Click here
      Home    DAG Tutorial    Search    Available Downloads     Feedback
 
The DAG does not reflect the changes in the DoDI5000.02. Work is in progress to update the content and will be completed as soon as possible.
 
.

4.3.3. Decision Analysis Process

Topic

Previous and Next Page arrows

DEFENSE ACQUISITION GUIDEBOOK
Chapter 4 -- Systems Engineering

4.3.3. Decision Analysis Process

4.3.3. Decision Analysis Process

The Decision Analysis process transforms a broadly stated decision opportunity into a traceable, defendable, and actionable plan. It encompasses one or more discrete analyses at one or more lower (e.g., system element) levels and aggregates them into a higher-level view (e.g., system “scorecard” presentation) relevant to the decision maker and other stakeholders. Decision Analysis can be the central process for formulating, managing, and executing an effective and efficient program at any point in the life cycle.

Decision Analysis and associated trade studies should be integrated with, and mutually supportive of, aspects of several SE processes in the early stages of the program, in particular:

  • Technical Planning (see DAG section 4.3.2. Technical Planning Process)
  • Technical Assessment (see DAG section 4.3.4. Technical Assessment Process)
  • Stakeholder Requirements Definition (see DAG section 4.3.10. Stakeholder Requirements Definition Process)
  • Requirements Analysis (see DAG section 4.3.11. Requirements Analysis Process)
  • Architecture Design (see DAG section 4.3.12. Architecture Design Process)

A well-executed decision analysis or trade study helps the Program Manager and the Systems Engineer understand the impact of various uncertainties, identify one or more course(s) of action that balance competing objectives, and objectively communicate the results to decision makers. As such, it provides the basis for selecting a viable and effective alternative from among many under consideration.

Decision Analysis applies to technical decisions at all levels, from evaluating top-level architectural concepts to sizing major system elements to selecting small design details. The breadth and depth of the analysis should be scaled to both the scope of the decision and the needs and expectations of the decision maker(s).

Activities and Products

Decision Analysis teams generally include a lead analyst with a suite of reasoning tools; subject matter experts with access to appropriate models and analytical tools; and a representative set of end users and other stakeholders. A robust Decision Analysis process acknowledges that the decision maker has full responsibility, authority, and accountability for the decision at hand.

Decision Analysis typically includes the following steps:

  • Review requirements and assumptions to establish the overall decision context
  • Frame/structure the decision in terms of supporting program/project objectives
  • Identify methods and tools to be used in the analyses (see DAG section 4.3.19. Tools and Techniques)
  • Develop decision criteria (objectives and measures), criteria weight, and associated rationale
  • Convey and track assumptions
  • Identify and define alternatives to be evaluated (for high-level analyses these are generally directed, although additional ones may arise during the course of the analysis)
  • Analyze and assess alternatives against criteria
  • Synthesize results
  • Analyze sensitivities
  • Develop decision briefing with action/implementation plan(s)
  • Make appropriate recommendation(s) to decision maker as expected/requested

Sound recommendations and action plans are the principal output of a well-framed and well-executed Decision Analysis process. The ability to drill down quickly from overall trade space visualizations to detailed analyses that support the synthesized views is particularly useful to decision makers in understanding the basis of observations and conclusions.

Previous and Next Page arrows

Previous Page Next Page

List of All Contributions at This Location

No items found.

