Phase 2 (2013-2014)

 

Overall project map

Overall project map 2010-2014

Phase 2 construction activities include:

  • Finish replacing asphalt on Field Road
  • Reconstruction of the Alexander Avenue & W. Bunker Road (Danes Drive) intersection
  • Reconstruction of wetlands and removal of Fort Cronkhite Dirt Overflow Lot
  • Restoring the Fort Cronkhite Annex Parade Ground Quarry to its pre-quarry original conditions to better match the landscape.
  • Construction of the Smith Road Parking Lot and Fort Cronkhite Parking Lot
  • Resurfacing, restoration, and rehabilitation of Old Bunker Road, Mitchell Road, and Bunker Road (intersection of Old Bunker Road/ Mitchell Road to the Baker-Barry Tunnel)
  • Construction of the Fort Cronkhite Annex Parking Lot near the Marine Mammal Center
  • Guardrail replacement at East Bunker Road 

Please check back for more information regarding Phase 2 construction including closures and delays.