 111-291 authorized funding to construction a MR&I water system on the Crow Indian Reservation. The proposed water supply system would include facilities to collect, treat, and distribute water to end users throughout the Reservation. The system would provide potable water to communities and rural residents of the Crow Reservation and is designed to meet both current and future water needs for domenstic, commercial, and industrial uses. For more information visit: www.usbr.gov/gp/nepa/cmri/index.html

 

 

Dakotas Area Office

<RO> <DKAO> <ECAO> <MTAO> <NKAO> <OTAO> <WYAO> <Regional Archive> <Back to Top>

Project Name Project Location NEPA Phase Dates of Phase Project Sponsor and/or Partners Public Contact
Expansion of the South Central Water District into South Kidder County Logan and Kidder County ND Env. Review / Cat. Exclus. Checklist Scoping July 1, 2015 Garrison Diversion Conservancy District Grant MRI Program/SCWD

Kelly McPhillips
(701) 221-1287
kmcphillips@usbr.gov

Additional Information: Reclamation is conducting an environmental review tiered from the SCWD-Emmons County Phase 3 EA. If no significant environmental effects are identified, Reclamation would sign a Finding of No New Significant Impact. Project work includes 150 miles of pipe construction and a single booster pump, and would serve 4 communities and approximately 350 rural customers.
 
Northwest Area Water Supply Project (EIS) Northwest North Dakota Final Supplemental EIS/ Draft ROD Comments on draft SEIS under review; Record of Decision anticipated in July 2015 State of North Dakota is the project sponsor and cooperating agency. Cooperating agencies include: EPA; US Army Corps of Engineers; Garrison Diversion Conservancy District; and the City of Minot, ND. Alicia Waters
(701) 221-1206
awaters@usbr.gov
Additional Information: This SEIS is being prepared in response to a District Court order remand of previous NEPA completed. The proposed action is to complete the construction of this municipal, rural and industrial water supply project which began in 2002 and then was challenged by the Province of Manitoba, Canada in the U.S. District Court. The communities and rural water systems within northwestern North Dakota face water quality and/or quantity concerns. The alternatives are being evaluated which would provide a reliable, high quality water supply for this area of North Dakota.
 

 

Eastern Colorado Area Office

<RO> <DKAO> <ECAO> <MTAO> <NKAO> <OTAO> <WYAO> <Regional Archive> <Back to Top>

Project Name Project Location NEPA Phase Dates of Phase Project Sponsor and/or Partners Public Contact
Arkansas Valley Conduit Long-Term Excess Capacity Master Contract (EIS) Lower Arkansas Valley Complete: Record of Decision issued February 27, 2014 Lower Arkansas Water Entities

Signe Snortland
(970) 962-4338
jsnortland@usbr.gov

Project Activities: Ongoing please visit the AVCEIS Web site.

Additional Information: www.usbr.gov/avceis/

 
Black Hills Corporation Pueblo Reservoir Substation (EA) Pueblo Reservoir, Pueblo, Colorado EA and FONSI Complete April 2014 Black Hills Corporation

Signe Snortland
(970) 962-4338
jsnortland@usbr.gov

Project Activities: Complete

Additional Information: Black Hills Corporation Pueblo Reservoir Substation

 
Colorado Springs - Southern Delivery System (EIS) Pueblo-Colorado Springs, Colorado Complete: Record of Decision issued March 2009 Colorado Springs Utilities, City of Fountain, Security Water District, and City of Pueblo West

Signe Snortland
(970) 962-4338
jsnortland@usbr.gov

Project Activities: Complete

Additional Information: Southern Delivery System

 
Estes Park Transit Facility Parking Structure Above Lake Estes, Estes Park, Colorado Draft EA January 2016 Town of Estes Park

Terence Stroh
970-962-4369
tstroh@usbr.gov

Project Activities: Draft EA distributed for public comment.

Additional Information: Estes Park Transit Facility Parking Structure

 
Granby Hydropower Project Grand County, Colorado EA and FONSI completed March 13, 2015 Northern Colorado Water Conservancy District

Signe Snortland
(970) 962-4338
jsnortland@usbr.gov

Project Activities: Final EA & FONSI are now available.

