Recommended Action Checklists

Indoor Air Quality Design Tools for Schools

NOTE: This page contains only a summary of the recommended actions, follow links in the text below for additional detail and explanatory information.

Contents

Each recommended action is broadly categorized according to the following codes: 

A=School Administrator/Facility Planner
D=Design Team
C=Construction Supervisor
F=Facility Manager

Preliminary Design Phases

checkbox Set high performance goals early and include them in your educational specifications. A      
checkbox Minimize the impact of the site. A D    
checkbox Select design team with necessary qualifications and experience with high performance design. A      
checkbox Communicate goals to designers. A D    
checkbox Pursue integrated design. A D    
checkbox Communicate goals to contractors. A D C F
checkbox Monitor construction. A D C  
checkbox Verify goals. A D    
checkbox Train school staff A D   F

Top of page

Planning, Programming, and Goal Setting

checkbox Establish superior indoor air quality as a design goal for the project in preliminary documents. A D    
checkbox Include requirements for attention to indoor air quality in all appropriate phases of planning, design, and construction. A D    

Top of page

School Site Selection and Evaluation

checkbox Prior to site acquisition, complete a Phase I Environmental Site Assessment using ASTM Standard Practice E1527-05 exiting EPA A D    
checkbox If preliminary assessment suggests significant potential sources of contamination, conduct a Phase II Environmental Site Assessment using ASTM Standard Practice E1903-97 (2002) A D    
checkbox Ensure that soil contamination is cleaned up or avoid site.  A D    
checkbox
Provide opportunities for participation in the school site acquisition process by school administrators and staff, parents, age-appropriate students, and community members.
A D    

Top of page

Selection of the Architectural and Engineering Team

checkbox Select a design team with the necessary qualifications for designing a high performance school, and include the requirement for a high performance school in the negotiated design services. A      
checkbox

Ask prospective design teams to answer key IAQ related questions.

A      
checkbox Request and check references to evaluate applicants' track record on health and safety issues, meeting budgets and goals, working with the community, and familiarity with materials selection and indoor air quality issues. A      
checkbox Communicate goals to designers. A      

Top of page

Controlling Pollutants and Sources

Controlling Indoor Sources

Material Selection

Strategies and Processes for Material Selection

checkbox Prioritize sensitive program areas. A D    
checkbox Use product consensus standards.   D    
checkbox Develop specification criteria. A D    
checkbox Obtain MSDS/manufacturer certifications.    D    
checkbox Require field approval for product substitutions. A D    

Categories of Materials to Consider from an Indoor Air Quality Perspective

Flooring

Carpet

checkbox If carpet is specified, select a carpet, cushion, and adhesive that:
  • have been tested and labeled for VOC emissions under the Carpet and Rug Institute's (CRI) IAQ testing programs
  • can be easily cleaned and maintained
  • are constructed to prevent liquids from penetrating the backing layer where moisture under the carpet can result in mold growth
  • can be easily removed without the use of toxic chemicals
  D    
checkbox Where new carpet odor is a concern, require suppliers to unroll and air-out carpets in a clean, dry warehouse before bringing them into the building. A D   F
checkbox Specify the least toxic carpet adhesive system compatible with selected carpet product. Require installer to use the smallest amount of adhesive necessary to fulfill the manufacturer’s performance specifications for that product. Alternately, specify tack-down carpet to eliminate gluing.   D    
checkbox Air out space(s) where carpet has been installed for a minimum of 72 hours.   D C F
checkbox In renovations, carpet installation should occur only when the school building is not in use.     C F
checkbox Do not install carpet near water fountains, sinks, showers, pools, or other locations where it may get wet.   D C  
checkbox Follow recommendations from the Carpet and Rug Institute exiting EPA for installation (CRI 104-- Standard for Installation of Commercial Carpet).     C  
checkbox Follow the carpet manufacturer's maintenance recommendations to protect the carpet warranties.     C F
checkbox All spills must be cleaned up immediately and thoroughly. If carpet becomes saturated with a clean water spill, extract the moisture and be sure the carpet is dry within 24 hours. Spills of other liquids require immediate extraction and spot cleaning as well as drying within 24 hours.     C F