Popular Tags

Browse

https://acc.dau.mil/UI/img/bo/minus.gifWelcome to the Defense Acquisition...
https://acc.dau.mil/UI/img/bo/plus.gifForeword
https://acc.dau.mil/UI/img/bo/minus.gifChapter 1 -- Department of Defense...
https://acc.dau.mil/UI/img/bo/plus.gif1.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif1.1. Integration of the DoD Decision...
https://acc.dau.mil/UI/img/bo/plus.gif1.2. Planning Programming Budgeting and...
https://acc.dau.mil/UI/img/bo/plus.gif1.3. Joint Capabilities Integration and...
https://acc.dau.mil/UI/img/bo/plus.gif1.4. Defense Acquisition System
https://acc.dau.mil/UI/img/bo/plus.gifChapter 2 -- Program Strategies
https://acc.dau.mil/UI/img/bo/plus.gifChapter 3 -- Affordability and...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 4 -- Systems Engineering
https://acc.dau.mil/UI/img/bo/plus.gif4.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif4.1. Introduction
https://acc.dau.mil/UI/img/bo/plus.gif4.2. Systems Engineering Activities in...
https://acc.dau.mil/UI/img/bo/minus.gif4.3. Systems Engineering Processes
https://acc.dau.mil/UI/img/bo/plus.gif4.3.2. Technical Planning Process
https://acc.dau.mil/UI/img/bo/minus.gif4.3.3. Decision Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.4. Technical Assessment Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.5. Requirements Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.6. Risk Management Process
https://acc.dau.mil/UI/img/bo/minus.gif4.3.7. Configuration Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.8. Technical Data Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.9. Interface Management Process
https://acc.dau.mil/UI/img/bo/minus.gif4.3.10. Stakeholder Requirements...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.11. Requirements Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.12. Architecture Design Process
https://acc.dau.mil/UI/img/bo/minus.gif4.3.13. Implementation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.14. Integration Process
https://acc.dau.mil/UI/img/bo/minus.gif4.3.15. Verification Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.16. Validation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.17. Transition Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18. Design Considerations
https://acc.dau.mil/UI/img/bo/minus.gif4.3.19. Tools Techniques and Lessons...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.19.1. Modeling and Simulation
https://acc.dau.mil/UI/img/bo/plus.gif4.3.19.2. Sustainability Analysis
https://acc.dau.mil/UI/img/bo/plus.gif4.3.19.3. Value Engineering
https://acc.dau.mil/UI/img/bo/plus.gif4.3.19.4. Lessons Learned Best Practices...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 5 -- Life-Cycle Logistics
https://acc.dau.mil/UI/img/bo/plus.gif5.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif5.1. Life-Cycle Sustainment in the...
https://acc.dau.mil/UI/img/bo/plus.gif5.2. Applying Systems Engineering to...
https://acc.dau.mil/UI/img/bo/plus.gif5.3. Supportability Design...
https://acc.dau.mil/UI/img/bo/plus.gif5.4. Sustainment in the Life-Cycle...
https://acc.dau.mil/UI/img/bo/plus.gif5.5. References
https://acc.dau.mil/UI/img/bo/plus.gifChapter 6 -- Human Systems Integration...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 7 -- Acquiring Information...
https://acc.dau.mil/UI/img/bo/plus.gif7.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif7.1. Introduction
https://acc.dau.mil/UI/img/bo/plus.gif7.2. DoD Information Enterprise
https://acc.dau.mil/UI/img/bo/plus.gif7.3. Interoperability and Supportability...
https://acc.dau.mil/UI/img/bo/plus.gif7.4. Sharing Data, Information, and...
https://acc.dau.mil/UI/img/bo/plus.gif7.5. Information Assurance (IA)
https://acc.dau.mil/UI/img/bo/plus.gif7.6. Electromagnetic Spectrum
https://acc.dau.mil/UI/img/bo/plus.gif7.7. Accessibility of Electronic and...
https://acc.dau.mil/UI/img/bo/plus.gif7.8. The Clinger-Cohen Act (CCA) --...
https://acc.dau.mil/UI/img/bo/plus.gif7.9. Post-Implementation Review (PIR)
https://acc.dau.mil/UI/img/bo/plus.gif7.10. Commercial Off-the-Shelf (COTS)...
https://acc.dau.mil/UI/img/bo/plus.gif7.11. Space Mission Architectures
https://acc.dau.mil/UI/img/bo/minus.gifChapter 8 -- Intelligence Analysis...
https://acc.dau.mil/UI/img/bo/plus.gif8.0. Introduction
https://acc.dau.mil/UI/img/bo/plus.gif8.1. Threat Intelligence Support
https://acc.dau.mil/UI/img/bo/plus.gif8.2. Signature and other Intelligence...
https://acc.dau.mil/UI/img/bo/plus.gif8.3. Support to the Intelligence...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 9 -- Test and Evaluation (T&E)
https://acc.dau.mil/UI/img/bo/plus.gif9.0 Overview
https://acc.dau.mil/UI/img/bo/plus.gif9.1 OSD T&E Organization
https://acc.dau.mil/UI/img/bo/plus.gif9.2 Service-Level T&E Management
https://acc.dau.mil/UI/img/bo/plus.gif9.3 Test and Evaluation
https://acc.dau.mil/UI/img/bo/plus.gif9.4 Integrated Test and Evaluation
https://acc.dau.mil/UI/img/bo/plus.gif9.5 Test and Evaluation Planning
https://acc.dau.mil/UI/img/bo/plus.gif9.6 T&E Reporting
https://acc.dau.mil/UI/img/bo/plus.gif9.7 Special Topics
https://acc.dau.mil/UI/img/bo/plus.gif9.8. Best Practices
