4.2.1. Life-Cycle Expectations

Topic

Previous and Next Page arrows

DEFENSE ACQUISITION GUIDEBOOK
Chapter 4 -- Systems Engineering

4.2.1. Life-Cycle Expectations

4.2.1. Life-Cycle Expectations

Systems engineering (SE) provides the technical foundation for all acquisition activities regardless of acquisition category (ACAT) or acquisition model (e.g., weapon system or information system). The SE framework described in this chapter spans the entire acquisition life cycle and is based on DoDD 5000.01 and DoDI 5000.02. Framework content should be tailored and structured to fit the technology maturity, risks, interdependencies, related characteristics, and context for the program or the system of interest. The succeeding sections identify the SE activities, processes, inputs, outputs, and expectations during each acquisition phase and for each technical review and audit.

Acquisition milestones and SE technical reviews and audits serve as key points throughout the life cycle to evaluate significant achievements and assess technical maturity and risk. Table 4.2.1.T1 identifies the objectives of each SE assessment and the technical maturity point marked by each review. The Materiel Development Decision (MDD) review is the formal entry point into the acquisition process and is mandatory for all programs in accordance with DoDI 5000.02. Depending on the maturity of the preferred materiel solution, the Milestone Decision Authority (MDA) designates the initial review milestone. This would normally be the MDD, but it can be A, B, or C. In any case the decision is documented in the Acquisition Decision Memorandum (ADM) published immediately after an MDD event. Since the review milestone is chosen consistent with the maturity of the preferred materiel solution, entry at any milestone requires evidence of the associated solution maturity as summarized in Table 4.2.1.T1 Technical Maturity Points.

Department experience (e.g., GAO Report 12-400SP) has found that successful programs use knowledge-based product development practices which include steps to gather knowledge to confirm the program’s technologies are mature, their designs are stable, and their production processes are in control. Successful product developers ensure a high level of knowledge is achieved at key junctures in development. Table 4.2.1.T1 summarizes the concept of technical maturity points.

Table 4.2.1.T1. Technical Maturity Points

TECHNICAL MATURITY POINTS

DoD Acquisition Milestone/Decision Point
&
Technical Review/Audit

Objective

Technical Maturity Point

Additional Information

Materiel Development Decision (MDD)

Decision to assess potential materiel solutions and appropriate phase for entry into acquisition life cycle.

Capability gap met by acquiring a materiel solution.

Technically feasible solutions have the potential to effectively address a validated capability need. Technical risks understood.

Alternative Systems Review (ASR)

Recommendation that the preferred materiel solution can affordably meet user needs with acceptable risk.

System parameters defined; balanced with cost, schedule, and risk.

Initial system performance established and plan for further analyses supports Milestone A criteria.

Milestone A

Decision to invest in technology maturation and preliminary design.

Affordable solution found for identified need with acceptable technology risk, scope, and complexity.

Affordability targets identified and technology development plans, time, funding, and other resources match customer needs. Prototyping and end-item development strategy for Technology Development (TD) phase focused on key technical risk areas.

System Requirements Review (SRR)

Recommendation to proceed into development with acceptable risk.

Level of understanding of top-level system requirements is adequate to support further requirements analysis and design activities.

Government and contractor mutually understand system requirements including
(1) the preferred materiel solution (including its support concept) from the Materiel Solution Analysis (MSA) phase,
(2) available technologies resulting from the prototyping efforts, and
(3) maturity of interdependent systems.

System Functional Review (SFR)

Recommendation that functional baseline fully satisfies performance requirements and to begin preliminary design with acceptable risk.

Functional baseline established and under formal configuration control. System’s functions decomposed and defined to lower levels in order to start preliminary design.

Functional requirements and verification methods support achievement of performance requirements. Acceptable technical risk of achieving allocated baseline.

Preliminary Design Review (PDR)

Recommendation that allocated baseline fully satisfies user requirements and developer ready to begin detailed design with acceptable risk.

Allocated baseline established such that design provides sufficient confidence to support 2366b certification.

