Sign up for updates: 
Skip to main content  
Accountability and Transparency - This is your money. You have a right to know where it's going and how it's being spent. Learn what steps we're taking to conduct oversight of funds distributed under this law in order to prevent fraud, waste and abuse. Share your Story - Tell us how the Recovery Act is affecting you. What's working? What isn't? We want to hear from you. State Progress and Resources - Curious about the recovery progress in your state?  Learn more about statewide recovery efforts here. Agency Progress and Resources - We're bringing transparency and accountability to all areas of government.  Learn about Recovery investments and grant programs at government agencies and departments.
Agency Summary
Department of Homeland Security



Financial Status

Weekly Progress
Source: Agency Financial and Activity Report
as of 2009-04-30
Financial and Activity Report

Report Date: 2009-04-24View History

 Financial Status:
  • Total Available: $102,965,725
  • Total Paid Out: $132,457
 Major Actions Taken to Date:
  • TSA:
  • - Hiring Plans are in place.
  • - Press release issued with TSA checked baggage screening projects listed.
  • - Issued conditional letters to airports indicating project consideration.
  • - Spend plan submitted to the Appropriations Committees on April 3, 2009
  • - Spend plan briefed to the Appropriations Committees on April 9, 2009
  • USCG:
  • - Funding has been allocated to the ( Acquisition, Construction and Improvements (AC&I $98M) to the program office
  • - Funding has been allocated to the (Alteration of Bridges (AB $142M) to the Coast Guard program office
  • - Submitted planned obligations and outlay data (by month) for the AC&I and AB Programs
  • - Mobile Bridge project was advertised. Bid Documents of EJ&E Bridge completed
  • - Preliminary planning documentation and outlay projections completed on all shore infrastructure projects
  • - Analysis, planning, and preliminary engineering design
  • documentation completed on vessel projects.
  • - Obligated $459K of AC&I funds for the Coast Guard 378 Foot High Endurance Cutter Project
  • - Funding provided to Facilities Design and Construction Center ($7M) to exercise option on current contract for CGC
  • Sycamore Cordova Housing Phase IV.
  • - Began first phase of DHS IG audit of ARRA AC&I and AB projects.
  • USM - Submitted RWA package to GSA for $198.9M commitment. Committed $450K for Site Survey Team
  • FEMA:
  • - Emergency Food & Shelter:
  • - Complete Congressional notifications of award April 9, 2009
  • - Awarded funds to the National Board of the Emergency Food and Program April 9, 2009.
  • ICE:
  • - Spend plan submitted to the Appropriations Committees on April 3, 2009
  • - Developed preliminary estimates of the communications network infrastructure required to upgrade
  • Boston and Denver Regions.
  • - Submitted Project 25 (P25) equipment and limited services procurement package for the Boston and Denver Regions
  • Denver Regions to Office of Acquisition Management (OAQ)
  • - Developed preliminary schedule for Boston and Denver Region P25 Upgrade initiative
  • count, and equipment list for the coverage areas.
  • - Completed initial draft of Tactical Communications Recovery Act Project Plan
  • - Completed edits from internal review of Recovery Act Plan and submitted for DHS review.
  • CBP:
  • - Agency spend plans have been forwarded to Appropriations Committees.
  • - Ports of Entry - Initiated outreach to landowners and surrounding
  • communities to begin site surveys and environmental assessments.
  • - Tactical Communications - conducted 2nd meeting with Procurement on
  • Taccom Acquisition strategy; provided info. as related to number of
  • requisitions required to obligate ARRA funding; ESC pre-briefings have
  • been provided to OBP, OFO and A&M as related to expenditures.
  • Briefed ARRA spend plans to the House and Senate appropriations staff
  • on April 9th; Submitted the OneNet paper to DHS in support of the ITAR
  • requirement for the Acquisition Plan Review.
  • - NII met with Procurement on Acquisition Strategy to support the $100M
  • for several different types of contracts, and is now in process of preparing
  • acquisition documents. NII is submitting the ARRA Procurement Requests
  • through the standard approval process as individual PRs for the $100M.
  • The first 2 PRs for $38M are moving quickly and are at the AC for approval on 4-27-09.
  • OIG:
  • - Initiated 10 audits of DHS agency plans of Recovery Act funds.