https://acc.dau.mil/UI/img/bo/plus.gif9.9. Prioritizing Use of Government Test...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 10 -- Decisions Assessments and...
https://acc.dau.mil/UI/img/bo/plus.gif10.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif10.1. Decision Points
https://acc.dau.mil/UI/img/bo/plus.gif10.2. Executive Review Forums
https://acc.dau.mil/UI/img/bo/plus.gif10.3. Integrated Product and Process...
https://acc.dau.mil/UI/img/bo/plus.gif10.4. Role of Exit Criteria
https://acc.dau.mil/UI/img/bo/plus.gif10.5. Role of Independent Assessments
https://acc.dau.mil/UI/img/bo/plus.gif10.5.3. Preliminary Design Review (PDR)...
https://acc.dau.mil/UI/img/bo/plus.gif10.6. Information Sharing and DoD...
https://acc.dau.mil/UI/img/bo/plus.gif10.7. Management Control
https://acc.dau.mil/UI/img/bo/plus.gif10.8. Program Plans
https://acc.dau.mil/UI/img/bo/plus.gif10.9. Acquisition Program Baseline (APB)
https://acc.dau.mil/UI/img/bo/plus.gif10.10. Periodic Reports
https://acc.dau.mil/UI/img/bo/plus.gif10.11. Major Automated Information...
https://acc.dau.mil/UI/img/bo/plus.gif10.12. Defense Acquisition Executive...
https://acc.dau.mil/UI/img/bo/plus.gif10.13. Acquisition Visibility
https://acc.dau.mil/UI/img/bo/plus.gif10.14. Special Interest Programs
https://acc.dau.mil/UI/img/bo/plus.gif10.15. Relationship of Affordability and...
https://acc.dau.mil/UI/img/bo/plus.gif10.16. Acquisition Program Transition...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 11 -- Program Management...
https://acc.dau.mil/UI/img/bo/plus.gif11.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif11.1. Joint Programs
https://acc.dau.mil/UI/img/bo/plus.gif11.2. International Programs
https://acc.dau.mil/UI/img/bo/plus.gif11.3. Integrated Program Management
https://acc.dau.mil/UI/img/bo/plus.gif11.4. Knowledge-Based Acquisition
https://acc.dau.mil/UI/img/bo/plus.gif11.5. Technical Representatives at...
https://acc.dau.mil/UI/img/bo/plus.gif11.6. Contractor Councils
https://acc.dau.mil/UI/img/bo/plus.gif11.7 Property
https://acc.dau.mil/UI/img/bo/plus.gif11.8. Modeling and Simulation (M&S)...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 12 - Defense Business System...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 13 -- Program Protection
https://acc.dau.mil/UI/img/bo/plus.gif13.0 Overview
https://acc.dau.mil/UI/img/bo/plus.gif13.1 The Program Protection Process
https://acc.dau.mil/UI/img/bo/plus.gif13.2 The Program Protection Plan (PPP)
https://acc.dau.mil/UI/img/bo/plus.gif13.3 Critical Program Information (CPI)...
https://acc.dau.mil/UI/img/bo/plus.gif13.4. Intelligence and...
https://acc.dau.mil/UI/img/bo/plus.gif13.5. Vulnerability Assessment
https://acc.dau.mil/UI/img/bo/plus.gif13.6. Risk Assessment
https://acc.dau.mil/UI/img/bo/plus.gif13.7. Countermeasures
https://acc.dau.mil/UI/img/bo/plus.gif13.8. Horizontal Protection
https://acc.dau.mil/UI/img/bo/plus.gif13.9. Foreign Involvement
https://acc.dau.mil/UI/img/bo/plus.gif13.10. Managing and Implementing PPPs
https://acc.dau.mil/UI/img/bo/plus.gif13.11. Compromises
https://acc.dau.mil/UI/img/bo/plus.gif13.12. Costs
https://acc.dau.mil/UI/img/bo/plus.gif13.13. Contracting
https://acc.dau.mil/UI/img/bo/plus.gif13.14. Detailed System Security...
https://acc.dau.mil/UI/img/bo/plus.gif13.15. Program Protection Plan (PPP)...
https://acc.dau.mil/UI/img/bo/plus.gif13.16. Program Protection Plan (PPP)...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 14 -- Acquisition of Services
https://acc.dau.mil/UI/img/bo/minus.gifDoD Directive 5000.01
https://acc.dau.mil/UI/img/bo/plus.gifENCLOSURE 1 ADDITIONAL POLICY
https://acc.dau.mil/UI/img/bo/minus.gifDoD Instruction 5000.02
https://acc.dau.mil/UI/img/bo/plus.gifTABLE OF CONTENTS
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 1 -- References
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 2 -- Procedures
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 3 -- Acquisition Category...
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 4 -- Statutory and Regulatory...
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 5 -- IT Considerations
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 6 -- Integrated T&E
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 7 -- Resource Estimation
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 8 -- Human Systems Integration...
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 9 -- Acquisition of Services
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 10 -- Program Management
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 11 -- Management of Defense...
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 12 -- Systems Engineering
https://acc.dau.mil/UI/img/bo/minus.gifRecent Policy and Guidance
https://acc.dau.mil/UI/img/bo/plus.gifDownload the Defense Acquisition...
https://acc.dau.mil/UI/img/bo/plus.gifWeapon Systems Acquisition Reform Act of...
https://acc.dau.mil/UI/img/bo/minus.gifCurrent JCIDS Manual and CJCSI 3170.01 I
https://acc.dau.mil/UI/img/bo/minus.gifDefense Acquisition Guidebook Key...
ACC Practice Center Version 3.2
  • Application Build 3.2.9
  • Database Version 3.2.9