R.E. Ginna Nuclear Power Plant -
License Renewal Application
Renewed License Issued 05/19/04
On this page:
Application Information:
The following links on this page are to documents in Adobe Portable Document
Format (PDF). See our Plugins, Viewers, and
Other Tools page for more information. For successful viewing of PDF documents on our site please be sure to use the latest version of Adobe.
License Renewal Review Schedule*
* These schedules reflect work plans that are subject to change. Early
completion of a milestone may affect the target date of future milestones.
Subsequent meetings and comment periods may change based on the revised
schedule. This work plan will be updated on a periodic basis. Please see
the NRC Public Meetings
Page or contact the listed PM for the latest
information on meetings and status.
Milestones |
Schedule Date |
Actual Date |
Receive License Renewal Application |
08/01/02 |
08/01/02 |
FRN Published for Receipt & Acceptability |
08/30/02 |
08/26/02 |
FRN Published for Acceptance/Rejection/Opportunity for Hearing of LRA |
09/30/02 |
09/30/02 |
FRN Published for Intent/Environmental Scoping Mtg |
10/10/02 |
10/10/02 |
Deadline for Filing Hearing Requests and Petitions for Intervention |
10/30/02 |
10/30/01 |
Environmental Scoping Meeting |
11/06/02 |
11/06/02 |
Environmental Scoping Period Ends |
12/11/02 |
12/11/02 |
Scoping and Screening Methodology Audit Complete |
12/13/02 |
12/13/02 |
Environmental RAIs Issued |
01/15/03 |
01/15/03 |
Environmental RAI Responses Received |
03/14/03 |
03/13/03 |
Safety RAIs Issued |
03/28/03 |
03/21/03 |
Safety RAI Responses Received |
06/12/03 |
06/12/03 |
Draft Supplemental Environmental Impact Statement Issued |
06/25/03 |
06/25/03 |
Scoping Inspection Complete |
06/27/03 |
06/27/03 |
FRN Published for Availability/Comment on Draft SEIS |
07/02/03 |
07/03/03 |
Public Mtg to Discus Draft SEIS |
08/07/03 |
08/07/03 |
Aging Management Review Inspection Complete |
08/15/03 |
08/08/03 |
End of Draft SEIS Comment Period |
09/16/03 |
09/16/03 |
SER with Open Items Issued |
10/09/03 |
10/09/03 |
ACRS Subcommittee Mtg on SER with Open Items |
11/04/03 |
11/04/03 |
SER Open Item Responses Received |
12/24/03 |
12/24/03 |
Optional Final Inspection Complete |
01/04 |
--- |
Final SEIS Issued |
02/06/04 |
01/23/04 |
FRN Published for availability of Final SEIS |
02/13/04 |
02/13/04 |
SER Issued |
03/08/04 |
03/03/04 |
Regional Administrator's Letter Issued |
03/19/04 |
03/18/04 |
ACRS Full Committee Mtg on SER |
04/16/04 |
04/16/04 |
ACRS Letter Issued |
04/04 |
04/23/04 |
Staff Recommendation to Director, NRR |
05/28/04 |
05/13/04 |
Decision - Director, NRR (license issued, if approved) |
06/04/04 |
05/19/04 |
Environmental Impact Statement
NUREG-1437, "Generic Environmental Impact Statement for License Renewal
of Nuclear Plants," Supplement
14, Regarding R.E. Ginna Nuclear Power Plant, was published February
2004.
This supplement documents the NRC staff's review of the environmental
issues at Ginna in support of the Rochester Gas and Electric's (RGE) application
for license renewal of that facility. The supplement was prepared in accordance
with 10 CFR 51.71. This supplemental environmental impact statement includes
the staff's analysis that considers and weighs the environmental effects
of the proposed action, the environmental impacts of alternatives to the
proposed action, and alternatives available for reducing or avoiding adverse
impacts. It also includes the staff's recommendation regarding the proposed
actions.
Safety Evaluation Report
The NRC staff reviewed the Ginna license renewal application for compliance
with the requirements of Title 10 of the Code of Federal Regulations,
Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power
Plants," and prepared this report to document its findings. The
document was first issued in October 2003, as "License Renewal Safety
Evaluation Report for the R.E. Ginna Nuclear Power Plant". The report
is available in ADAMS under accession number ML032820021.
In May 2004, the report "Safety Evaluation Report - Related to the
License Renewal of the R. E. Ginna Nuclear Power Plant,"was issued
as NUREG-1786.
The report is also available in ADAMS under accession number ML040640687.
Public Involvement
The public is encouraged to participate in the reactor license renewal
process through public meetings, and public comment periods on rules,
renewal guidance, and other documents. The
Reactor License Renewal Public Involvement page provides general information
to help the public participate.
Date |
Description |
04/16/04 |
Meeting with RGE to discuss issues related to the Safety Evaluation
Report (SER) for the R. E. Ginna Nuclear Power Plant, License
Renewal Application
|
11/04/03 |
Meeting with RGE to discuss issues related to the Safety Evaluation
Report (SER) with open items for the R. E. Ginna Nuclear Power
Plant, License Renewal Application
|
10/22/03 |
Meeting with RGE to present the results of the NRC's second
regional inspection (Aging Management Review) of the company's
license renewal program at R. E. Ginna Nuclear Power Plant.
|
08/07/03 |
Meeting with RGE to discuss the Draft Environmental Impact Statement (EIS) for the
R. E. Ginna Nuclear Power Plant, License Renewal.
|
07/08/03 |
Meeting with RGE to present the results of the NRC's first
regional inspection (Scoping and Screening) of the company's license
renewal program at R. E. Ginna Nuclear Power Plant.
|
05/22/03 |
Meeting with RGE to discuss the pressurizer surge line fatigue
analysis for the R. E. Ginna Nuclear Power Plant.
|
02/10/03 02/11/03 |
Meeting with RGE to discuss the draft request for additional
information for the R. E. Ginna Nuclear Power Plant license renewal.
- Notice
***REVISED SEE NOTICE FOR 02/03/03 & 02/04/03***
|
02/03/03 02/04/03 |
Meeting with RGE to discuss the draft request for additional
information (RAI) for the R. E. Ginna Nuclear Power Plant license
renewal.
|
12/17/02 |
Meeting with Rochester Gas and Electric (RGE) to discuss the
details regarding installation of an automated fatigue monitoring
system, Fatigue Pro, at the R. E. Ginna Nuclear Power Plant used
to quantify fatigue calculation for the pressurizer surge line.
|
12/13/02 |
Meeting with the Rochester Gas and Electric (RGE) to discuss
the results of the NRC's initial inspection (Scoping Methodology)
of the Company's license renewal program at Ginna Nuclear
Power Plant.
|
11/06/02 |
Meeting to discuss the Environmental Scoping Process for the
Ginna Nuclear Plant License Renewal Application.
|
10/15/02 |
Meeting with Rochester Gas and Electric (RGE) to discuss the
electrical area of the license renewal application.
|
08/27/02 |
Meeting with Rochester Gas and Electric (RGE) to provide the
Nuclear Regulatory Commission (NRC) staff with an overview of
the Ginna Nuclear Power Plant License Renewal Application.
|
|