Timeline
In This Section
Federal Agencies receiving Recovery funds have met the dates designated for reporting the distribution and implementation of those funds. In August, the Council of Economic Advisors begins quarterly reporting, and in October recipients of Recovery funds begin reporting the distribution of Recovery funds.
Date | Event |
|
---|---|---|
February 13, 2009 | H.R. 1 passed by the House of Representatives |
|
February 13, 2009 | H.R. 1 passed by the Senate |
|
February 17, 2009 | H.R. 1 Signed into law, and site goes live |
|
February 19, 2009 | Federal agencies to begin reporting their formula block grant awards |
|
March 3, 2009 | Federal agencies to begin reporting on their use of funds |
|
May 1, 2009 | Draft Agency and Program Plans completed |
|
May 15, 2009 | Final Agency and Program Plans submitted to Office of Management and Budget |
|
May 17, 2009 | Agency and Program Plans posted on Recovery.gov |
|
May 18, 2009 | President to report to Congress on the progress of projects in compliance with the National Environmental Policy Act |
|
August 14, 2009 | Council of Economic Advisers begin quarterly reporting |
|
October 10, 2009 | Recipient reporting begins, with subsequent quarterly reports due 10 days after the end of each calendar quarter |