Resilient Flooring

checkbox Specify low-VOC adhesives and coatings to minimize the indoor air pollution load and health risks to both installers and occupants.   D    
checkbox Ask for manufacturer’s emissions data to aid in selection.   D    
checkbox Require installer to use the smallest amount of adhesive necessary to fulfill the manufacturer’s performance specifications for that product. (Note: In some applications, interlocked rubber tiles and heavy linoleum can be laid without adhesive.)   D C  
checkbox Air out space(s) where resilient flooring has been installed for a minimum of 72 hours.   D C F

Walls and Ceiling Materials

checkbox Select formaldehyde-free acoustical ceiling and wall systems with recycled-content.   D    
checkbox Where feasible, sequence work to avoid applying VOC-containing materials in spaces with exposed acoustical surfaces.   D C F
checkbox Require adequate ventilation during installation of finish materials that emit indoor pollutants.   D C F
checkbox Consult with the manufacturer before painting/coating any acoustical material. With most ceiling tiles, for example, the material loses its acoustical properties once it has been painted.   D C F
checkbox Coordinate placement of lighting fixtures and other equipment in ceilings to provide clear access for inspection and servicing of HVAC system air filters and other components.   D C  
checkbox Remove and discard any wetted ceiling tiles from the site immediately to avoid mold contamination.     C F
checkbox Avoid using ceiling tile and sprayed-on ceiling finishes containing asbestos or  formaldehyde.   D C  

Paints and Coatings

checkbox Specify least toxic, formaldehyde-free, zero-VOC or low-VOC paint that meets durability and other performance requirements.   D    
checkbox Specify products containing no lead, mercury, hexavalent chromium or cadmium. Though regulations have nearly eliminated many toxic components from consumer paint lines, industrial and commercial paints may still contain them. Check the MSDSs.   D    
checkbox Specify isolation requirements (isolation of construction zones from completed zones to prevent cross-contamination; removal, coverage, or isolation of porous materials to avoid adsorption and subsequent re-emission of solvents, maintaining negative ventilation in construction areas). When sanding dried paint, a dust mask should be worn.   D C  
checkbox Review recommended duration between paint application and occupancy and review for compatibility with maintenance schedules/requirements.   D C F
checkbox When possible, schedule work during unoccupied periods or periods of least occupancy. Large projects should be scheduled during the summer vacation months or other breaks. The maintenance schedule should also factor in manufacturer recommended air temperatures for application. A D C F
checkbox Where possible, perform painting and stripping off-site or select materials with factory-applied finishes.     C F
checkbox For on-site interior painting, cover surfaces (e.g., with plastic sheeting), such as fabric-covered furnishings, that may adsorb VOCs. Specify sequence of installation so that painting and other "wet" applications occur before installation of "fleecy" materials.     C F
checkbox Consider constructing barriers (for example, walls or curtains of plastic sheeting) to help isolate portions of larger areas and minimize the distribution of dust and other pollutants.     C F
checkbox Wipe down all surfaces with a wet cloth as soon as practical after completing all dust-generating work typically associated with surface preparation.     C F
checkbox Carefully observe manufacturers recommendation for cleanup, storage, and disposal, for paints, primers, and thinners. (Note: Some products are classified as "flammable liquids" under federal regulations and must be stored in a specifically constructed safety cabinet.)     C F
checkbox Keep paint containers covered as much as possible during and following use to protect against VOC release.     C F

Adhesives and Sealants

checkbox Avoid using solvent-based products, which include butyls and urethanes, indoors. Low VOC, low-toxic water-based, formulations are now available for many applications.   D C F
checkbox Specify the least toxic/lowest VOC product suitable for the application and require installer to use the smallest amount of adhesive necessary to fulfill the manufacturer’s performance specifications for that product.   D    

Engineered Wood Products

checkbox Use low VOC, low-toxic water-based, formulations which are now available for many applications.   D C F
checkbox Specify the least toxic/lowest VOC product suitable for the application and require the installer to use the smallest amount of adhesive necessary to fulfill the manufacturer’s performance specifications for that product.   D    

Installation Sequencing

checkbox Specify air exchange rates and proper air filtration procedures for the ventilation system in construction documents to ensure that whenever possible, any necessary off-gasing from Type One materials is dissipated before Type Two materials are installed.   D    
checkbox Require the contractor to properly clean all duct work and replace all air filters before building occupancy.   D C  