Preliminary design and basic system architecture support capability need and affordability target achievement.

Pre-Engineering and Manufacturing Development (EMD) Review

Determination that program plans are affordable and executable and that the program is ready to proceed to EMD phase source selection.

Systems engineering trades completed and have informed program requirements. Competitive prototyping and the development of the preliminary design have influenced risk management plans and should cost initiatives.

The Request for Proposal (RFP) reflects the program’s plans articulated in the draft Acquisition Strategy and other draft, key planning documents such as the Systems Engineering Plan (SEP), Program Protection Plan (PPP), Test and Evaluation Master Plan (TEMP), and Life-Cycle Sustainment Plan (LCSP).

Milestone B

Decision to invest in product development, integration, and verification as well as manufacturing process development.

Critical technologies assessed able to meet required performance and are ready for further development. Resources and requirements match.

Maturity, integration, and producibility of the preliminary design (including critical technologies) and availability of key resources (time, funding, other) match customer needs. Should cost goals defined.

Critical Design Review (CDR)

Recommendation to start fabricating, integrating, and testing test articles with acceptable risk.

Product design is stable. Initial product baseline established.

Design is stable and performs as expected. Initial product baseline established by the system detailed design documentation confirms affordability/should-cost goals. Government control of Class I changes as appropriate.

System Verification Review (SVR)

Recommendation that the system as tested has been verified (i.e., product baseline is compliant with the functional baseline) and is ready for validation (operational assessment) with acceptable risk.

System design verified to conform to functional baseline.

Actual system (which represents the production configuration) has been verified through required analysis, demonstration, examination, and/or testing. Synonymous with system-level Functional Configuration Audit (FCA).

Production Readiness Review (PRR)

Recommendation that production processes are mature enough to begin limited production with acceptable risk.

Design and manufacturing are ready to begin production.

Production engineering problems resolved and ready to enter production phase.

Milestone C

Decision to produce production-representative units for operational test and evaluation (OT&E).

Manufacturing processes are mature enough to support Low-Rate Initial Production (LRIP) and generate production-representative articles for OT&E.

Production readiness meets cost, schedule, and quality targets. Begin initial deployment as appropriate.

Physical Configuration Audit (PCA)

Recommendation to start full-rate production and/or full deployment with acceptable risk.

Final product baseline established. Verifies the design and manufacturing documentation matches the item to be fielded, following update of the product baseline to account for resolved OT&E issues.

Confirmation that the system to be fielded matches the product baseline. Product configuration finalized and system meets users’ needs. Conducted after OT&E issues are resolved.

Full-Rate Production Decision Review (FRP DR) or Full Deployment Decision Review (FDDR)

Decision to begin full-rate production and/or decision to begin full deployment.

Manufacturing processes are mature and support full-rate production and/or capability demonstrated in operational environment supporting full deployment (i.e., system validated through OT&E).

Delivers fully funded quantity of systems and supporting materiel and services for the program or increment to the users.

Figure 4.2.1.F1 provides the end-to-end perspective and the integration of SE technical reviews and audits across the system life cycle.

Figure 4.2.1.F1. Weapon System Development Life Cycle

Figure 4.2.1.F1. Weapon Systems Development Life Cycle

The Systems Engineer leads the development and implementation of a technical program strategy. SE processes help deliver capabilities that meet warfighter needs within cost and schedule by balancing end-user needs, design considerations, resource constraints, and risk. The Systems Engineer uses technical reviews and audits to assess whether preplanned technical maturity points are reached during the acquisition life cycle as the system and system elements mature. This knowledge forms the basis for the Systems Engineer’s recommendations to the Program Manager on how to technically proceed with the program.

Previous and Next Page arrows

Previous Page Next Page

List of All Contributions at This Location

No items found.