Additional Information: Granby Hydropower Project

 
Horsetooth Reservoir Admin and Maintenance Facilities Larimer County, Colorado EA and FONSI completed October 2015 Larimer County Parks Terence Stroh
970-962-4369
tstroh@usbr.gov
or
Mark Caughlan
Larimer County Parks
970-498-5600
mcaughlan@larimer.org

Project Activities: Final EA & FONSI are now available.

Additional Information: Horsetooth Reservoir Admin and Maintenance Facilities

 
Pueblo Hydropower Project (EA) Pueblo Dam, Pueblo, Colorado Draft EA January 2016 Southeastern Colorado Water Conservation District, Colorado Springs Utilities, and Board of Water Work of Pueblo

Terence Stroh
970-962-4369
tstroh@usbr.gov

Project Activities: Draft EA distributed for public comment.

Additional Information: Pueblo Hydropower Project

 
Pueblo Resource Management Plan (EA) Pueblo Reservoir and Lake Pueblo State Park, Pueblo, Colorado Drafting EA 2014 Colorado Parks & Wildlife

Signe Snortland
(970) 962-4338
jsnortland@usbr.gov

Project Activities: Drafting EA

Additional Information: Pueblo Resource Management Plan

 
Ruedi Repayment Contracts for 19585 Acre-Feet Colorado West Slope Counties Final EA and FONSI complete. July 2013 Colorado West Slope Counties Signe Snortland
(970) 962-4338
jsnortland@usbr.gov

Project Activities: Final EA & FONSI are now available.

Additional Information: Ruedi Repayment Contracts for 19585 Acre-Feet

 
Water Users Commitment to Provide 10,825 AF to the 15 Mile Reach CO R. Basin Complete: Final EA/FONSI March 2012 Upper Colorado River Basin Signe Snortland
(970) 962-4338
jsnortland@usbr.gov

Project Activities: Final EA and FONSI are now available.

Additional Information: Water Users Commitment to Provide 10825 AF

 
Windy Gap Firming Project (EIS) Colorado and South Platte River Basins, Colorado Final EIS

Supplemental Information Report and related errata.
Fall 2011

November 2012
Municipal Subdistrict of the Northern Colorado Water Conservancy District
Cooperating agencies: Corps of Engineers, Western Area Power Administration, Grand County
Signe Snortland
(970) 962-4338
jsnortland@usbr.gov

Project Activities: Supplemental Information Report and related errata now available.

Additional Information: Windy Gap Firming Project EIS

 

 

Montana Area Office

<RO> <DKAO> <ECAO> <MTAO> <NKAO> <OTAO> <WYAO> <Regional Archive> <Back to Top>

Project Name Project Location NEPA Phase Dates of Phase Project Sponsor and/or Partners Public Contact
Lower Yellowstone Intake Diversion Dam Modifications (EA) Intake, Montana Final Supplemental EA/FONSI January 2015 Corps of Engineers (Co-Lead); US Fish and Wildlife Service; Montana Fish, Wildlife and Parks; Lower Yellowstone Irrigation Project David Trimpe
(406) 247-7668
dtrimpe@usbr.gov

Additional Information: The Lower Yellowstone Intake Project consists of improving fish passage for pallid sturgeon at Intake Dam on the Yellowstone River. For more information visit: www.usbr.gov/gp/mtao/loweryellowstone/index.html

 
St. Mary ESA Modifications (EA) Babb, Montana Draft EA Drafting US Fish and Wildlife Service; National Park Service; Blackfeet Tribe; Milk River Joint Board of Control Justin Kucera
(406) 247-7330
jkucera@usbr.gov

Additional Information: Several chapters of the draft Environmental Assessment are completed. Progress on the draft EA is expected to resume when engineering design (fish screen and passage) and ESA compliance details are coordinated.

 
Canyon Ferry Water & Sewer District (EA) Canyon Ferry, Montana Draft EA November 2014 East & West Canyon Ferry Water and Sewer District Justin Kucera
(406) 247-7330
jkucera@usbr.gov
Additional Information: Land transfer proposed to provide land for community based septic systems. Awaiting information from project sponsors to establish need.
 
Helena Valley Irrigation District – Lease of Power Privilege – Final Environmental Assessment and Finding of No Significant Impact Lewis and Clark County, Montana, approximately 10.0 miles southeast of the town of Helena, Montana Final EA and FONSI December 2015 Helena Valley Irrigation District Justin Kucera
(406) 247-7330
jkucera@usbr.gov

Project Activities: Final EA and FONSI now available.

