NASA:
Assessments of Major Projects
GAO-20-405: Published: Apr 29, 2020. Publicly Released: Apr 29, 2020.
Multimedia:
-
PODCAST: 2020 NASA Major Projects Quick Look
Cristina Chaplain is with the Watchdog Report to discuss GAO's annual look at the costs and schedules for NASA's major projects.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-4841
chaplainc@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
In our 12th annual Quick Look at the status of NASA's major projects, we found costs grew for the third year in a row. NASA’s acquisition management is on our High Risk List.
We expect cost increases and schedule delays for major programs to get worse. For example, delays are likely for the Artemis I mission, NASA’s next step in returning astronauts to the moon in 2024. NASA is also planning other lunar-related efforts that will become major projects. These efforts are complex and could face significant cost increases and schedule delays.
Our report also provides snapshot profiles of 24 of NASA’s major projects.
Crew Capsule Launch Abort System at Kennedy Space Center to Support Artemis Missions
NASA facility
Multimedia:
-
PODCAST: 2020 NASA Major Projects Quick Look
Cristina Chaplain is with the Watchdog Report to discuss GAO's annual look at the costs and schedules for NASA's major projects.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Version:
Contact:
(202) 512-4841
chaplainc@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
The National Aeronautics and Space Administration's (NASA) portfolio of major projects continued to experience significant cost and schedule growth this year and the performance is expected to worsen. Since GAO last reported on the portfolio in May 2019, cost growth was approximately 31 percent over project baselines—the third consecutive year that cost growth has worsened after a period of decline. The average launch delay was 12 months, compared to 13 months last year. See figure.
Development Cost Performance and Average Launch Delay for Major NASA Projects from Fiscal Year 2010 through Fiscal Year 2020
Additional cost growth and schedule delays are likely after NASA establishes a new launch date for Artemis I—an uncrewed test flight of the Space Launch System, Orion crew capsule, and associated ground systems. Further, in 2019, GAO found that the Space Launch System (SLS) and Orion programs have underreported cost growth. GAO recommended that SLS calculate cost growth based on costs that are currently included in the first mission and that the Orion program update its cost estimate to reflect the schedule agreed to in its baseline. Both recommendations still require action to address. Looking ahead, NASA will continue to face significant cost and schedule risks as it undertakes complex efforts to return to the moon under an aggressive time frame.
NASA has taken actions to identify and address challenges contributing to its chronic difficulty meeting cost and schedule goals. For example, in response to a GAO recommendation, NASA plans to broaden its use of a project management process known as earned value management. In addition, NASA plans to assess and update its cost and schedule estimates at more points in the acquisition process and bolster its training for analysts who oversee projects. Such actions will help to provide a better foundation for decision-making, but it will take time to assess the extent to which these efforts are having an effect. Further, GAO's work has found that success also hinges on leadership commitment, accountability, and demonstrated progress.
Why GAO Did This Study
This report provides GAO's annual snapshot of how well NASA is planning and executing its major acquisition projects. In May 2019, GAO found that the cost of NASA's major projects had grown by almost 28 percent since they were baselined with an average launch delay of 13 months.
Congressional conferees included a provision for GAO to prepare status reports on selected large-scale NASA programs, projects, and activities. This is GAO's 12th annual assessment. This report assesses (1) the cost and schedule performance of NASA's portfolio of major projects and (2) progress NASA has made identifying and addressing challenges that contribute to acquisition risk, among other objectives. This report also includes assessments of 24 major projects, each with a life-cycle cost of over $250 million using 2020 data. To conduct its review, GAO analyzed cost, schedule, technology maturity, and other data; reviewed project status reports; and interviewed NASA officials.
What GAO Recommends
GAO has made a number of recommendations over the last 5 years to improve NASA's acquisition of major projects. NASA has implemented changes in response to many of these recommendations, although 17 recommendations have not yet been fully addressed. NASA generally agreed with the findings in this report.
For more information, contact Cristina T. Chaplain at (202) 512-4841 or chaplainc@gao.gov.
Dec 22, 2020
-
Commercial Space Transportation:
FAA Should Examine a Range of Options to Support U.S. Launch InfrastructureGAO-21-154: Published: Dec 22, 2020. Publicly Released: Dec 22, 2020.
Dec 15, 2020
-
NASA Human Space Exploration:
Significant Investments in Future Capabilities Require Strengthened Management OversightGAO-21-105: Published: Dec 15, 2020. Publicly Released: Dec 15, 2020.
Apr 30, 2020
-
Priority Open Recommendations:
National Aeronautics and Space AdministrationGAO-20-526PR: Published: Apr 23, 2020. Publicly Released: Apr 30, 2020.
Jan 29, 2020
-
NASA Commercial Crew Program:
Significant Work Remains to Begin Operational Missions to the Space StationGAO-20-121: Published: Jan 29, 2020. Publicly Released: Jan 29, 2020.
Jan 28, 2020
-
James Webb Space Telescope:
Technical Challenges Have Caused Schedule Strain and May Increase CostsGAO-20-224: Published: Jan 28, 2020. Publicly Released: Jan 28, 2020.
Dec 19, 2019
-
NASA Lunar Programs:
Opportunities Exist to Strengthen Analyses and Plans for Moon LandingGAO-20-68: Published: Dec 19, 2019. Publicly Released: Dec 19, 2019.
Sep 18, 2019
-
NASA:
Actions Needed to Improve the Management of Human Spaceflight ProgramsGAO-19-716T: Published: Sep 18, 2019. Publicly Released: Sep 18, 2019.
Jun 20, 2019
-
NASA Commercial Crew Program:
Schedule Uncertainty Persists for Start of Operational Missions to the International Space StationGAO-19-504: Published: Jun 20, 2019. Publicly Released: Jun 20, 2019.
Jun 19, 2019
-
NASA Human Space Exploration:
Persistent Delays and Cost Growth Reinforce Concerns over Management of ProgramsGAO-19-377: Published: Jun 19, 2019. Publicly Released: Jun 19, 2019.
May 30, 2019
-
NASA:
Assessments of Major ProjectsGAO-19-262SP: Published: May 30, 2019. Publicly Released: May 30, 2019.
Looking for more? Browse all our products here