Top of page

Preventing the Entry of Pollutants from Outside the Building

Radon Barriers

checkbox Install 4 inches of ½ to 1 inch clean aggregate and a vapor barrier under all slab areas.  D C
checkbox Install one centrally located sump pit per 100,000 square feet of earth-contact floor area D C
checkbox Install a 6 inch PVC vent pipe from the sump pit to the roof. D C
checkbox Install a 120VAC, 15A weatherproof junction box on the roof next to the 6 inch vent pipe, to permit installation of a fan to vent soil gas if post-construction testing finds elevated radon levels.   D C  
checkbox Seal all major slab openings, cracks, or penetrations with polyurethane sealant D C
checkbox Make post-construction radon measurements using EPA's Radon Measurement in Schools Protocol (EPA-402-R-92-014). A C F

Sewer Gas Barriers

Drain Traps

checkbox Install automatic drain trap primers, available from several major manufacturers, in all floor drains to ensure that a small amount of water is periodically delivered to the trap, preventing the trap from drying out.   D C  

Sewer Vents

checkbox Make sure sewer vents are not located where gases can be pulled back into the building or install an air admittance valve.   D C  

Entry Mat Barriers

checkbox The entry mat system should be at least 20 feet long and as wide as the entry doors, and employ three different types of matting.    D C  
checkbox All mats should have anti-slip backings or other locking mechanisms to reduce sliding and tripping hazards.   D C  
checkbox Since daily cleaning will be required, the ease of cleaning should be considered during selection.   D C  

Shell Penetration Barriers

checkbox Seal all openings in walls, floors, and ceilings that separate conditioned space (heated or cooled) from unconditioned space.   D C  

Top of page

Heating, Ventilation, and Air-Conditioning (HVAC)

Codes and Standards

checkbox Design in accordance with ASHRAE standards A D    
checkbox Ensure familiarity with and adherence to all state and local building codes and standards. A D C  

Potential for Natural Ventilation and Operable Windows

checkbox Designers should consider the use of natural ventilation and operable windows to supplement mechanical ventilation.   D    
checkbox If operable windows will be used to supplement the HVAC system, ensure that:
 
bullet openings for outdoor air are located between 3-6 feet from the floor (head height);
bullet the windows are adjustable and can close tightly and securely;
bullet they are placed to take maximum advantage of wind direction, with openings on opposite sides of the building to maximize cross-ventilation;
bullet consider outdoor sources of pollutants (including building exhausts) and noise when determining if and where to provide operable windows;
bullet avoid placing operable windows near building exhaust openings.
  D    

Selection of HVAC Equipment

checkbox Where feasible, utilize central HVAC air handling units that serve multiple rooms in lieu of unit ventilators or individual heat pumps.   D    
checkbox Specify IAQ compatible features for all air handling units.   D    

Energy Recovery Ventilation

checkbox Consider specifying energy recovery ventilation equipment. A D    

Location of Outdoor Air Intakes and Exhaust

checkbox Locate outdoor air intakes away from pollutant sources and prevent blockage.   D C  
checkbox Intakes should not be placed within 25 feet of any potential sources of air contaminants, including sewer vents, exhaust air from the school, loading docks, bus loading areas, garbage receptacles, boiler or generator exhausts, and mist from cooling towers.   D C  
checkbox Grilles protecting air intakes should be bird- and rodent-proofed to prevent perching, roosting, and nesting.   D C F
checkbox Intake Screens must be accessible for inspection and cleaning.   D C F
checkbox Consider adding a section of sloped intake plenum that causes moisture to flow to the outside or to a drain if intake grilles are not designed to completely eliminate the intake of rain or snow.   D C  

Outdoor Air Quantity

Air Filtration

checkbox Air filters should have a dust-spot rating between 35% and 80% or a Minimum Efficiency Rating Value (MERV) of between 8 and 13.   D    
checkbox Design more filter surface area into ventilation systems.   D    
checkbox Consider installing a simple pressure differential gauge across all filter banks.   D    