  • - Held meeting with DHS and agency liaisons to communicate and coordinate requirements under the Recovery Act.
  • - Held planning meeting with primary Recovery Act audit teams to work on overall audit approach for all
  • Recovery Act audit teams.
  • - Initiate development of the tools and systems to meet the reporting needs as required by the Recovery Act.
  • - Drafted an advisory report of DHS capabilities to assist the department and its agencies to prioritize and
  • mitigate risks to implement initiatives funded by the Recovery Act.
  • - Updated staff training plan designed to increase the knowledge of IG audit staff to effectively audit initiatives
  • funded by the Recovery Act.
  • - Held entrance conference on April 9, 2009 for OIG's audit of DHS' agency Recovery Plan.
  • - Held entrance conference on for OIG's audit of U.S. Immigration and Customs Enforcement's, spending plan.
  • U.S. Customs and Border Protection, Transportation Security Administration, U.S. Coast Guard for audits
  • of spending plans..
  • - Finalized the audit plan for DHS spending plan audits.
  • - Attended first Recovery Accountability and Transparency Board working group meeting.
  • - Issued Draft Advisory Report on DHS' Capabilities to Implement the American Recovery and Reinvestment
  • Act of 2009
  • - Held entrance conference on April 22, 2009, for the audit of Federal Emergency Management Agency's
  • capabilities to oversee grant programs funded by the Recovery Act
  • - Finalized the audit plan for the audit of Federal Emergency Management Agency's capabilities to
  • - oversee American Recovery and Reinvestment Act grant programs
  • - Attended working meeting with Department of Homeland Security to discuss and finalize the Office
  • of Inspector General's Advisory Report on the department's capabilities to implement the American
  • Recovery and Reinvestment Act of 2009
  • - Conducted interviews of component personnel responsible for developing spending plans and
  • supporting documentation requested undergoing analysis
 Major Planned Actions:
  • TSA - Negotiate with airports on OTAs
  • USCG:
  • - Bid solicitation advertisements for the Burlington Bridge project
  • - Complete bid documentation of Burlington Bridge project
  • - Continue planning documentation for final shore
  • infrastructure project.
  • - Continue engineering design documentation for vessel projects.
  • - Award of option on existing contract for $7M to complete Cordova Housing Project.
  • USM - Plan to obligate $198.9M with GSA in late April 2009; remaining funds to obligate by 9/30/09.
  • FEMA: State & Local Programs/Firefighters Assistance Grants:
  • - Will issue grant guidance June/July 2009
  • - Receipt and review of grant applications July/August 2009
  • - Grants will be awarded September/December 2009
  • ICE:
  • - Develop procurement package for Hub Upgrade Generator Power System
  • - Develop Mobile Communications System procurement package
  • - Develop Wireless Communications Kit procurement package for submission to
  • Office of Acquisitions (OAQ) by end of April 2009.
  • - Develop HUB Upgrade Infrastructure Brand Name J&A and submit to OAQ.
  • - Changed bullet to read plan to obligate $198,900M with GSA in late April 2009;
  • remaining funds to obligate by 9/30/09.
  • CBP:
  • - Ports of Entry - Plans to issue multiple Request for Proposal (RFP)
  • by 6/25/09 for multiple design/build project contract awards by 8/16/09.
  • - SBInet - Initiate procurement and deployment of near-term
  • existing technology, June/July 2009.
  • - Non-intrusive inspection (NII) systems - Estimated contract award
  • of 5/29/2009 for the first of approx. 5 or 6 awards. All awards should
  • be completed by the 4th quarter of FY09.
  • - Tactical Communications - Estimated contract award July 2009;
  • initiate procurement & conduct radio site construction activities;
  • Develop white paper explaining the role of the IP console and
  • infrastructure upgrade in response to request from the House
  • Appropriations Committee staff.
  • OIG :
  • - Issue Advisory Report on DHS' Capabilities to Implement the American Recovery and
  • Reinvestment Act of 2009
  • - Inspector General will attend bi-weekly meeting of the Recovery Accountability
  • meetings of the Recovery Accountability and Transparency Board
  • Continued fieldwork on all 11 ongoing Recovery Act audits, including additional interviews
  • and analysis of supporting documentation

  View Source file


Report History

Report Date
Source