USGS CMG-WR Field Schedule (MOP)

Skip navigational links
Search InfoBank
Home tab FACS tab Activities tab Atlas tab Geology School tab More tab More tab FACS tabs
   
New Field Work: GE ( Future  Present )    Past (GE)    Field Schedules: ( Santa Cruz / Menlo Park   St. Petersburg   Woods Hole )    News: ( CMG   USGS   DOI )
Descriptions: Before Activity   During Activity   After Activity   Overview Log   Crew Log   Equipment Log   Navigation Log   Operation Log  
Downloadable Forms: Overview Log (doc)  
Appendix: FACS Coordinators   Day of Year   Activity ID definition   Improving data sharing to improve science  (from MMI)   Crew Log (txt)   Equipment Log (txt)   Navigation Log (txt)   Operation Log (txt)  
   

Legend
underway planned proposed special

FY09 PROJECT CHIEF STATUS PROJECT Project # FACS ID DATES EST. DURATION SHIP PROGRAM Notes
                     
25 Conrad/Edwards planned Southern CA C4AE5 S-I2-09-SC Mar 21 - 28 4 days Sproul gravity/box corer Elfers, Dal Ferro
26 Finlayson planned       Mar 23 - 27     CARIS Hips/Sips class  
27 Jaffe planned SF Bay salt flats BQ600 BOHD0   Apr 6 - 10 2 days Snavely SwathPlus/grab sample  
28 Takesue/Lacy planned San Juan Isl., WA AZZB2   April 21 days   SLOB deployment no MarFac support
29 Finlayson et al. planned Santa Cruz     Mar - Apr 10 days Snavely Reson multibeam calibration & testing
30 Finlayson planned       Apr 14 - 16     NOAA datums course  
31 Field/Storlazzi planned Coral Reefs   A-3-09-MK May 18-27 8 days Alyce C sediment monitoring, south Molokai  
32 Gibbons/Reiss planned       May 15-17 3 days Snavely USGS Open House  
33 Lorenson/Leifer planned Santa Barbara     June 17-19 3 days Snavely ROV Hatcher
34 Cochrane/Johnson planned Puget Sound     May 4 - 10 7 to 9 days Karluk camera groundtruthing  
35 Conrad/Ryan planned Santa Monica Bay to Catalina     Jul 6 - 10 5 days Snavely minisparker/chirp  
36 Johnson/Watt planned Morro Bay/ Avila Beach     Jul 14 - 28 14 days Snavely minisparker/ magnetometer PG&E
37 Watt planned Morro Bay     Jul 28 - Aug 7 10 days Snavely magnetometer PG&E
38 Dartnell proposed Catalina I. / Pt. Mugu     Aug 10-21 12 days Shearwater groundtruthing New earmark
39 Richmond/Gibbs planned Alaska North Slope     Jul-Aug 5 weeks aircraft airborne LIDAR GPS ground control and tides
40 Cochrane/Johnson proposed CA state waters mapping Monterey Canyon to Ano Nuevo 0LDB4   Aug 20 days Snavely SwathPlus/Chirp CCC contract OFA; needs start work
41 Jaffe planned SF Bay salt flats BQ600 BOHD0   Jul - Aug 2 days Snavely SwathPlus/grab sample  
42 Hutchinson/Mayer planned Arctic   9006 09007 Aug 7 - Sep 16 42 days Healy multibeam joint US-Canada
43 Lorenson/Coffin proposed Arctic     Sept 2 - 16 14 days Polar Sea vibracore NRL
44 S. Rubin / Warrick proposed Elwha / SJDF     Aug 10 - Sept. 11 three (3) @ 5 days jet boat/RIB diving Grover
45 Gelfenbaum / Stevens planned WA coast/Elwha     Aug-Sept three (3) @ 1 week jet ski    
46 Erikson/Richmond proposed Barrow     Aug - Sept 14 days   single-beam, AWACS, LiDAR, eyeball, BASC
47 Ryan/Lee planned Whittier/Valdez     Aug 17 - 28 10 days Gyre minisparker only day ops/ Pratt add-on
48 Cochrane/Edwards proposed Pt. Arena to OR     Aug - Sept 20 days day lease camera groundtruthing, (grab sampling, mini-sparker) New earmark
49 Lacy planned S. SF Bay     Aug-Sept 3 days Frontier moorings  
50 Jayko/Hart proposed Mono Lake     Sept 7 - 10 days borrow or lease Mini-sparker Boyle
51 Jaffe planned SF Bay salt flats BQ600 BOHD0   October 2 days Snavely SwathPlus/grab sample  
52 Johnson proposed CA state waters mapping Phase II Stinson Beach north 0LD   Sept 3 - 4 weeks Snavely minisparker New earmark
53 Johnson proposed CA state waters mapping Monterey Canyon to Ano Nuevo 0LD   Oct - Dec 20 - 30 days Snavely SwathPlus / minisparker CCC contract OFA; needs start work
54 Barnard planned Santa Barbara   S-V1-09-CA Oct 13-23 10 days   jetski, beach surveys  
55 Warrick planned Elwha     Jan-Feb 2010 10 days Snavely SwathPlus  
                     
FABRICATION / OTHER                    
1 Kayen/Hatcher planned integrate Riegl LIDAR w/ IMU              
2 Tate/Hogg underway new winches for sidescan and camera on Snavely              
3 Boyle/Hatcher underway improved transducer mount for Karluk              
4 Hatcher/Reiss/Wyland/Stevens underway jetski upgrades              
5 Childs/Hart planned maintenance Bauer compressor and small airguns              
6 Storlazzi/Erikson planned