Top of page

Ventilation Controls

Volume Monitoring and Control

checkbox Specify the addition of a measuring station that actively controls the amount of outdoor airflow by modulating the outdoor air damper, and if needed to overcome wind and stack effects, the return (recirculation) damper.   D    

Moisture and Humidity Control

Air Distribution and Duct Insulation

checkbox Pay special attention to preventing moisture from entering duct work. D C F
checkbox If specifying duct board or internal duct lining for thermal and/or acoustical control, be sure to consider the potential for uncontrolled moisture to enter the duct over the life of the system.  Select products that will minimize the potential for moisture retention in the event of unforeseen moisture contamination of the duct system, such as those with properties that reduce the potential for moisture to penetrate the air stream surface. Ensure that all duct systems are properly fabricated and installed.   D C  
checkbox Degrease sheet metal air ducts.   D C  
checkbox Seal air ducts to prevent HVAC system air leakage.   D C  

Exhaust Air

checkbox Provide exhaust ventilation for janitors closets.   D C  
checkbox Provide exhaust ventilation for copy/work rooms.   D C  
checkbox Provide exhaust ventilation for arts and crafts preparation areas where off-gasing from significant quantities of materials and products may occur.    D C  
checkbox Consider specifying a differential pressure monitor to monitor building pressurization.   D    
checkbox Do not operate exhaust systems when the HVAC system is turned off to avoid bringing in unconditioned moist air that may condense on cooler indoor surfaces.   D C F

Designing for Efficient Operations and Maintenance

checkbox Ensure that all system components, including air handling units, controls, and exhaust fans are easily accessible.   D C F
checkbox Label HVAC system components to facilitate operations and maintenance.   D C F

Moisture Control

Building Materials

checkbox Keep building materials dry during construction.   D C  
checkbox Dry water damaged materials as quickly as possible, preferably within 24 hours.   D C F

Precipitation Control

checkbox Sloped Roof   D C  
checkbox Ground Slope – Ensure that ground next to the building slopes away from the foundation.   D C  
checkbox Covered Entries – Ensure that exterior entries have sufficient overhang to prevent rain or snow from being blown into the building, or from large amounts of moisture collecting directly in front of the entry and being tracked into the building.   D C  
checkbox Sloped Intake Plenum – Consider adding a section of sloped intake plenum that causes moisture to flow to the outside or to a drain if intake grilles are not designed to completely eliminate the intake of rain or snow.   D C  

Building Envelope

checkbox To prevent moisture migration, framed walls, floors and roofs should have a vapor barrier on the warm, moist side of the insulation.   D C  
checkbox For floor slabs in immediate contact with the ground, consider installing a 3-6 mil continuous vapor barrier under the slab to prevent moisture entry through the slab.   D C  
checkbox In addition to correctly installing a vapor barrier, it is important to provide adequate ventilation of spaces where moisture can build up.   D C F
checkbox Pay close attention to both the design and proper installation of roof flashing, pan flashing for windows and doors, capillary breaks for footings, and other areas where moisture can enter the building envelope.   D C  

Controlling Moisture in Ventilation Air

checkbox To protect health, comfort, the school building and its contents, it is important that indoor relative humidity be maintained below 60%, ideally between 30% and 50%.  A D C F
checkbox Avoid over-sizing the HVAC system, particularly in high humidity climates.   D    
checkbox Consider specifying energy recovery ventilation equipment. A D    
checkbox If humidification equipment is installed in very dry climates, care must be taken to avoid microbiological problems associated with excess humidity and to ensure maintenance of humidification equipment. A D   F

Summer Breaks and Humidity Control

checkbox Consider cycling the air conditioning system (if present) several hours every day to reduce indoor moisture, or run portable de-humidifiers. A     F
checkbox Consider establishing policies that moisture generating activities (e.g., carpet cleaning) not be conducted in the summer in humid climates unless air conditioning or other moisture removing equipment is available. A     F
checkbox Consider manual thermostat overrides. D
checkbox Consider CO2 sensors in each zone to control outdoor air dampers during summer periods when occupancy may be intermittent.   D