Additional Information: Helena Valley Irrigation District – Lease of Power Privilege

 

 

Nebraska-Kansas Area Office

<RO> <DKAO> <ECAO> <MTAO> <NKAO> <OTAO> <WYAO> <Regional Archive> <Back to Top>

Project Name Project Location NEPA Phase Dates of Phase Project Sponsor and/or Partners Public Contact
Box Butte Dam Safety Repairs (EA) Box Butte Dam, Nebraska Final EA/FONSI Final EA Mirage Flats Irrigation District Lucas Milheiser
(308) 345-8323
lmilheiser@usbr.gov

Additional Information: Final EA and FONSI available on the Box Butte Dam Safety Repairs page. Selected alternative includes repair of toe drain and filter system. Construction proposed to begin in Fall of 2017.

 

 

Oklahoma-Texas Area Office

<RO> <DKAO> <ECAO> <MTAO> <NKAO> <OTAO> <WYAO> <Regional Archive> <Back to Top>

Project Name Project Location NEPA Phase Dates of Phase Project Sponsor and/or Partners Public Contact
Altus Safety of Dams (EA) W.C. Altus Project, Oklahoma Draft EA July 2015 Bureau of Reclamation Precious Braggs
(405) 470-4825
pbraggs@usbr.gov

Additional Information: Reclamation is proposing repairs to several dikes at Atlus Dam and Reservoir in order to reduce the probability of failure, reduce uncontrolled releases from Altus Reservoir, and reduce public safety risks. For more information, visit: www.usbr.gov/gp/otao/altus/index.html

 

 

Wyoming Area Office

<RO> <DKAO> <ECAO> <MTAO> <NKAO> <OTAO> <WYAO> <Regional Archive> <Back to Top>

Project Name Project Location NEPA Phase Dates of Phase Project Sponsor and/or Partners Public Contact
Boysen Reservoir Resource Management Plan (EA) Fremont County, Wyoming Final Public Review and Comment June 2015 Wyoming State Parks George Neuberger
(307) 261-5675
gneuberger@usbr.gov
and
Laura Schwieger
(307) 261-5664
lschwieger@usbr.gov
Additional Information: Wyoming State Parks, Reclamation's managing partner for Boysen Reservoir, has contracted for the preparation of a Recreation Master Plan / Resource Management Plan and Environmental Assessment. Document is undergoing final public review and comment. For more information, visit http://boysenstateparkmasterplan.com

 

 

Regional Archive (NEPA Complete)

<RO> <DKAO> <ECAO> <MTAO> <NKAO> <OTAO> <WYAO> <Regional Archive> <Back to Top>

Project Name Project Location NEPA Phase Dates of Phase Project Sponsor and/or Partners Public Contact
Box Butte Dam: Safety of Dams Corrective Actions Box Butte Dam, Dawes County, Nebraska Draft EA January 15-February 12 Bureau of Reclamation and Mirage Flats Irrigation District Christina Gomer
(406) 247-7753
cmgomer@usbr.gov
or
Lucas Milheiser
(308) 345-8323
lmilheiser@usbr.gov

Additional Information: Reclamation is seeking public review and comment on the Draft EA. The proposed action includes repair of toe drain, filter system, and spillway. Construction is proposed to begin in 2017.

 
Bull Lake Dam Safety of Dams Corrective Action (EA) Wind River Indian Reservation, Wyoming Final EA/FONSI May 2014 Reclamation's Safety of Dams Office; Midvale Irrigation District

Lyle Myler
(307) 261-5676
lmyler@usbr.gov
and
Laura Schwieger
(307) 261-5664
lschwieger@usbr.gov

Additional Information: Bull Lake Dam has been inspected for safety conditions and needs repair work to the spillway structure. The project would modify the spillway portion of the dam so that the dam could be safely operated under full reservoir conditions.

 
Central MT Rural Water (EA) Canyon Ferry, Montana Final EA/FONSI May 2014 Bureau of Reclamation

Justin Kucera
(406) 247-7330
jkucera@usbr.gov

Additional Information: EA Completed. Signed a non-decisional FONSI while the project works through the authorization process.

 
Construction of the New South West Pipeline Water Treatment Plant (EA) Dickinson, ND Final EA/FONSI March 2015 Garrison Diversion Conservancy District; North Dakota State Water Commission Kelly McPhillips
(701) 221-1287
kmcphillips@usbr.gov

Additional Information: A new water treatment plant in Dickinson is being proposed for The South West Pipeline Project. The plant would supply potable water with the potential to serve the South West Pipeline Project area.