Popular Tags

Browse

https://acc.dau.mil/UI/img/bo/minus.gifWelcome to the Defense Acquisition...
https://acc.dau.mil/UI/img/bo/minus.gifForeword
https://acc.dau.mil/UI/img/bo/plus.gifChapter 1 -- Department of Defense...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 2 -- Program Strategies
https://acc.dau.mil/UI/img/bo/plus.gifChapter 3 -- Affordability and...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 4 -- Systems Engineering
https://acc.dau.mil/UI/img/bo/plus.gif4.0. Overview
https://acc.dau.mil/UI/img/bo/minus.gif4.1. Introduction
https://acc.dau.mil/UI/img/bo/minus.gif4.1.1. Systems Engineering Policy and...
https://acc.dau.mil/UI/img/bo/plus.gif4.1.2. Systems Engineering Plan
https://acc.dau.mil/UI/img/bo/minus.gif4.1.3. Systems Level Considerations
https://acc.dau.mil/UI/img/bo/plus.gif4.1.3.1. Software
https://acc.dau.mil/UI/img/bo/plus.gif4.1.4. Engineering Resources
https://acc.dau.mil/UI/img/bo/minus.gif4.1.5. Certifications
https://acc.dau.mil/UI/img/bo/plus.gif4.1.6. Systems Engineering Role in...
https://acc.dau.mil/UI/img/bo/minus.gif4.2. Systems Engineering Activities in...
https://acc.dau.mil/UI/img/bo/minus.gif4.2.1. Life-Cycle Expectations
https://acc.dau.mil/UI/img/bo/plus.gif4.2.1.1. Systems Engineering in Other...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.1.2. Systems of Systems
https://acc.dau.mil/UI/img/bo/plus.gif4.2.2. Pre-Materiel Development Decision
https://acc.dau.mil/UI/img/bo/plus.gif4.2.3. Materiel Solution Analysis Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.4. Technology Development Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.5. Engineering and Manufacturing...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.6. Production and Deployment Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.7. Operations and Support Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.8. Technical Reviews and Audits...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.9. Alternative Systems Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.10. System Requirements Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.11. System Functional Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.12. Preliminary Design Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.13. Critical Design Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.14. System Verification...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.15. Production Readiness Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.16. Physical Configuration Audit
https://acc.dau.mil/UI/img/bo/plus.gif4.2.17. In-Service Review
https://acc.dau.mil/UI/img/bo/minus.gif4.3. Systems Engineering Processes
https://acc.dau.mil/UI/img/bo/plus.gif4.3.2. Technical Planning Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.3. Decision Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.4. Technical Assessment Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.5. Requirements Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.6. Risk Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.7. Configuration Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.8. Technical Data Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.9. Interface Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.10. Stakeholder Requirements...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.11. Requirements Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.12. Architecture Design Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.13. Implementation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.14. Integration Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.15. Verification Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.16. Validation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.17. Transition Process
https://acc.dau.mil/UI/img/bo/minus.gif4.3.18. Design Considerations
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.1. Accessibility (Section 508...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.2. Affordability – Systems...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.3. Anti-Counterfeiting
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.4. Commercial-Off-the-Shelf
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.5. Corrosion Prevention and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.6. Critical Safety Item
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.7. Demilitarization and Disposal
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.8. Diminishing Manufacturing...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.9. Environment Safety and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.10. Human Systems Integration
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.11. Insensitive Munitions
