NASA Commercial Crew Program:
Schedule Uncertainty Persists for Start of Operational Missions to the International Space Station
GAO-19-504: Published: Jun 20, 2019. Publicly Released: Jun 20, 2019.
Additional Materials:
- Highlights Page:
- Full Report:
- Related WatchBlog Post:
Contact:
(202) 512-4841
chaplainc@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
NASA contracted with two companies, Boeing and SpaceX, to develop vehicles to transport astronauts to the International Space Station.
Before any missions can happen, NASA will have to certify that both contractors' vehicles are safe for human spaceflight. But both contractors have run into chronic delays. While both contractors originally planned to be certified in 2017, now neither is expected to be ready until late 2019 at the earliest.
NASA has bought seats on a Russian vehicle to ensure U.S. access to the space station through September 2020, but does not have a plan if delays persist past then.
Artist depiction of contractors' crew vehicles near the International Space Station
Artist depiction of the contractors' vehicles and the International Space Station above the Earth
Additional Materials:
- Highlights Page:
- Full Report:
- Related WatchBlog Post:
Contact:
(202) 512-4841
chaplainc@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
Both of the Commercial Crew Program's contractors, Boeing and SpaceX, have made progress on their crew transportation systems. However, neither is ready to begin carrying astronauts into space as both continue to experience delays to certification. Certification is a process that the National Aeronautics and Space Administration (NASA) will use to ensure that each contractor's spacecraft, launch vehicle, and ground support systems meet its requirements for human spaceflight before any operational missions to the International Space Station (ISS) can occur. Factors contributing to schedule uncertainty include:
Fluctuating schedules. As the contractors continue to build and test hardware—including SpaceX's March 2019 uncrewed test flight— their schedules for certification change frequently. As of May 2019, both contractors had delayed certification nine times, equating to more than 2 years from their original contracts (see figure). This includes several delays since GAO last reported in July 2018.
Commercial Crew Program: Contractor Certification Delays as of May 2019
aGAO reported that Boeing's current proposed certification date was January 2019 and SpaceX's was February 2019. See GAO-18-476.
Program Workload. NASA's ability to process certification data packages for its two contractors continues to create uncertainty about the timing of certification. The program has made progress conducting these reviews but much work remains. In addition, the program allowed both contractors to delay submitting evidence that they have met some requirements. This deferral has increased the amount of work remaining for the program prior to certification.
In February 2019, NASA acknowledged that delays to certification could continue, and announced plans to extend U.S. access to the ISS through September 2020 by purchasing seats on the Russian Soyuz vehicle. However, this arrangement does not fully address GAO's July 2018 recommendation to develop a contingency plan for ensuring access to the ISS until a Commercial Crew Program contractor is certified. NASA concurred with the recommendation but has not yet implemented it. Continued NASA attention on this issue is needed given the uncertainty associated with the final certification dates.
Why GAO Did This Study
In 2014, NASA awarded two firm-fixed-price contracts to Boeing and SpaceX, worth a combined total of up to $6.8 billion, to develop crew transportation systems and conduct initial missions to the ISS. In July 2018, GAO found that both contractors continued to delay their certification dates and that further delays were likely. NASA must certify the contractors' crew transportation systems before the contractors can begin operational missions to the ISS. The contractors were originally required to provide NASA all the evidence it needed to certify that their systems met its requirements in 2017.
The House Committee on Appropriations included a provision in its 2017 report for GAO to continue to review NASA's human space exploration programs. This is the latest in a series of reports addressing the mandate. This report examines the extent to which the Commercial Crew Program and its contractors have made progress towards certification.
To do this work, GAO analyzed contracts, schedules, and other documentation and spoke with officials from the Commercial Crew Program, Boeing, and SpaceX.
What GAO Recommends
GAO continues to believe that NASA should develop a contingency plan to ensure uninterrupted access to the ISS if delays persist beyond September 2020. NASA generally agreed with GAO's findings.
For more information, contact Cristina T. Chaplain at (202) 512-4841 or chaplainc@gao.gov.
Dec 22, 2020
-
Commercial Space Transportation:
FAA Should Examine a Range of Options to Support U.S. Launch InfrastructureGAO-21-154: Published: Dec 22, 2020. Publicly Released: Dec 22, 2020.
Dec 15, 2020
-
NASA Human Space Exploration:
Significant Investments in Future Capabilities Require Strengthened Management OversightGAO-21-105: Published: Dec 15, 2020. Publicly Released: Dec 15, 2020.
Apr 30, 2020
-
Priority Open Recommendations:
National Aeronautics and Space AdministrationGAO-20-526PR: Published: Apr 23, 2020. Publicly Released: Apr 30, 2020.
Apr 29, 2020
-
NASA:
Assessments of Major ProjectsGAO-20-405: Published: Apr 29, 2020. Publicly Released: Apr 29, 2020.
Jan 29, 2020
-
NASA Commercial Crew Program:
Significant Work Remains to Begin Operational Missions to the Space StationGAO-20-121: Published: Jan 29, 2020. Publicly Released: Jan 29, 2020.
Jan 28, 2020
-
James Webb Space Telescope:
Technical Challenges Have Caused Schedule Strain and May Increase CostsGAO-20-224: Published: Jan 28, 2020. Publicly Released: Jan 28, 2020.
Dec 19, 2019
-
NASA Lunar Programs:
Opportunities Exist to Strengthen Analyses and Plans for Moon LandingGAO-20-68: Published: Dec 19, 2019. Publicly Released: Dec 19, 2019.
Sep 18, 2019
-
NASA:
Actions Needed to Improve the Management of Human Spaceflight ProgramsGAO-19-716T: Published: Sep 18, 2019. Publicly Released: Sep 18, 2019.
Jun 19, 2019
-
NASA Human Space Exploration:
Persistent Delays and Cost Growth Reinforce Concerns over Management of ProgramsGAO-19-377: Published: Jun 19, 2019. Publicly Released: Jun 19, 2019.
May 30, 2019
-
NASA:
Assessments of Major ProjectsGAO-19-262SP: Published: May 30, 2019. Publicly Released: May 30, 2019.
Looking for more? Browse all our products here