4.3.18.9. Environment, Safety, and Occupational Health

4.3.18.9. Environment, Safety, and Occupational Health

Environment, Safety, and Occupational Health (ESOH) analyses are an integral, ongoing part of the systems engineering (SE) process throughout the life cycle. The benefits of early integration of ESOH considerations include:

  • Mitigation of program cost and schedule risks from actions that cause damage to people, equipment, or the environment
  • Reduction of Operations and Support and disposal costs
  • Provision of a safe, suitable, supportable, and sustainable capability able to operate world-wide

Throughout each acquisition phase, programs conduct the ESOH analyses to:

Efforts to identify and analyze hazards, and mitigate ESOH risks provide information needed for informed design decisions and development of ESOH-related documentation for milestone decisions.

DoD defines ESOH in MIL-STD-882E, DoD Standard Practice for System Safety as "the combination of disciplines that encompass the processes and approaches for addressing laws, regulations, EOs, DoD policies, environmental compliance, and hazards associated with environmental impacts, system safety (e.g., platforms, systems, system-of-systems, weapons, explosives, software, ordnance, combat systems), occupational safety and health, hazardous materials management, and pollution prevention."

ESOH System Design Requirements

The Systems Engineer identifies the ESOH requirements applicable to the system throughout its life cycle from statutes, regulations, policies, design standards, and capability documents. From these requirements, the Systems Engineer should derive ESOH design requirements and include them in capability documents, technical specifications, solicitations, and contracts.

ESOH in Program Documents

The Acquisition Program Office ESOH-specific documents are the Programmatic ESOH Evaluation (PESHE) and the NEPA/EO 12114 Compliance Schedule. The Systems Engineering Plan (SEP) contains the ESOH management planning information. The SEP, PESHE, and NEPA/EO 12114 Compliance Schedule provide inputs to program documentation that include, but are not limited to: Technology Development Strategy (TDS), Test and Evaluation Strategy (TES), Test and Evaluation Master Plan (TEMP), Life-Cycle Sustainment Plan (LCSP), Corrosion Prevention and Control Plan (CPCP), system specifications, solicitations, and contracts; and capability documents.

The SEP contains ESOH design considerations as an integral part of the requirements analysis process, including trade study criteria. ESOH design considerations are particularly important for Milestone A to ensure SE addresses ESOH during the Technology Development (TD) phase, which includes a significant amount of the design development, testing, and the Preliminary Design Review. SEP Table 4.6-1 includes the information listed in Table 4.3.18.9.T1. Additional ESOH details are provided in SEP Sections 3.4 and 3.6; Tables 2.2-1, 3.4.4-1, 3.4.4-2, and 4.4-1; and Figure 3.4.1-1.

Table 4.3.18.9.T1. ESOH Information in SEP

Column Heading in

SEP Table 4.6-1

Expected Information

(provided or attached)

Cognizant PMO Organization

Organizational structure for integrating ESOH (or refer to Table 3.4.4-2 if it includes the ESOH team details) and the Program Office ESOH point of contact

Certification

Required ESOH approvals, endorsements, releases, and the designated high and serious risk acceptance user representative(s)

Documentation

PESHE and NEPA/EO 12114 Compliance Schedule

Contractual Requirements (CDRL#)

ESOH contractual language, ESOH Contract Data Requirements List (CDRL) items, and ESOH DFARS clauses

Description / Comments

Description of how design minimizes ESOH risks by summarizing how the program has integrated ESOH considerations into SE processes including the method for tracking hazards and ESOH risks and mitigation plans throughout the life cycle of system

The PESHE documents the ESOH design consideration data produced by executing the ESOH planning described in the SEP. The PESHE includes, but is not limited to:

  • ESOH Risk Matrices (for hardware and software) used by the program with definitions for severity categories, probability levels, risk levels, and risk acceptance and user representative concurrence authorities.
  • The following data for each hazard: Hazard Tracking System (HTS) identification number, hazard description, potential mishap, initial Risk Assessment Code (RAC) and risk level, mitigation measure(s) and funding status, target RAC and risk level, current RAC and risk level, and risk acceptance and user concurrence status (NOTE: providing an electronic copy of the current data from the HTS would satisfy this requirement).
  • The following data for each hazardous material, hazardous waste, and pollutant associated with the system: the specific uses, locations, quantities, and plans for their minimization and/or safe disposal (NOTE: providing an electronic copy of the current data from either the HTS (if it includes this information) or the hazardous materials management data would satisfy this requirement).
  • Environmental impact information not included in the HTS or hazardous materials tracking system needed to support installation and range analyses.

