Crystal River - License Renewal Application
On this page:
- Application Information
- License Renewal Review Schedule
- Environmental Impact Statement
- Safety Evaluation Report
- Public Involvement
- Project Managers for Crystal River
Application Information:
License Renewal Review Schedule*
*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.
Milestones | Schedule Date | Actual Date |
---|---|---|
Receive license renewal application (LRA) | 12/18/08 | 12/18/08 |
Publish Federal Register Notice (FRN) - LRA availability | 02/04/09 | 02/04/09 |
Publish FRN - acceptance and opportunity for hearing | 03/09/09 | 03/09/09 |
Publish FRN - environmental scoping meeting | 03/30/09 | 03/30/09 |
Audit – Environmental | 07/20/09- 07/24/09 |
7/20/09- 07/24/09 |
Public Meeting - License Renewal Overview and Environmental Scoping meeting | 04/16/09 | 04/16/09 |
Deadline for filing hearing requests and petitions for intervention | 05/08/09 | 05/08/09 |
Environmental scoping period ends | 06/08/09 | 06/08/09 |
Audit – Scoping & Screening Audit Methodology | 06/22/09- 06/26/09 |
06/22/09- 06/26/09 |
Audit – Aging Management Programs | 07/13/09- 07/17/09 |
07/13/09- 07/17/09 |
Issue safety evaluation report (SER) with open items | 12/10/10 | 12/14/10 |
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting | 01/12/11 | 01/12/11 |
Issue draft supplemental environmental impact statement (SEIS) | 05/11 | 05/26/11 |
Public Meeting - draft SEIS meeting | 06/28/11 | 06/28/11 |
End of draft SEIS comment period | 07/25/11 | 07/25/11 |
Issue final SEIS | TBD | |
Issue final SER | TBD | |
ACRS Subcommittee meeting | TBD | |
ACRS Full Committee meeting | TBD | |
Decision – Director, Office of Nuclear Reactor Regulation | TBD |
* The review schedule was revised as described in the letters below:
- Revised Schedule Letter (June 10, 2011)
- Revised Schedule Letter (February 17, 2011)
- Revised Schedule Letter (November 5, 2010)
- Revised Schedule Letter (August 12, 2010)
- Revised Schedule Letter (January 25, 2010)
- Original Schedule Letter (May 22, 2009)
Environmental Impact Statement
NUREG-1437, “Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Crystal River Unit 3 Nuclear Generating Plant (NUREG-1437, Supplement 44) Draft Report for Comment,” was published in May 2011. This supplement documents the NRC staff’s review of the environmental issues at Crystal River Unit 3 Nuclear Generating Plant regarding the Florida Power Corporation application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the NRC staff’s analysis that considers and weighs the environmental effects of the proposed action (license renewal), the environmental impacts of alternatives to the proposed action, and potential mitigative measures for reducing or avoiding adverse impacts. It also includes the NRC staff’s preliminary recommendation regarding the proposed action.
Safety Evaluation Report
The NRC staff reviewed the Crystal River Unit 3 Nuclear Generating Plant license renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its preliminary findings. The document was issued on December 14, 2010, as "Safety Evaluation Report with Open Items Related to the License Renewal of Crystal River Unit 3 Nuclear Generating Plant."
Public Involvement
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
Public Meetings Related to Environmental Review
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Date | Description |
---|---|
06/28/11 | Meeting to discuss the preliminary results of the environmental review for Crystal River Unit 3. |
Project Managers for Crystal River
Crystal River Station PMs | |
---|---|
License Renewal (Safety) | John Daily |
License Renewal (Environmental) | Elaine Keegan |
Lead Power Plant | Farideh Saba |