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.12. Intelligence (Life-Cycle...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.13. Interoperability and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.14. Item Unique Identification
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.15. Open Systems Architecture
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.16. Operational Energy
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.17. Packaging Handling Storage...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.18. Producibility Quality and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.19. Reliability and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.20. Spectrum Management
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.21. Standardization
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.22. Supportability
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.23. Survivability and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.24. System Security Engineering
https://acc.dau.mil/UI/img/bo/plus.gif4.3.19. Tools Techniques and Lessons...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 5 -- Life-Cycle Logistics
https://acc.dau.mil/UI/img/bo/plus.gif5.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif5.1. Life-Cycle Sustainment in the...
https://acc.dau.mil/UI/img/bo/plus.gif5.2. Applying Systems Engineering to...
https://acc.dau.mil/UI/img/bo/plus.gif5.3. Supportability Design...
https://acc.dau.mil/UI/img/bo/plus.gif5.4. Sustainment in the Life-Cycle...
https://acc.dau.mil/UI/img/bo/plus.gif5.5. References
https://acc.dau.mil/UI/img/bo/plus.gifChapter 6 -- Human Systems Integration...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 7 -- Acquiring Information...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 8 -- Intelligence Analysis...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 9 -- Test and Evaluation (T&E)
https://acc.dau.mil/UI/img/bo/plus.gif9.0 Overview
https://acc.dau.mil/UI/img/bo/plus.gif9.1 OSD T&E Organization
https://acc.dau.mil/UI/img/bo/plus.gif9.2 Service-Level T&E Management
https://acc.dau.mil/UI/img/bo/plus.gif9.3 Test and Evaluation
https://acc.dau.mil/UI/img/bo/plus.gif9.4 Integrated Test and Evaluation
https://acc.dau.mil/UI/img/bo/plus.gif9.5 Test and Evaluation Planning
https://acc.dau.mil/UI/img/bo/plus.gif9.6 T&E Reporting
https://acc.dau.mil/UI/img/bo/plus.gif9.7 Special Topics
https://acc.dau.mil/UI/img/bo/plus.gif9.8. Best Practices
https://acc.dau.mil/UI/img/bo/plus.gif9.9. Prioritizing Use of Government Test...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 10 -- Decisions Assessments and...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 11 -- Program Management...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 12 - Defense Business System...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 13 -- Program Protection
https://acc.dau.mil/UI/img/bo/plus.gif13.0 Overview
https://acc.dau.mil/UI/img/bo/plus.gif13.1 The Program Protection Process
https://acc.dau.mil/UI/img/bo/plus.gif13.2 The Program Protection Plan (PPP)
https://acc.dau.mil/UI/img/bo/plus.gif13.3 Critical Program Information (CPI)...
https://acc.dau.mil/UI/img/bo/plus.gif13.4. Intelligence and...
https://acc.dau.mil/UI/img/bo/plus.gif13.5. Vulnerability Assessment
https://acc.dau.mil/UI/img/bo/plus.gif13.6. Risk Assessment
https://acc.dau.mil/UI/img/bo/plus.gif13.7. Countermeasures
https://acc.dau.mil/UI/img/bo/plus.gif13.8. Horizontal Protection
https://acc.dau.mil/UI/img/bo/plus.gif13.9. Foreign Involvement
https://acc.dau.mil/UI/img/bo/plus.gif13.10. Managing and Implementing PPPs
https://acc.dau.mil/UI/img/bo/plus.gif13.11. Compromises
https://acc.dau.mil/UI/img/bo/plus.gif13.12. Costs
https://acc.dau.mil/UI/img/bo/plus.gif13.13. Contracting
https://acc.dau.mil/UI/img/bo/plus.gif13.14. Detailed System Security...
https://acc.dau.mil/UI/img/bo/plus.gif13.15. Program Protection Plan (PPP)...
https://acc.dau.mil/UI/img/bo/plus.gif13.16. Program Protection Plan (PPP)...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 14 -- Acquisition of Services
https://acc.dau.mil/UI/img/bo/plus.gifDoD Directive 5000.01
https://acc.dau.mil/UI/img/bo/plus.gifDoD Instruction 5000.02
https://acc.dau.mil/UI/img/bo/minus.gifRecent Policy and Guidance
https://acc.dau.mil/UI/img/bo/plus.gifDownload the Defense Acquisition...
https://acc.dau.mil/UI/img/bo/plus.gifWeapon Systems Acquisition Reform Act of...
https://acc.dau.mil/UI/img/bo/plus.gifCurrent JCIDS Manual and CJCSI 3170.01 I
https://acc.dau.mil/UI/img/bo/plus.gifDefense Acquisition Guidebook Key...
ACC Practice Center Version 3.2
  • Application Build 3.2.9
  • Database Version 3.2.9