Oak Ridge Gaseous Diffusion Plant (K-25 Site)
(Site Profile Number 026)

Location: Oak Ridge, Tennessee

Also Known As: East Tennessee Technology Park (ETTP)

Site Profile

  1. Introduction
    (Revised May 4, 2006)
    this document in PDF PDF 49 KB (9 pages)

    Revision Includes: Incorporates introductory language and updates the document for biennial review. No further changes resulted as a result of formal internal review.

  2. Site Description
    (Revised October 4, 2006)
    this document in PDF PDF 70 KB (14 pages)

    Revision Includes: Revised the Introduction to include required language by NIOSH. Added Purpose and Scope sections. Deleted unnecessary Figure 2.1-1 in Section 2.2. Responded to Worker Outreach comments 22 and 24. No further changes occurred as a result of formal internal review. No changes were required due to the K25 Worker Outreach SPFPA and IGUA Worker Outreach meeting held on April 5, 2006 or K25 Worker Outreach PACE Local 5-288 and Pace International Union Worker Outreach meeting held on April 6, 2006. This revision results in no change to the assigned dose.


  3. Occupational Medical Dose
    (Page Change Revision November 7, 2006)
    this document in PDF PDF 60 KB (13 pages)

    Page Change Revision Includes: Approved page change revision to update required language on pages 4 and 5 in Section 3.1. Updates acronyms and abbreviations on page 3. Adds a Purpose Section and a Scope Section on page 5. No sections were deleted. No further changes occurred as a result of formal internal review. No changes required to this document due to Worker Outreach comments. This revision results in no change to the assigned dose and no PER is required.


  4. Occupational Environmental Dose
    (Revised June 22, 2007)
    this document in PDF PDF 236 KB (22 pages)

    Revision Includes: Added Attributions and Annotations section. No further changes occurred as a result of formal internal and NIOSH review. This revision results in no change to the assigned dose and no PER is required.


  5. Occupational Internal Dose
    (Page Change Revision October 4, 2006)
    this document in PDF PDF 152 KB (24 pages)

    Page Change Revision Includes: Page change revision to update required language in the Introduction on page 5. Adds Purpose and Scope sections on pages 6 and 7. Incorporates Worker Outreach comments in on page 12 in Section 5.5 and page 14 in Section 5.6. Adds RU sentence on page 11 in Section 5.4. Adds two references to page 17. Incorporates NIOSH formal review comments. Incorporates internal formal review comments. Corrects dates on page 6 in Section 5.3 for consistency. Provides reference to Internal Dosimetry Coworker Data for K-25. This revision results in no change to the assigned dose.


  6. Occupational External Dose
    (Page Change Revision September 26, 2006)
    this document in PDF PDF 143 KB (24 pages)

    Page Change Revision Includes: Approved page change revision to add required language on pages 7 and 8 in Section 6.1. Changed wording on pages 11 and 15 in Sections 6.5.2.1 and 6.6 respectively. Tables 6-4 and 6-5 on pages 14, 15, and 16 in Sections 6.5.1 and 6.5.2 in Rev 00 have been replaced with Table 2 from ORAUT-OTIB-0026 Rev 00 PC-1. Added references on page 21 in Reference Section. This revision addresses comments from the K25 Worker Outreach SPFPA and IGUA Worker Outreach meeting held on April 5, 2006 or K25 Worker Outreach PACE Local 5-288 and Pace International Union Worker Outreach meeting held on April 6, 2006. All worker outreach comments were considered. In a number of comments, the information was already covered and no change to the document was made. Incorporates internal and NIOSH formal review comments. To address Worker Outreach comment PACE #48, Table 6-4 and 6-5 were replaced with Table 2 from ORAUT-OTIB-0026. No sections were deleted. This revision results in no change to the assigned dose.

Top of Page

Technical Information Bulletins (TIBs)

  • External Coworker Dosimetry Data for the K-25 Site
    this document in PDF PDF 63 KB (11 pages)

    Document Number: ORAUT-OTIB-0026 Rev-00 PC-2

    About this Document: Establishes the technical basis to allow Dose Reconstructors (Health Physicists) to assign doses to certain workers at the K-25 site who have no or limited monitoring data, based on site coworker data.

    Page Change Revision: November 15, 2006

    Page Change Revision Includes: Approved page change revision due to release of OTIB-0052. Updates required language on page 4 in Section 1.0. Lists ORAUT-OTIB-0052 Rev 00 as a reference on page 6 in Section 5.0. Removes Section 8.0 on page 10, changes title and inserts on page 11. No further changes occurred as a result of formal internal and NIOSH review. No sections were deleted. This revision results in an increase in assigned dose and a PER is required.