Additional Information: Construction of the New South West Pipeline Water Treatment Plant

 
Contract Renewal for Jacobsen and Hamilton (EA) Washakie County, Wyoming Final EA/FONSI November 2014 Independent Water Users Brock Merrill
(307) 261-5649
bemerrill@usbr.gov
and
Laura Schwieger
(307) 261-5664
lschwieger@usbr.gov
Additional Information: This action is for renewal of an existing long-term water service contract. Read the Final EA/FONSI.
 
Contract Renewal for Robbins (EA) Hot Springs County, Wyoming Final EA/FONSI November 2014 Independent Water Users Brock Merrill
(307) 261-5649
bemerrill@usbr.gov
and
Laura Schwieger
(307) 261-5664
lschwieger@usbr.gov
Additional Information: This action is for renewal of an existing long-term water service contract. Read the Final EA/FONSI.
 
Crossing Right of Way Through Fish and Wildlife Service Refuge Lands to Connect the Spirit Lake Rural Water Distribution Line to the School Tank (EA) Benson County, ND FONSI/ Decision Notice October 2014 Devils Lake Wetland Management District; Fish and Wildlife Service; Spirit Lake Rural Water System Kelly McPhillips
(701) 221-1287
kmcphillips@usbr.gov
Additional Information: A water distribution line from the Spirit Lake Rural Water System to serve a local water use near Devils Lake is being evaluated. Reclamation is no longer involved in the project. The U.S. Fish and Wildlife Service has the lead.
 
Crow Irrigation Project Rehabilitation and Improvement (EA) Crow Indian Reservation, Montana Final EA/FONSI June 2015 Crow Tribe Water Resources Department; Bureau of Indian Affairs Christina Gomer
(406) 247-7753
cmgomer@usbr.gov

Additional Information: Public Law 111-291 authorized funding to repair and rehabilitate the Crow Irrigation Project. The Crow Tribe has contracted with Bartlett & West to prepare the Programmatic Environmental Assessment (EA) and the Master Engineering Plan. The Final EA and Finding of No Significant Impact/Decision Document are now available online. For more information visit: www.usbr.gov/gp/nepa/cip/index.html

 
Crow MR&I Water System - Pilot Water Treatment Plant (EA) Crow Indian Reservation, Montana Final EA/FONSI July 2015 Crow Tribe, Water Resources Department Christina Gomer
(406) 247-7753
cmgomer@usbr.gov

Additional Information: Public Law 111-291 authorized funding to construct a MR&I water system on the Crow Indian Reservation. In order to facilitate the construction and design of the MR&I water system, the Crow Tribe conducted a three month pilot plant study. The Crow Tribe contracted with Bartlett & West to prepare an Environmental Assessment to evaluate the proposed pilot study. The Final EA and FONSI is available. For more information visit: www.usbr.gov/gp/nepa/cmri/index.html

 
Goose Bay Modernization (EA) Canyon Ferry, Montana Final EA/FONSI May 2014 Bureau of Reclamation Justin Kucera
(406) 247-7330
jkucera@usbr.gov
Additional Information: The Goose Bay Marina on Canyon Ferry Reservoir is being modernized and improved for recreation uses and services. For more information visit: www.usbr.gov/gp/mtao/canyonferry/goosebay/
 
Nelson Reservoir Safety of Dams Corrective Action (EA) Malta, Montana Final EA/FONSI January 2014 Malta Irrigation District Justin Kucera
(406) 247-7330
jkucera@usbr.gov

Additional Information: Nelson Reservoir has a series of dikes that were inspected for safety reasons, two of which were found in need of repair. Continued levels of water seepage through the dikes could lead to failure and result in property and resource damage. The project involves reconstructing the dikes to control water seepage and provide proper drainage.

 
Shoreline Protection and Aquatic Habitat Restoration Project at Medicine Creek State Recreation Area (EA) Cambridge, Nebraska Final EA/FONSI April 2014 Nebraska Game and Parks Commission Andrea Severson
(308) 345-1028
aseverson@usbr.gov

Additional Information: The EA can be accessed at www.usbr.gov/gp/nkao/nepa/med_creek_ea_fonsi.pdf.

 
Last Updated: 6/20/16