NOTE: The results of the sustainability analysis (see DAG section 4.3.19.2. Sustainability Analysis) should be used to inform the hazard analysis.

DoDI 5000.02, Enclosure 12 requires that each program maintain a NEPA/EO 12114 compliance schedule. This schedule includes, but is not limited to:

  • Each proposed action (e.g., testing or fielding)
  • Proponent (as defined in DoDI 4715.9) for each action
  • Anticipated start date for each action at each specific location
  • Anticipated NEPA/EO 12114 document type
  • Anticipated start and completion dates for each document
  • The document approval authority

Because actions occurring during the TD phase may require NEPA/EO 12114 compliance, the program should develop a TD Compliance Schedule for inclusion in the SEP. DoDI 5000.02, Enclosure12 also requires programs to support other organizations’ NEPA/EO 12114 analyses involving their systems.

ESOH Activities by Phase

Table 4.3.18.9.T2. aligns typical ESOH activities by phase.

Table 4.3.18.9.T2. ESOH Activities by Phase

Acquisition Phase

Typical ESOH Activities

Materiel Solution Analysis (MSA)

  • Participate in Analysis of Alternatives (AoA)
  • Provide inputs to the SEP, draft Capability Development Document (CDD), Corrosion Prevention and Control (CPC) Planning, TDS, Test and Evaluation (T&E) Strategy (TES), Life-cycle Sustainment Plan (LCSP), and draft Request for Proposal (RFP)

Technology Development (TD)

  • Participate in prototyping and design development through the IPT structure
  • Prepare initial PESHE and NEPA/EO 12114 Compliance Schedule
  • Ensure NEPA/EO 12114 compliance, ESOH risk acceptance, Preliminary Design Review (PDR) risk reporting, and safety releases
  • Inputs to SEP, CPC Planning, final CDD, Test and Evaluation Master Plan (TEMP), LCSP, and draft RFP

Engineering and Manufacturing Development (EMD)

  • Participate in trades and design development activities through the IPT structure
  • Evaluate T&E results, to include assessment of ESOH risk mitigations
  • Update NEPA/EO 12114 Compliance Schedule and PESHE; support NEPA/EO 12114 compliance activities, ESOH risk acceptance
  • Obtain required ESOH approvals, endorsements, and releases; provide inputs to the SEP, CPC Planning, LCSP, Capability Production Document (CPD), and draft RFP

Production and Deployment (P&D)

  • Participate in initial Configuration Control Board (CCB) process
  • Evaluate T&E results, to include assessment of ESOH risk mitigations
  • Analyze deficiency reports
  • Review Physical Configuration Audit (PCA)
  • Update NEPA/EO 12114 Compliance Schedule and PESHE
  • Support NEPA/EO 12114 compliance activities and ESOH risk mitigations
  • Obtain required ESOH approvals, endorsements, and releases
  • Support Initial Operational Capability (IOC) and Full Operational Capability (FOC)
  • Provide inputs to the LCSP, CPC Planning, and product support package

Operations and Support (O&S)

ESOH Risk Management

The Systems Engineer uses the MIL-STD-882E process to identify and assess hazards (to include software safety), eliminate hazards where possible, and manage ESOH risks where hazards cannot be eliminated. MIL-STD-882E provides a matrix and defines probability and severity criteria to categorize ESOH risks. Prior to exposing people, equipment, or the environment to known system-related hazards, the Systems Engineer ensures ESOH risks are formally accepted, which includes formal concurrence on high and serious risks by the designated user representative as defined in MIL-STD-882E (or by each participating Service user representative in a Joint program). DoDI 5000.02 identifies the appropriate management level authorized to accept ESOH risks.

For Joint programs, the Component Acquisition Executive of the Lead Executive Component should be the acceptance authority for high-level risks. The program documents formal risk acceptances as part of the program record (e.g., Hazard Tracking System (HTS)). If a risk level increases for a hazard, a new risk acceptance is required prior to exposing people, equipment, or the environment to the increased risk. The program also participates in system-related mishap investigations to assess contributing hazards, risks, and mitigations.

DoDI 5000.02, Enclosure 12 requires programs to report the status of current high and serious ESOH risks at program reviews and fielding decisions and the status of all ESOH risks at technical reviews. The purpose of this reporting is to inform the Milestone Decision Authority (MDA), Program Executive Office (PEO), Program Manager, and end user about trades being made and ESOH risks that need to be accepted. Each ESOH risk report includes the following: the hazard, potential mishap, initial Risk Assessment Code (RAC) and risk level, mitigation measure(s) and funding status, target RAC and risk level, current RAC and risk level, and risk acceptance / user representative concurrence status.

