Skip Navigation
 
Federal Energy Regulatory Commission



Industries Electric Industry Activities
  Order No. 1000 - Transmission Planning and Cost Allocation

 
Text Size small medium large
Order No. 1000 Interregional Compliance Orders

Note: All links are to PDF’s
DLO= Delagated Letter Order

Region Round Lead Docket No. Date Issued Cite
ISO-NE/NYISO/PJM One ER13-1957-000 05/14/15 151 FERC ¶ 61,133
  Two ER13-1957-001 11/19/15 DLO
MISO/PJM One ER13-1944-000 12/18/14 149 FERC ¶ 61,250
  Two ER13-1944-001 04/05/16 155 FERC ¶ 61,008
  Three ER13-1944-003 10/28/16 157 FERC ¶ 61,065
MISO/SPP One ER13-1937-000 08/20/15 150 FERC ¶ 61,093
  Two ER13-1937-002 02/16/16 154 FERC ¶ 61,075
  Three ER13-1937-003 04/06/16 DLO
SERTP/Florida One ER13-1922-000 01/23/15 150 FERC ¶ 61,044
  Two ER13-1922-001 07/30/15 DLO
SERTP/MISO One ER13-1923-000 01/23/15 150 FERC ¶ 61,045
  Two ER13-1923-001 11/25/15 153 FERC ¶ 61,247
  Three ER13-1923-003 03/03/16 154 FERC ¶ 61,227
  Four ER13-1940-010 04/20/16 DLO
SERTP/PJM One ER13-1927-000 01/23/15 150 FERC ¶ 61,046
  Two ER13-1927-001 09/21/15 152 FERC ¶ 61,122
  Three ER13-1928-007 12/16/15 DLO
SERTP/South Carolina One ER13-1922-000 01/23/15 150 FERC ¶ 61,044
  Two ER13-1928-002 07/30/15 DLO
SERTP/SPP One ER13-1939-000 03/19/15 150 FERC ¶ 61,210
  Two ER13-1939-001 08/31/15 152 FERC ¶ 61,172
  Three (Part 1) ER13-1928-006 10/09/15 DLO
  Three (Part 2) ER13-1939-002 02/02/16 154 FERC ¶ 61,076
  Four ER13-1939-003 04/12/16 DLO
Western One ER13-1470-000 12/18/14 149 FERC ¶ 61,247
  Two ER13-1470-001 06/01/15 151 FERC ¶ 61,189