Accountability and Transparency - This is your money. You have a right to know where it's going and how it's being spent. Learn what steps we're taking to conduct oversight of funds distributed under this law in order to prevent fraud, waste and abuse. Fraud, Waste and Abuse - Large amount of cash can attract fraud. Learn how to report any suspected waste and misuse of the recovery money.State, Local, Tribal and Territorial Resources - Curious about recovery progress in your specific area? Learn more about Recovery efforts here.Agency Progress and Resources - We're bringing transparency and accountability to all areas of government.  Learn about Recovery investments and grant programs at government agencies and departments.
DOS - Financial and Activity Report
Department of State
Report Date: 2009-04-17View History

 Financial Status:
  • Total Available: $7,206,449
  • Total Paid Out: $0
 Major Actions Taken to Date:
  • International Water and Boundary Commission (IBWC): Awarded Purchase Request for re-design of Hidalgo Phase I segment in the Lower Reach in the amount of $33,158
  • IBWC: Awarded Purchase Request for historic architectural investigations in the Canalization segment in the Upper Reach in the amount of $214,996
  • IBWC: Awarded Purchase Request for environmental assessment of the Arroy Colorado segment in the Lower Reach in the amount of $242,725
  • IBWC: Awarded Purchase Request for geo-technical investigation of American Dam-Riverside Weir Rectification segment in the Upper Reach in the amount of $467,931
  • IBWC: Awarded Purchase Request for design of the Main Floodway-Arroyo segments in the Lower Reach in the amount of $3,276,000
  • IBWC: Awarded Purchase Request for the re-design of Hidalgo Phase II segment in the Lower Reach in the amount of $27,000
  • IBWC: Awarded Purchase Request for the design of Lateral A-Donna Pump/Retamal Dike segment in the Lower Reach in the amount of $440,345
  • IBWC: Initiated review of candidates for term contract specialist position
  • IBWC: Conducted tour of levees being rehabilitated in Dona Ana County, NM with prior appropriations and with Recovery Act funding for Senator Udall (D-NM) and Congressman Teague (D-NM)
  • Data Center: Began development of a Statement of Work to engage an IT Integrator to plan and execute the transition of services and systems into the two new data centers
  • Data Center: Continued development of a Statement of Work for the engagement of a firm to serve as the Government Representative in future Data Center design and acquisition activities
  • Data Center: Worked with GSA to develop a plan for engaging GSA services for the identification and acquisition of a suitable site for the ESOC West facility
  • IT Platform Modernization: Finalized specifications for upcoming equipment procurement (regarding $6.2 Million for OpenNet Equipment)
  • National Foreign Affairs Traning Center: Awarded contract for $173,580.31 for furniture procurement
  • Hard Skills Training Center: Obligated $2 million to GSA for site acquisition work
 Major Planned Actions:
  • IBWC: Issue Task Order for aerial survey (Lidar) for the Upper Reach (est. week of 4/20/2009)
  • Cyber Security: Waiting for Committee on National Security Systems (CNSS)National Telecom Security Working Group (NTSWG) approval for systems
  • Data Center: Procure services via an existing IDIQ contract with a firm to serve as the Government Representative in future Data Center design and acquisition activities