  • Internal Dosimetry Coworker Data for K-25
    this document in PDF PDF 252 KB (19 pages)

    Document Number: ORAUT-OTIB-0035 Rev-00 PC-1

    About this Document: Establishes the technical basis for assignment of K-25 internal doses based on coworker bioassay data.

    Page Change Revision: July 21, 2006

    Page Change Revision Includes: Approved page change revision to add updated language to Section 1.0 on pages 5 and 6. Details were added to page 6 in Section 2.0. The date in Section 5.1 and in Table 5.1 on page 8 was changed from 1948 to 1945. Attachment C, Estimate of Intake Rates for 1945-1947 was added to pages 18 and 19. Incorporates internal and NIOSH formal review comments on pages 6, 7, 8, and 9 in Sections 2.0, 4.0, 5.1, and 5.2 respectively. No sections were deleted.

Top of Page

Program Evaluation Reports (PERs) and Program Evaluation Plans (PEPs)

NIOSH is committed to applying the best available science in dose reconstructions. In keeping with this commitment, completed cases with probabilities of causation less than 50% are reviewed as relevant new information becomes available. The results of these reviews are described in a Program Evaluation Report (PER). The PER details the effect, if any, of the new information on the completed dose reconstruction. If it appears that the compensability of a completed dose reconstruction may be effected, NIOSH is committed to working with the Department of Labor to reopen and rework the dose reconstruction, as appropriate. A Program Evaluation Plan (PEP) describes plans for evaluating specific program details or issues.

  • PER 11: K-25 TBD and TIB Revisions
    this document in PDF PDF 17 KB (2 pages)

    Document Number: OCAS-PER-0011 Rev-00

    About this Document: New document to determine which previously completed claims require a new dose reconstruction as a result of changes to the K-25 dose reconstruction methods.

    Approved: September 26, 2007

    Summary: There were 432 claims completed by NIOSH between 11/24/2004 and 8/31/2006 that resulted in a POC less than 50%. This does not include claims that may have been submitted in that time frame but subsequently returned to NIOSH for any reason. All these claims will be reviewed by NIOSH to determine if external co-worker data was used. NIOSH will request that DOL return those claims completed before 5/21/2005 determined to have been completed using external co-worker data. NIOSH will also request the return of those claims completed with external co-worker data between 5/21/2005 and 8/31/2006 if they are deemed a Construction Trades worker. DOL will be provided with documentation for the remaining claims indicating the claim did not meet these criteria.


Top of Page

Worker Outreach Activities

Based on a recommendation from the Advisory Board to provide workers and site experts with opportunities to participate in developing the technical documents used in dose reconstruction, NIOSH established a Worker Outreach Program.

At Worker Outreach Meetings, current and former DOE and AWE employees have opportunities to obtain information about Site Profiles, Technical Basis Documents, and Technical Information Bulletins, and to provide information for consideration and possible use in dose reconstruction. This process is valuable to ensure that the technical documents used in dose reconstruction contain correct and useful information.

Below are the Worker Outreach Activities for the K-25 Site:

  • April 6, 2005
    Meeting with PACE Local 5-288 and International Unions

    Final Minutes
    this document in PDF PDF 45 KB (10 pages)

  • April 5, 2005
    Meeting with Security, Police, and Fire Professionals of America; International Guards Union of America

    Final Minutes
    this document in PDF PDF 67 KB (9 pages)

Top of Page

Comments on K-25 Site Documents

How to Submit Comments
Comments on K-25 Site documents can be submitted to the NIOSH Docket Officer electronically by e-mail at NIOCINDOCKET@cdc.gov or printed comments can be mailed to NIOSH Docket Office, Robert A. Taft Laboratories, MS-C34, 4676 Columbia Parkway, Cincinnati, OH 45226. Please include the Site Profile Number (026) on all comments.

Comments Received

At this time, no comments have been submitted on K-25 Site documents.

Top of Page

Special Exposure Cohort Petition Information for K-25 Site

  • Submissions Not Qualifying for Evaluation
    In addition to the petition listed below, two additional submissions were received but did not qualify for evaluation because the class defined in the submission was already included in the SEC.


  • Class Added to the SEC
    • Gaseous Diffusion Plants--employees who worked at least 250 days before February 1, 1992, at a gaseous diffusion plant in Paducah, Kentucky; Portsmouth, Ohio; or Oak Ridge, Tennessee and who were or could have been monitored in those jobs using dosimetry badges

      Note: The SEC was established by The Act. The K-25 Site was one of the classes that Congress included when The Act was signed.