Condensation

checkbox Fully insulate all cold water pipes and fittings, and condensate drain pipes, with appropriate insulation (see discussion of duct insulation under HVAC--Air Distribution). There should not be any gaps or unsealed seams in the insulation, and all fittings, including valve stems, should be insulated.   D C  
checkbox Fully insulate all cold refrigerant lines similar to cold water pipes.   D C  
checkbox Fully insulate cold-air supply ducts.   D C  
checkbox Minimize thermal bridging in the building shell.   D C  
checkbox If renovating, add appropriate levels of insulation to prevent cool interior surfaces of windows, walls, ceilings, and floors.   D C  
checkbox Specify windows and doors with frames and spacers around edges that have thermal breaks.   D    

Top of page

Construction

IAQ Management During Construction Planning

checkbox Incorporate indoor air quality goals into the bid and construction documents. A D    
checkbox Ensure that all members of the project team are knowledgeable about indoor quality issues and have defined responsibilities for implementation of good indoor air quality practices. A D C F
checkbox Require the development and use of an indoor air quality management plan. A D C F
checkbox Conduct regular inspection and maintenance of indoor air quality measures including ventilation system protection, and ventilation rate. A D C F
checkbox Conduct safety meetings, develop signage, and establish subcontractor agreements that communicate the goals of the construction indoor air quality plan. A D C F
checkbox Require contractors to provide information on product substitutions sufficient to enable O&M staff to properly maintain and repair materials in place. A D C F

Construction Practices

checkbox Keep building materials dry.     C F
checkbox Dry water damaged materials quickly.     C F
checkbox Clean spills immediately.     C F
checkbox Seal unnecessary openings.     C F
checkbox Temporarily seal duct-work.     C F
checkbox Ventilate when needed.     C F
checkbox During installation of carpet, paints, furnishings, and other VOC-emitting products, provide supplemental (spot) ventilation for at least 72 hours after work is completed. A D C F
checkbox Require VOC-safe masks for workers installing VOC-emitting products (interior and exterior).     C F
checkbox Reduce construction dust.     C F
checkbox Use wet sanding for gypsum board assemblies. Exception     C F
checkbox Avoid use of combustion equipment indoors.       C F
checkbox Store liquids outdoors.      C F
checkbox Use less toxic cleaning agents.     C F
checkbox Consider a building flush-out at the end of the construction process and before occupancy. A D C F

Commissioning

checkbox Commission key building systems. A D C F

Operations and Maintenance

checkbox Obtain, adapt as needed, and implement EPA's Indoor Air Quality Tools for Schools Program Tool Kit. A D   F
checkbox Require that an "Owners Manual" be developed and maintained at the school that contains all of the information needed to maintain the school and its equipment. A D   F
checkbox Ensure that "as-built" blueprints and/or drawings are provided and maintained as building modifications occur. A D C F
checkbox Provide training to school staff appropriate to their roles.  A D   F
checkbox Establish and implement a cleaning program. A     F
checkbox Establish and implement an Integrated Pest Management exiting EPA plan. A     F

Top of page

Renovation and Repair

Techniques for Protecting Occupants from Renovation Pollutants

checkbox Before performing any demolition, check for lead-based paints and asbestos. A D C F
checkbox When possible, perform work at times when the occupants are not in the building, such as vacation breaks, weekends, or evenings. A D C F
checkbox Keep building occupants as far from renovation activities as possible.  The further the distance between pollutants and occupants, the less concentrated the pollutants will be upon reaching the occupants. A D C F
checkbox Install temporary barriers such as plastic walls to seal the work areas from the occupied areas. Cover all supply and return air grilles if the HVAC system in the renovation area also serves occupied areas so that the air ducts will not spread pollutants to occupied area. Exhaust air from the construction area so that pollutants cannot flow from the construction area to the occupied areas.   D C F
checkbox When possible, keep pollutants confined to as small an area as reasonably possible, rather than allow them to spread to larger areas.   D C F
checkbox At least daily, construction debris, dust, and scraps should be adequately cleaned up so that there is less chance that these pollutants will enter occupied areas.   D C F

