FDCCLANT WEEKLY REPORT
05 August 2008
FORMAT NOTES:
CG Academy, CT: CONSTRUCT CHASE HALL ANNEX E (PHASE I), (60-L8001), (D/B, $14,100K, FY06 AC&I: 99% construction completed to date. Project scope is to design and build a 4-story, 70,000 GSF Annex E to Chase Hall (cadet barracks) to include support spaces and 150 berthing rooms. RFP issued last week for additional retaining wall fencing, vehicle guard rail and misc. items in the building. Proposal received from contractor 30 July is under review.
Award Date: 02MAY06. RCCD: 01SEP08 (Originally 25JAN08)
Contractor: Nutmeg Companies Inc. / A/E: EYP (Einhorn/Yaffee/Prescott)
Award Date: 15AUG06 RCCD: 09NOV08 (Originally 24JUN08)
Contractor: Diversified Technology Consultants (DTC)
STA
73% construction completed to date. Project scope is to
design and construct a 4,100 GSF Command and
Award Date: 05JUN06. CCD: 13JAN08.
Contractor: Marco Enterprises, Inc. / EBL Engineering
STA Fire Island, NY: WATERFRONT REHAB, (01-L00010, D/B, $1049K, FY07 AC&I), (01-P00264, D/B, $1,045K, FY07 AFC43): 99% (original) construction completed to date (mod work to start in July). Project scope includes demolition or repair of various deteriorated waterfront structures and construction of new wave barrier, pier and bulkheads. New fuel tank and shore tie from original contract will be installed week of 18AUG08.
Award date: 08MAR07 RCCD: 12OCT08(originally 02DEC07).
Contractor:
CGC Mackinaw, Cheboygan, MI: SITE IMPROVEMENTS, (09-364676), (D/B, $865K, FY06 AC&I Vessels): 100% construction completed to date (not including the storage building). Project scope includes providing security fence with gate, flagpole, landscaping, replacement of existing storage building, and performing other miscellaneous site work. Final inspection of all work except storage building conducted successfully on 06 DEC07. Final inspection of the storage building conducted successfully on 16JUL08. The Contractor is working on completing the remaining punch list items.
Award Date: 25JAN07 RCCD: 30NOV07 (originally 06NOV07). Storage Bldg CCD 14JUL08
Contractor: BRIX Corporation
STA Marquette, MI: Rebuild Boat Station, (09-L00002), (D/B,
$6.0M, FY08 AC&I): 8% construction completed to
date. Scope of work is to construct a
new Station building (7,500 GSF) and Boathouse (3,000 GSF) on land acquired
from the City of
Award Date: 08APR08 RCCD:
15JUN09 (originally 05MAY09)
Contractor: Viteri Construction
Management, Inc.
Hurricane projects
STA
Project
is 75% complete. Project scope is to rebuild multi-mission Station Gulfport
(26,000 GSF) and associated utilities, roadways, and parking facilities.
on 2nd Floor – 75%, GWB Installation on 3rd Floor – 80%, GWB Finishing on 3rd Floor – 10%, Installation of Architectural Glass Blocks – 90%, Plumbing Rough-In – 95%, Electrical Rough-In – 95%, Sprinkler Rough-In – 75%, Elevator – 50%, Insulation for Ducts & Piping – 75%. Site Fill, Gravel, Pavement Prep – 70%. Roof Framing and Insulation – 100%, Installation of Roof Standing
Seam Metal Panels (colored panels) scheduled for mid August.
Award Date: 31JAN07
CCD: 24OCT08
Contractor:
Tesoro Corporation
Station Building – 4 pages
ISC
Project scope is to reconstruct approximately 130,000 GSF of buildings, waterfront facilities, and all associated utilities, roadways, security, and parking areas to house ISC NOLA functions and tenant commands on 26 acres at the NASA Michoud Assembly Facility installation. Field surveying and test piles continue, construction trailers installed, buildings pads grubbed, sand fill for Administrative Bldg. underway, hard road graveled. Pile driving scheduled for 06AUG08. Progress Mtg. No. 1 scheduled for 13AUG08.
Award Date: 17APR08
CCD: 01JUL2010
Contractor: Broadmoor / Boh Brothers Construction
Site – 4 pages
SECTOR
The scope of the contract
is to design and construct a new 46,000 GSF facility collocating the Sector
Command Cadre,
Award: 11JUN08
CCD: 17DEC09
Contractor: IKBI, Inc.
Reimbursable projects
USDA PLUM ISLAND, NY:
UPGRADE POWER PLANT, (N32-0089), ($12.1M, USDA): 98% construction completed to date. Project scope provides for new electrical
feed from Long Island (LIPA) and emergency power generation capability via
diesel generators for
Contractor: Danaco
Contractors, Inc.Re-procurement Contractor: Tesoro Corp.
Sector
Award Date: 20SEP07 CCD: 08FEB09
Contractor: Tesoro Corporation
Phase
II Steel Work and Block Wall
Department of Homeland Security:
Award Date: 21NOV07. CCD: (Bldg 19) 14DEC08 (was 10DEC08); (Bldg 61) 27FEB09
Contractor: Tesoro Corporation
Bldg 61 - Plumbing lines before concrete is installed in thick slab
Boston Lighthouse: NEW ACCESS TO LITTLE BREWSTER ISLAND,
(01-L03050), (D/B, $1.4M, NPS): Project scope is to
provide improved waterfront access to island.
Majority of structure fabrication work will be accomplished off site at
fabrication shop in
Contractor: Atlantic Mechanical
USCG FINCEN, Chesapeake VA: PROVIDE 80 KVA UPS TO COMPUTER CENTER, (N32-0111) , (BID/BUILD $164K AFC30): Project scope is to provide an additional 80KVA uninterruptible power supply (UPS) unit to FINCEN’s server room. 25% construction completed to date. Contractor has installed interior conduit. Proposed location or new UPS and panel schedule revision are under review. New UPS is expected week of 04AUG08.
Award Date: 16MAY08 CCD: 29AUG08
Contractor: York River Electric, Inc.