Construction Report

This page contains links and information to Facilities’ monthly construction reports, which detail where you can expect to find campus mobility obstructed by construction activities.

Click on the construction areas in the map to find more information, or open the map in a new window by clicking here. The attachment at the bottom of the page is a link to a text-only report of this information.

 

May 2019 Construction Obstruction Report

Project Name: Biomedical Engineering Lab

Project Lead: Jan Mak

Project Start Date: 5/1/2018

Project End Date: 5/31/2019

Location Description: Northwest corner of Discovery Park main building.

Project Summary: Build a new lab space for biomedical engineering lab.

Areas Impacted: Pedestrian traffic on west side of building will be blocked for the duration of project.

 

Project Name: Facilities Fuel Tank Replacement

Project Lead: Chad Davenport

Project Start Date: 5/1/2019

Project End Date: 8/31/2019

Location Description: Southeast corner of Automotive Services

Project Summary: Replace current fuel tanks and upgrade to current Federal standards

Areas Impacted: Vehicular and pedestrian traffic will be blocked during construction.

 

Project Name: Santa Fe Entrance and Widow Replacement

Project Lead: Jeff Hilliard

Project Start Date: 5/13/2019

Project End Date: 7/12/2019

Location Description: North and east side of Santa Fe Hall

Project Summary: Replace flagstone entrance to building and windows.

Areas Impacted: Vehicular and pedestrian traffic will be blocked for project duration.

 

Project Name: North Texas Blvd Street Repair

Project Lead: City of Denton

Project Start Date: 4/29/2019

Project End Date: 5/10/2019

Location Description: Right southbound lane of North Texas between W. Prairie and Sycamore

Project Summary: Milling roadway, repair substrate and repave street

Areas Impacted: Pedestrian and vehicular traffic will be blocked for duration of project.

 

Project Name: College Inn Stairwell

Project Lead: Jeff Hilliard

Project Start Date: 5/20/2019

Project End Date: 8/2/2019

Location Description: Lot 12 area

Project Summary: Construct new egress stairway.

Areas Impacted: Vehicular and pedestrian traffic will be blocked for project duration.

 

Project Name: Coliseum Roof Repair

Project Lead: Gilly Gilland

Project Start Date: 2/25/2019

Project End Date: 12/31/2019

Location Description: Coliseum Roof

Project Summary: Repair roof and replace metal panels.

Areas Impacted: SW corner of building blocked to pedestrians.

 

Project Name: Lot 20 Expansion Phase 2A

Project Lead: Traci Jones

Project Start Date: 1/2/2019

Project End Date: 5/31/2019

Location Description: North side of Fouts Field from Risk Management Building to USB

Project Summary: Install new drainage infrastructure and build parking lot

Areas Impacted: Parking and pedestrians will be barred for duration in project area.

 

Project Name: Lot 20 Expansion Phase 2B

Project Lead: Traci Jones

Project Start Date: 1/15/2019

Project End Date: 7/20/2019

Location Description: South side of Fouts Field and surrounding parking lot

Project Summary: Construct new parking lot in place of Fouts Field

Areas Impacted: Vehicular and pedestrian traffic will be blocked for duration of project.

 

Project Name: Lot 20 Expansion Phase 4

Project Lead: Traci Jones

Project Start Date: 12/17/2018

Project End Date: 5/31/2019

Location Description: Main entrance to Lot 20 off of North Texas Blvd west to Risk Management building

Project Summary: Demolish existing lot and building new lot entrance to support bus traffic

Areas Impacted: Pedestrian and vehicular traffic will be blocked for duration of project.

 

Project Name: Hickory Street Capital Improvement Program

Project Lead: Atmos

Project Start Date: 11/1/2017

Project End Date: 5/31/2019

Location Description: Hickory Street between Avenue B and Welch Street

Project Summary: Replace existing gas main and service connections

Areas Impacted: Pedestrian and vehicular traffic may be impacted during project.

 

Project Name: SRB Greenhouse

Project Lead: Chad Davenport

Project Start Date: 4/1/2019

Project End Date: 9/30/2019

Location Description: SW corner of Science Research Building

Project Summary: Build new greenhouse

Areas Impacted: Pedestrians and parking will be restricted for duration

 

Project Name: Life Science Exhaust Upgrade

Project Lead: Scott Harris

Project Start Date: 5/11/2019

Project End Date: 8/25/2019

Location Description: Lot 8 parking lot

Project Summary: Upgrade lab fume hoods

Areas Impacted: Parking lot will be closed to traffic for the duration of the project.

 

Project Name: Bruce Hall Landscaping

Project Lead: Brandon Lacy

Project Start Date: 5/1/2019

Project End Date: 8/16/2019

Location Description: Landscape beds on west side of Bruce Hall

Project Summary: Upgrade landscaping and drainage improvements.

Areas Impacted: Pedestrian traffic may be impacted during project.

 

Project Name: Music Courtyard Renovation

Project Lead: Janell Cottam

Project Start Date: 5/15/2019

Project End Date: 9/30/2019

Location Description: Music Building courtyard

Project Summary: Renovate courtyard area outside Voertman Hall lobby

Areas Impacted: Pedestrian traffic will be blocked during construction.

 

Project Name: Union Dock & Parking Lot

Project Lead: Randy Salsman

Project Start Date: 5/10/2019

Project End Date: 8/31/2019

Location Description: Student Union loading dock area

Project Summary: Demolish existing paving and landscaping and install new drainage and pavement.

Areas Impacted: Pedestrian and vehicular traffic will be impacted during construction.

 

Project Name: Central Dining Hall

Project Lead: Jeannine Vail

Project Start Date: 2/11/2019

Project End Date: 5/31/2020

Location Description: Greenspace east of Business Leadership Building

Project Summary: Build new dining facility

Areas Impacted: Pedestrian traffic will be blocked for duration of project.

 

Project Name: Joe Greene Hall

Project Lead: Janna Morgan

Project Start Date: 1/11/2017

Project End Date: 6/1/2019

Location Description: SE section of Kerr Hall block

Project Summary: Construct new dormitory

Areas Impacted: Pedestrian and vehicular traffic blocked for project duration.

 

Project Name: Victory Hall Envelope

Project Lead: Jeff Hilliard

Project Start Date: 5/24/2019

Project End Date: 6/28/2019

Location Description: North and south breezeway courtyard entrances.

Project Summary: Resolve standing water issues in courtyard entrances.

Areas Impacted: Pedestrian traffic will be blocked during project.

 

Project Name: Indoor Practice Facility

Project Lead: Terri Pierce

Project Start Date: 9/12/2018

Project End Date: 7/31/2019

Location Description: Football practice fields

Project Summary: Build new indoor practice facility.

Areas Impacted: Pedestrian traffic will be blocked for project duration.