Agency Summary
|
Weekly Progress
Source: Agency Financial and Activity Report as of 2009-05-14
|
Financial and Activity Report
Financial Status: |
- Total Available: $19,282,025
- Total Paid Out: $0
|
Major Actions Taken to Date: |
- International Boundary and Water Commission (IBWC): Committed purchase request for design of Main and North Floodway and the Arroyo Colorado segments in the Lower Reach in the amount of $4,224,000
- IBWC: Committed Purchase Request for design of Hidalgo Phase II segment in the Lower Reach in the amount of $8,412
- IBWC: Committed Purchase Request for bid construction services for Banker Floodway North Levee segment in the Lower Reach in the amount of $290,253
- IBWC: Committed Purchase Request for the construction of Banker Floodway North Levee segment in the amount of $740,439
- National Foreign Affairs Training Center (NFATC): Awarded contract for $49,931.60 to Landmark Technology Inc. for furniture demolition/movement
- NFATC: Phasing work in order to avoid disrupting classes has necessitated a change in the contract with Kimball Furniture (Indiana). The amount obligated has been changed from $357,695.91 to $1,090,655.67
|
Major Planned Actions: |
- IBWC: Issue design task order for the Fabens and Fort Hancock levee segments in the Upper Reach (est. 6/4/09)
- IBWC: Issue design task order for the following segments in the Upper Reach (est. 6/5/09): Hatch West, Mesilla West, Canutillo West, Anapra
|