The instructions for
submitting this form (if required) are included in 7 CFR 1726, Electric
System Construction Policies and Procedures.
Fld Name / |
Instruction |
Section 1 (Page 1) |
First Blank: Enter the number of the contract. Second and Third Blanks: Enter the date of the original contract. Fourth Blank: Enter name of RUS Borrower (Owner). Fifth Blank: Enter Borrower’s (Owner’s) RUS designation (e.g., AL001). Sixth Blank: Enter name of contractor. Seventh Blank: Enter the date of completion of the contract. |
Section 7 |
Enter the total cost of the contract. |
First Signature Block |
Enter the name of the Architect or Engineer, the date prepared, the date signed, and the title of the signer. (Sign the printed copy.) |
Section 1 (Page 2) |
Enter the date of the original contract. |
Second Signature Block |
Enter the names of the Owner and Contractor, dates, and title of the contractor’s signer. (Sign printed copy.) |