Programming/Site Investigation |
June 2008 - February 2009 |
Program Redefinement and Concept Development |
October 2008 - March 2009 |
Schematic Design |
January 2009 – June 2009 |
Schematic Design Drawings |
June 2009 |
Design Development |
June 2009 – October 2009 |
Cost Estimate |
September 2009 – October 2009 |
Construction Documents |
July 2009 – February 2010 |
Demolition of Kendall Hall |
September 2009 – December 2009 |
Groundbreaking |
December 2009 |
Construction |
December 2009 – June 2011 |
Construction Complete/Occupancy |
July 2011 |