Recreation Facility Modernization 2005-2006

The US Army Corps of Engineers at Rathbun Lake completed a $500,000 Recreation Facility Modernization Program in 2006. Most new facilities have been completed. A few facilities are under construction and will be completed by May 2006.

General Facility Improvement Plan

  1. 127 new 50 amp electrical pedestals at non-electric campsites
  2. Replace 53 deteriorated 30-amp pedestals with 50-amp pedestals
  3. Renovate and enlarge 105 campsites
  4. 2 new trailer dump stations (6 total stations)
  5. 6 new water hydrants and water lines
  6. New rinse station at swimming beach
  7. 2 new playgrounds
  8. New swimming beach

Details by Park

  1. Island View Park
    1. Replace 41 30-amp pedestals w/50-amp pedestals (IV D loop 1-45, replace with 41 sites, enlarge all of 41 campsites)
    2. Add 69 new 50-amp pedestals (IV E loop 13,14,16-65 replace with 25 sites; IV B loop 1-5, 10-20, 26-35, 67-73 replace with 44 sites), enlarge all 69 campsites
    3. New four-station trailer dump station (near park entrance booth)
    4. Add six new water hydrants and water lines to B, D and E loops
    5. New water line and rinse station at swimming beach under construction
    6. New playground (Dedication Site shelter area)
    7. Replace twelve 30-amp pedestals with 50-amp pedestals (IV group camp)
    8. Add two 50-amp pedestals at shelter in IV group camp
  2. Buck Creek Park
    1. New two-station trailer dump station (near park entrance station)
    2. New swimming beach, 100 car parking lot, picnic sites (Cedar Circle)
  3. Bridgeview Park
    1. 16 new 50-amp pedestals (F loop, enlarge 12 campsites, build 4 new sites)
    2. New playground (A loop)
  4. Prairie Ridge Park
    1. 26 new 50-amp pedestals (A loop, enlarge all 26 sites)
    2. Enlarge 3 campsites (B 20-25), add 8 new campsites (B loop)
    3. Add sixteen 50-amp pedestals (B loop)
If you have any questions, please contact the Corps of Engineers at 641-647-2464 or email: Rathbun@usace.army.mil

Page last updated:

USACE Home Page USACE Civil Works NWD Home Page NWD Home Page NWK Home Page NWK Operations Page One Door Instructions District Civil Works Site Marker Operations Manager, Rathbun Project Office
20112 Hwy J5T
Centerville, IA 52544
Phone: 641-647-2464

U.S. Army Corps of Engineers
Kansas City District
601 E 12th Street
Kansas City, Mo 64106

Public Affairs
Webmaster