DOS - Financial and Activity Report
Financial Status: |
- Total Available: $771,059
- Total Paid Out: $0
|
Major Actions Taken to Date: |
- International Water and Boundary Commission (IBWC): Committed Purchase Request in the amount of $7,141,145 for design of Canalization segments in the Upper Reach
- IBWC: Committed Purchase Request in the amount of $28,605 for re-design of Hidalgo Phase I in the Lower Reach
- IBWC: Committed Purchase Request in the amount of $78,654 for design for Lateral A segment in the Lower Reach
- IBWC: Committed Purchase Request in the amount of $2,985,089 for design of Rectification segment in the Upper Reach
- IBWC: Awarded Task Order in the amount of $771,059 for geo-technical investigations for segments in the Lower Reach
- Hard Skills Training Center: DOS Office of Real Property Management sent letter to GSA Office of Real Estate Aquisition formally requesting assistance in acquiring a site
- Cyber Security: Met with Center for Security Evaluation to discuss tools to guard against and track cyber attacks
- Data Center: Worked with GSA to assess additional sites identified as potential ESOC locations
- IT Platform Modernization: Finalized specifications for upcoming equipment procurement
- National Foreign Affairs Training Center: Initial quote for systems furniture to increase occupancy of eight (8) SLS office's from three to six personnel was received
|
Major Planned Actions: |
- IBWC: Will conduct tour of levees being rehabilitated in Dona Ana County, NM with prior appropriations and with Recovery Act funding for Senator Udall and Congressman Teague at the Senator's request
- IBWC: Award Task Order for aerial survey (Lidar) (est. week of 4/13/2009)
- IBWC: Award Task Order for re-design of Hidalgo Phase II segment in the Lower Reach (est. week of 4/13/2009)
- Data Center: Begin development of Statement of Work to engage an IT integrator
|