The timeline for completion of each work package task is shown in the following table. It is anticipated that data compilation, collection, and analysis tasks will be completed no later than the beginning of the fourth quarter of FY2006. Most data collection tasks will be completed prior to that time, except for the evapotranspiration task, which is planned for data collection through two growing seasons (May-June of 2005 and 2006). Report preparation will begin for many tasks by mid-fiscal year 2006 and is scheduled for completion by November 2007 (1st quarter of fiscal year 2008).

Major Tasks
Fiscal Year 2005
Fiscal Year 2006
Fiscal Year 2007
1
2
3
4
1
2
3
4
1
2
3
4
Geology
Regional Influences                        
Geophysical Studies                        
Aquifer Properties                        
Recharge and Discharge
Recharge                        
Springflow/streamflow                        
Pumpage                        
Evapotranspiration                        
Chemical Partitioning                        
Potentiometric Map
Map production                        
Geochemistry
Data Compilation                        
Sampling                        
Modeling                        
Data Integration
Web Site                        
Database                        
GIS Coverages                        
Data Synthesis and Evaluation
Water Budget                        
Conceptual Model                        
Report Preparation                        

 