MMS United States Department of the Interior
OCS-Related Incidents -- Offshore Energy and Minerals Management

Offshore Minerals Management home page
Safety-Related Information
Offshore Stats and Facts
OCS-Related Incidents
spacer
Abbreviations and Acronyms
Collisions
Crane Incidents
Fatalities
Fires/Explosion
Incident Reporting
Incident Statistics Summaries
Incidents 1996-2005
Injuries
Loss of Well Control
Other Incidents
Pipeline Incident
Spills 1996-2008
Spills 1994-1995
spacer
Privacy Act/Disclaimers
Minerals Commodities Revenue Statistics
spacer

 Content:
   
Cheryl Anderson

 Pagemasters:
    OMM Web Team

spacer

  Gulf of Mexico Region

Spills ≥ 50 Barrels (2,100 gallons)1976

February 29, 1976 - Gulf Oil Corporation Corporation/Chevron

Pollution: 414 bbl Crude Oil Operation: Pipeline
Rig/Platform: Platform D Lease: N/A
Area:
Block:
South Timbalier
130
Cause: External Damage & Leak: anchor & corrosion
Distance to Shore: 28 Miles Water Depth: 160 Feet
Pipeline Segment: 03573 Pipeline Diameter: 18 Inches

Remarks: Several leaks caused by internal corrosion were discovered in the submerged gathering line from the platform to the Bay Marchand shore facility. The initial leak was in state waters snagged by boat anchor. Other leaks were in Federal waters. Response: repairs were made by replacing pipe where needed. (The 443 bbl spilled may be the spillage in Federal waters only--a 10 bbl spill recorded the same day in BM 3 is possibly the state portion.)


October 19, 1976 - Chevron Oil Company

Pollution: 300 bbl Diesel Operation: Drilling & Motor Vessel
Rig/Platform: Platform B Lease: G02076
Area:
Block:
Vermilion
214
Cause: Equipment Failure & Human Error: transfer hose & negligence
Distance to Shore: 57 Miles Water Depth: 127 Feet
Other Events: Vessel Mishap

Remarks: A loading hose broke while diesel fuel was being pumped from the motor vessel D.V. Levy to the B platform. Break was not detected for some time. Response: shut off pump.


December 18, 1976 - Penzoil Company & Placid

Pollution: 4,000 bbl Crude Oil Operation: Pipeline
Rig/Platform: Tie-in of Placid and Pennzoil pipelines Lease: N/A
Area:
Block:
Eugene Island
297
Cause: External Damage: shrimp trawl
Distance to Shore: 71 Miles Water Depth: 210 Feet
Pipeline Segment: 01184 Pipeline Diameter: 10 Inches

Remarks: A shrimp trawl was dragged across the submerged tie-in where Placid's 10" pipeline joins Pennzoil's 14" Bonita pipeline, pulling loose a one-inch ball valve and nipple. Response: installed one 1" ball valve on the 10" oil pipeline.