Milestones | Schedule Date | Actual Date |
---|---|---|
Receive license renewal application (LRA) |
01/08/08 |
01/08/08 |
Publish Federal Register Notice (FRN) - LRA availability |
01/31/08 |
01/31/08 |
Public Meeting - license renewal overview |
03/04/08 |
03/04/08 |
Publish FRN - acceptance/rejection and opportunity for hearing |
03/13/08 |
03/14/08 |
Publish FRN - environmental scoping meeting |
03/24/08 |
03/28/08 |
Audit – Environmental |
04/28/08 |
04/28/08 |
Public Meeting - environmental scoping meeting |
05/01/08 |
05/01/08 |
Deadline for filing hearing requests and petitions for intervention |
05/13/08 |
05/13/08 |
Environmental scoping period ends |
05/30/08 |
05/30/08 |
Audit – Scoping & Screening Audit Methodology |
05/19/08 |
05/19/08 |
Audit – Aging Management Programs |
07/28/08 |
07/28/08 |
Issue draft supplemental environmental impact statement (SEIS) |
12/04/08 |
|
Publish FRN - draft SEIS available for comments |
12/19/08 |
|
Public Meeting - draft SEIS meeting |
01/28/09 |
|
Issue safety evaluation report (SER) with open items |
02/09/09 |
|
End of draft SEIS comment period |
03/04/09 |
|
Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting |
04/01/09 |
|
Issue final SER |
07/13/09 |
|
Issue final SEIS |
07/15/09 |
|
U.S. Environmental Protection Agency FRN Published - availability of final |
07/24/09 |
|
ACRS full committee meeting |
09/2009 |
|
Decision – Director, Office of Nuclear Reactor Regulation (22 months if no |
11/06/09 |
|
Commission decision (30 months if hearing) |
07/08/2010 |
|
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
TMI Unit 1 PMs | |
---|---|
License Renewal | Jay Robinson |
License Renewal | Sarah Lopas |
Lead Power Plant | Peter Bamford |
Privacy Policy |
Site Disclaimer |