Coast Guard Acquisitions:

Opportunities Exist to Reduce Risk for the Offshore Patrol Cutter Program

GAO-21-9: Published: Oct 28, 2020. Publicly Released: Nov 12, 2020.

Additional Materials:

Contact:

Marie A. Mak
(202) 512-4841
makm@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

In 2018, Hurricane Michael devastated the shipyard where construction of the Coast Guard's Offshore Patrol Cutters was about to begin. The service needs the 25 new cutters soon to replace others that are more than 50 years old, but the hurricane added delays and cost.

The Coast Guard accepted significant risk with the design, schedule, and cost—both before and after the hurricane—to get the cutters built quickly. But the cutter's design is unstable, its schedule optimistic, and its cost estimate incomplete—making it likely that building it will take longer and cost more.

Our 8 recommendations could help set the program on a better path.

Rendering of the Coast Guard's Offshore Patrol Cutter

A Coast Guard Cutter underway off the coast of Florida.

Additional Materials:

Contact:

Marie A. Mak
(202) 512-4841
makm@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

What GAO Found

The Coast Guard divided the Offshore Patrol Cutter (OPC) program into two stages and revised its cost and schedule goals following widespread disruptions from Hurricane Michael in October 2018, which led the shipbuilder to request relief from certain requirements under contract. Under this revised plan, the current shipbuilder will build up to four OPCs in the first stage, while the acquisition of the remaining 21 OPCs will be awarded under one or more new contracts starting in fiscal year 2022 in the second stage.

The Coast Guard's determination to deliver the OPCs in a timely manner has driven the program through key acquisition decisions despite significant design, testing, schedule, and cost risks, which remained or were exacerbated after the hurricane (see figure).

Offshore Patrol Cutter Program Moved Forward Despite Major Risks

HL_5_v4-103742

Unstable Design. The Coast Guard authorized the start of construction for the first two OPCs despite not having a stable design, which is inconsistent with shipbuilding best practices. Proceeding towards OPC 3 construction before stabilizing the design—including maturing the design drawings of major ship systems—increases the risk of construction rework if changes are needed. This could further delay schedules and increase costs.

Deficient and Optimistic Schedule. Prior to the construction award for OPC 1, the OPC program's schedule has contained significant deficiencies that are contrary to what is called for in best practices for developing schedules that GAO identified. Further, the revised post-hurricane delivery dates for the first four OPCs are optimistic and do not fully incorporate schedule risks, increasing the likelihood that the OPCs will not be delivered when promised.

Incomplete Cost Estimate. The cost estimate used to inform the program's new cost goals did not include key analyses called for in best practices for developing cost estimates GAO identified. These key analyses include varying assumptions to determine how sensitive the estimates are to various factors and quantifying the effects of potential risks. Omitting these analyses undermines the credibility of the estimated program costs, increasing the risk that decision makers do not have a complete picture of the full range of costs the program could incur.

Why GAO Did This Study

The Coast Guard—a component of the Department of Homeland Security (DHS)—is planning to spend over $12 billion to acquire a fleet of 25 OPCs. This is the component's highest investment priority and will help ensure a variety of missions, such as drug and migrant interdiction, are carried out in offshore waters once its aging Medium Endurance Cutters are decommissioned. After Hurricane Michael—a category 5 storm—significantly disrupted the OPC shipbuilder's ability to continue work in October 2018, DHS granted up to $659 million in extraordinary contractual relief to the shipbuilder.

GAO was asked to review the status of the OPC acquisition program. This report examines, among other objectives, how the Coast Guard revised the OPC program after Hurricane Michael and the extent to which the program addressed major risks—particularly in the areas of design maturity, schedule, and cost— before proceeding through key acquisition decisions both pre- and post-hurricane. GAO reviewed Coast Guard program and contract documents, analyzed Coast Guard data, and interviewed Coast Guard and DHS officials.

What GAO Recommends

GAO is making eight recommendations to the Coast Guard and DHS, including ensuring that the program stabilizes its design before proceeding with construction of the next OPC, updates its schedule to address deficiencies and incorporate risks, and updates its cost estimate to improve its credibility.

For more information, contact Marie A. Mak at (202) 512-4841 or makm@gao.gov.

Recommendations for Executive Action

  1. Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The DHS Secretary should ensure the DHS Under Secretary for Management directs the Coast Guard to revise OPC's acquisition program baseline for stage 1 to include OPC's delivery dates. (Recommendation 1)

    Agency Affected: Department of Homeland Security

  2. Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The DHS Secretary should ensure the DHS Under Secretary for Management directs the Coast Guard to include in OPC's acquisition program baseline for stage 2 OPC's delivery dates when the stage 2 acquisition program baseline is established and approved at ADE 2B. (Recommendation 2)

    Agency Affected: Department of Homeland Security

  3. Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The Commandant of the Coast Guard should ensure the OPC program demonstrates that the OPC design for stage 1 is stable prior to approval of construction start for OPC 3 by (1) completing ESG's basic and functional designs and (2) maturing the davit technology to a TRL of 7, consistent with shipbuilding best practices. (Recommendation 3)

    Agency Affected: Department of Homeland Security: United States Coast Guard

  4. Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The Commandant of the Coast Guard should ensure the Coast Guard Component Acquisition Executive revises Coast Guard's acquisition policy to include criteria and a methodology for demonstrating design maturity for shipbuilding programs that are aligned with shipbuilding best practices, including specifying the completion of basic and functional designs and maturing critical technologies to a TRL of 7. (Recommendation 4)

    Agency Affected: Department of Homeland Security: United States Coast Guard

  5. Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The DHS Secretary should ensure the DHS Under Secretary for Management directs the Coast Guard, prior to approval of construction start for OPC 3, to identify the associated cost, schedule, and operational risks of the program's testing strategy for stage 1; and document these analyses in an updated test and evaluation master plan. (Recommendation 5)

    Agency Affected: Department of Homeland Security

  6. Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The Commandant of the Coast Guard should ensure the OPC program updates its shipbuilder and government schedules for OPCs 1 through 4 to (1) fully address deficiencies identified in the shipbuilder's schedule, and (2) fully incorporate schedule risk analysis in accordance with schedule best practices. (Recommendation 6)

    Agency Affected: Department of Homeland Security: United States Coast Guard

  7. Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The DHS Secretary should ensure the DHS Under Secretary for Management directs the Coast Guard, as it develops the next life cycle cost estimate for the OPC program, to update its cost estimate for stage 1 in accordance with best practices for cost estimation, including: (1) conducting a sensitivity analysis, (2) conducting a risk and uncertainty analysis, (3) reflecting information from the program's most recent technical baseline, and (4) conducting an independent cost assessment of the estimate. (Recommendation 7)

    Agency Affected: Department of Homeland Security

  8. Status: Open

    Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.

    Recommendation: The Commandant of the Coast Guard should ensure the OPC program improves its risk management processes to follow the format and include content as indicated in DHS acquisition policy and Coast Guard guidance, including (1) holding monthly risk management board meetings and updating its risk register regularly; (2) revising the risk register to include the risks we identified in this report—proceeding into construction with an incomplete 3D model, conducting late operational testing, challenges with ESG's scheduling practices, and challenges with ESG's accounting system; and (3) revising the risk register to comprehensively track risk management information. (Recommendation 8)

    Agency Affected: Department of Homeland Security: United States Coast Guard

 