Top of page

Portable Classrooms

Specifying New Portable Classrooms

(See also:  www.epa.gov/iaq/schooldesign/portables.html#Specifying New Portable Classrooms)

checkbox When specifying a new portable classroom, ensure that the HVAC system can: (a) provide a minimum of 450 cfm of outside air (based on 30 occupants at 15 cfm/occupant); and (b) heat and cool this outdoor air at design outdoor temperatures for the specific geographic location where each classroom is installed. A D    
checkbox Some manufacturers of portable units do not include outdoor air intakes in their standard classroom models. It is important that an additional "outdoor air kit" be ordered for this purpose. Further, installation of an outdoor air intake must be specified as part of the exhaust system. A D    
checkbox Outdoor air should be supplied continuously when a classroom is occupied. A D   F
checkbox Air filters are needed for protection of HVAC components and reduction of airborne dust, pollens and microorganism from recirculated and outdoor air streams.  Air filters should have a dust-spot rating between 35% and 80% or a Minimum Efficiency Rating Value (MERV) of between 8 and 13.   D C F
checkbox When carpets are specified, use carpets that have been tested under the Carpet and Rug Institute’s Indoor Air Quality Carpet Testing Program. A D    
checkbox Locate classroom away from locations where: (a) vehicles idle, (b) water accumulates after rains or (c) there are other major sources of air pollution.   D    
checkbox Ensure that at least one supply air outlet and return air inlet are located in each enclosed area.   D    
checkbox Ensure that building air intakes are located away from any exhaust outlet(s) or other contaminant sources.   D C  
checkbox Specify operable windows to provide user-controlled ventilation when needed. A D    
checkbox Consider covered entries with an exterior entry mat.   D C  
checkbox Do not use carpet in entryways to classrooms with direct outdoor access. Supply waterproof mats over carpeted entryways for drying of clothing and umbrellas.   D C  
checkbox Check that special-use classrooms (e.g., for chemistry, biology, fine arts, etc.) have local exhaust ventilation (e.g., hoods or window fans) and appropriate ventilation rates.   D C  
checkbox Locate HVAC and air handler units as far away as possible from teaching areas to reduce noise.   D C  
checkbox If specifying duct board or internal duct lining for thermal and/or acoustical control, be sure to consider the potential for uncontrolled moisture to enter the duct over the life of the system.  Select products that will minimize the potential for moisture retention in the event of unforeseen moisture contamination of the duct system, such as those with properties that reduce the potential for moisture to penetrate the air stream surface. Ensure that all duct systems are properly fabricated and installed.   D    
checkbox Ensure that HVAC ducts and plenums have easy access for inspection and cleaning.   D    
checkbox Specify that low VOC emitting building materials be used in construction. A D    
checkbox Specify complete documentation of operation and maintenance requirements. A D   F
Commissioning Portable Classrooms

(see also www.epa.gov/iaq/schooldesign/portables.html#commissioning)

checkbox Prior to use of any new portable units by staff or students, operate HVAC systems at their maximum outdoor air intake rate continuously for several days. Start the "flush out" as soon as the HVAC system is operational, and continue after furniture installation. During this period, do not recirculate return air.  In humid climates, use conditioned air to avoid introducing significant amounts moisture during the flush out.   D C F
checkbox Measure the amount of outdoor air entering the outdoor air intake of the HVAC unit to ensure it meets or exceeds the amount specified or 15 cfm per person, whichever is greater.   D C F
checkbox Do not "bake-out" the unit. "Bake-out" is defined as increasing temperatures up to 100F in order to "artificially age" building materials. It's effectiveness has not been proven and it may in fact damage parts of the HVAC system or building components.   D C F
checkbox Continue "flush-out" ventilation during periods of first use.   D C F
checkbox Establish an Integrated Pest Management plan.   A D C F
Operations and Maintenance of Portable Classrooms

(see also:  www.epa.gov/iaq/schooldesign/portables.html#Operations and Maintenance)

checkbox Provide training on operation and maintenance of new HVAC equipment to appropriate staff. Be certain that operation and maintenance documentation is kept readily accessible to staff servicing the system. A D   F
checkbox Allocate sufficient staff time and funds for maintenance. A     F
checkbox Instruct teachers and staff on proper use and settings of thermostat and ventilation controls – provide each classroom with hardcopy (plastic-covered) instruction sheets.       F
checkbox Establish a regular and timely plan for inspecting and performing specific maintenance tasks: Inspect roofs, ceilings, walls, floor, and carpet for evidence of water leakage or intrusions, and for mold growth or odor. Replace water damaged materials promptly. A     F