skip navigation links 
 
 Search Options 
Index | Site Map | FAQ | Facility Info | Reading Rm | New | Help | Glossary | Contact Us blue spacer  
secondary page banner Return to NRC Home Page
Plant Applications for License Renewal
Arkansas Nuclear One,
Unit 1
Arkansas Nuclear One,
Unit 2
Beaver Valley
Browns Ferry
Brunswick
Calvert Cliffs
D.C. Cook
Dresden and Quad Cities
Edwin I. Hatch
Farley
FitzPatrick
Fort Calhoun
Ginna
Harris
Indian Point
Kewaunee
McGuire and Catawba
Millstone
Monticello
Nine Mile Point,
Units 1 and 2
North Anna and Surry
Oconee
Oyster Creek
Palisades
Peach Bottom
Pilgrim
Point Beach
Prairie Island, Units 1 and 2
Robinson
St. Lucie
Summer
Susquehanna
Three Mile Island, Unit 1
Turkey Point
Vermont Yankee
Vogtle
Wolf Creek

Kewaunee Power Station - License Renewal Application

Kewaunee Power Station

On this page:

Application Information:

The following links on this page are to documents in Adobe Portable Document Format (PDF). See our Plugins, Viewers, and Other Tools page for more information. For successful viewing of PDF documents on our site please be sure to use the latest version of Adobe.

(To top of page)

License Renewal Review Schedule*

*These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestones Schedule Date Actual Date

 Receive license renewal application (LRA)

TBD

 

 Publish Federal Register Notice (FRN) - LRA availability

TBD

 

 Publish FRN - acceptance/rejection and opportunity for hearing

TBD

 

 Publish FRN - environmental scoping meeting

TBD

 

 Audit – Environmental

TBD

 

 Public Meeting - License Renewal Overview and Environmental Scoping meeting

TBD

 

 Deadline for filing hearing requests and petitions for intervention

TBD

 

 Environmental scoping period ends

TBD

 

 Audit – Scoping & Screening Audit Methodology

TBD

 

 Audit – Aging Management Programs

TBD

 

 Issue draft supplemental environmental impact statement (SEIS)

TBD

 

 Publish FRN - draft SEIS available for comments

TBD

 

 Public Meeting - draft SEIS meeting

TBD

 

 Issue safety evaluation report (SER) with open items

TBD

 

 End of draft SEIS comment period

TBD

 

 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting

TBD

 

 Issue final SER

TBD

 

 Issue final SEIS

TBD

 

 U.S. Environmental Protection Agency FRN Published - availability of final SEIS

TBD

 

 ACRS full committee meeting

TBD

 

 Decision – Director, Office of Nuclear Reactor Regulation (22 months if no hearing)

TBD

 

 Commission decision (30 months if hearing)

TBD

 

(To top of page)

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

(To top of page)

Project Managers for Kewaunee Power Station

Kewaunee Power Station PMs
License Renewal John Daily
License Renewal Sarah Lopas
Lead Power Plant Peter Tam