Top of Page

Previous Versions of K-25 Site Documents

  • Site Profile: Introduction
    Approved January 6, 2004
    this document in PDF PDF 89 KB (5 pages)


  • Site Profile: Site Description
    Approved January 12, 2004
    this document in PDF PDF 176 KB (14 pages)


  • Site Profile: Occupational Medical Dose
    (Approved June 29, 2004)
    this document in PDF PDF 165 KB (12 pages)


  • Site Profile: Occupational Environmental Dose
    • Page Change Revision September 26, 2006
      this document in PDF PDF 205 KB (21 pages)

      Page Change Revision Includes: Approved page change revision to include new standard language on page 6 in Section 4.1. Adds reference to page 13 in Reference Section. No sections were deleted. No changes occurred as a result of internal formal review.

      OCAS comment was addressed. No changes were required due to the K25 Worker Outreach SPFPA and IGUA Worker Outreach meeting held on April 5, 2006 or K25 Worker Outreach PACE Local 5-288 and Pace International Union Worker Outreach meeting held on April 6, 2006. However, the document previously addressed the following comments:

      From K25 Worker Outreach SPFPA and IGUA Worker Outreach meetings April 5, 2006-Response to Comment #30: Atmospheric releases are addressed in Section 4.2.1.

      From K25 Worker Outreach PACE Local 5-288 and Pace International Union Worker Outreach comments April 6, 2006-Response to Comment #4: Fires are discussed in the reference "DOE (U.S. Department of Energy), 2000b, Independent Investigation of the East Tennessee Technology Park." Response to Comment #33: Atmospheric releases of Uranium and other radioactive materials are addressed in Section 4.2.1. Response to Comment #45: Because of the known limitations of air monitoring environmental intakes are calculated based on releases of materials; this is discussed in Section 4.2. Response to Comment #46: As documented in Section 4.3.1, neutron exposures were not reported for environmental results until 2003.

      This revision results in no change to the assigned dose.


    • Approved December 29, 2004
      this document in PDF PDF 191 KB (19 pages)

  • Site Profile: Occupational Internal Dose

    • Revised January 6, 2006
      this document in PDF PDF 204 KB (24 pages)

      Revision Includes: Incorporates recent direction from NIOSH to include DOL review comments in the Introduction. Incorporates information on bioassay codes provided by Task 5 in sections 5.3.2 and 5.4.2; adds Attachments A, B, C. Deletes reference to Y-12 bioassay program from section 5.3.


    • Approved December 21, 2004
      this document in PDF PDF 180 KB (20 pages)

  • Occupational External Dose
    (Approved November 24, 2004)
    this document in PDF PDF 199 KB (24 pages)


  • Technical Information Bulletin: External Coworker Dosimetry Data for the K-25 Site

    • Revised July 29, 2005
      this document in PDF PDF 63 KB (10 pages)

      Document Number: ORAUT-OTIB-0026 Rev-00 PC-1

      Revision Includes: Page change incorporates recent direction from NIOSH regarding the calculation and use of coworker doses to pages 7, 8, 9, and 10. Text was modified in Sections 6.0 and 7.0. No sections were deleted.

    • Approved May 31, 2005
      this document in PDF PDF 63 KB (10 pages)

      Document Number: ORAUT-OTIB-0026 Rev-00

  • Technical Information Bulletin: Internal Dosimetry Coworker Data for K-25
    Approved August 9, 2005
    this document in PDF PDF 223 KB (15 pages)

    Document Number: ORAUT-OTIB-0035 Rev-00

Top of Page

Page last updated: September 28, 2007
Page last reviewed: May 30, 2008
Content Source: National Institute for Occupational Safety and Health (NIOSH)

Find It !
On this page...
Site Profile
Technical Information Bulletins (TIBs)
Program Evaluation Reports (PERs) and Program Evaluation Plans (PEPs)
Worker Outreach Activities
Comments on K-25 Site Documents
Special Exposure Cohort Petition Information for K-25 Site
Previous Versions of K-25 Site Documents
Claimant Corner
Claim Information
Commonly Used Acronyms
FAQs
General Activities on AWE Cases
General Activities on DOE Cases
Help A-Z
List of Work Sites
Phone Interview Information
OCAS Print Materials
Status of Your Dose Reconstruction
OCAS Directory
About OCAS
The Act (EEOICPA)
Advisory Board
Conflict or Bias Policy and Disclosure Statements
Dose Reconstruction
Help A-Z
Latest Update to OCAS Web Site
Probability of Causation
(NIOSH-IREP)

Program Evaluation Reports (PERs) and Program Evaluation Plans (PEPs)
Public Meetings
Regulatory Record
(Public Docket)

Related Links
Special Exposure Cohort
Technical Documents Used in Dose Reconstruction
Timeline of Major OCAS Events