Hazardous Materials (HAZMAT) Management

When Hazardous Materials (HAZMAT) and chemicals/materials of evolving regulatory concern are designed into the system or used for system operation and maintenance, the Systems Engineer assesses and documents the ESOH risks for each combination of HAZMAT and application. The Systems Engineer also documents:

  • The locations, quantities, and usage of each HAZMAT
  • Safe demilitarization and disposal requirements
  • Energetic qualification information, as applicable
  • Reasonably anticipated quantities of hazardous waste generated during normal operation and maintenance
  • Hazardous emissions/discharges including those anticipated in emergency situations
  • Special training, handling, and storage requirements

The Systems Engineer manages hexavalent chromium usage in systems to balance the requirements for corrosion control and prevention and the procedures in DFARS Subpart 223.73 - Minimizing the Use of Hexavalent Chromium. For more information on chemicals/materials of evolving regulatory concern, refer to the DENIX website.

Safety Release for Testing

The Program Manager, in concert with the user and the T&E community, provides safety releases (to include formal ESOH risk acceptance in accordance with DoDI 5000.02, Enclosure 12, Section 6), to the developmental and operational testers before any test using personnel. The safety release addresses each system hazard present during the test and include formal risk acceptance for each hazard. The program’s safety release is in addition to any test range safety release requirements, but it should support test range analyses required for a range-generated test release. The program documents safety releases as part of the Program Record.

The Program Manager should provide a transmittal letter to the involved test organization with a detailed listing of the system hazards germane to the test that includes the current risk level and documented risk acceptance along with information on all implemented mitigations.

Green Procurement Program (GPP)

In an effort to enhance and sustain mission readiness over the system life cycle, reduce reliance on resources, as well as reduce the DoD footprint, programs should follow the policy and procedures identified in the DoD Green Procurement Program (GPP). GPP benefits include:

  • Reducing resource consumption
  • Ensuring availability of chemicals and materials
  • Reducing waste generation
  • Contributing to regulatory compliance

Program Managers should implement the applicable GPP procedures in Federal Acquisition Regulation (FAR) Subparts 23.2, 23.4, 23.7 and 23.8 to select materials and products that are energy-efficient, water conserving, and environmentally preferable. More information on GPP is available on the DENIX website.

Key Resources

Previous and Next Page arrows

Previous Page Next Page

List of All Contributions at This Location

No items found.

Popular Tags

Browse

https://acc.dau.mil/UI/img/bo/minus.gifWelcome to the Defense Acquisition...
https://acc.dau.mil/UI/img/bo/plus.gifForeword
https://acc.dau.mil/UI/img/bo/plus.gifChapter 1 -- Department of Defense...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 2 -- Program Strategies
https://acc.dau.mil/UI/img/bo/plus.gifChapter 3 -- Affordability and...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 4 -- Systems Engineering
https://acc.dau.mil/UI/img/bo/plus.gif4.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif4.1. Introduction
https://acc.dau.mil/UI/img/bo/plus.gif4.2. Systems Engineering Activities in...
https://acc.dau.mil/UI/img/bo/minus.gif4.3. Systems Engineering Processes
https://acc.dau.mil/UI/img/bo/plus.gif4.3.2. Technical Planning Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.3. Decision Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.4. Technical Assessment Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.5. Requirements Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.6. Risk Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.7. Configuration Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.8. Technical Data Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.9. Interface Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.10. Stakeholder Requirements...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.11. Requirements Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.12. Architecture Design Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.13. Implementation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.14. Integration Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.15. Verification Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.16. Validation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.17. Transition Process
https://acc.dau.mil/UI/img/bo/minus.gif4.3.18. Design Considerations
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.1. Accessibility (Section 508...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.2. Affordability – Systems...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.3. Anti-Counterfeiting
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.4. Commercial-Off-the-Shelf
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.5. Corrosion Prevention and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.6. Critical Safety Item
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.7. Demilitarization and Disposal
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.8. Diminishing Manufacturing...
https://acc.dau.mil/UI/img/bo/minus.gif4.3.18.9. Environment Safety and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.10. Human Systems Integration
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.11. Insensitive Munitions
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.12. Intelligence (Life-Cycle...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.13. Interoperability and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.14. Item Unique Identification
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.15. Open Systems Architecture
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.16. Operational Energy
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.17. Packaging Handling Storage...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.18. Producibility Quality and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.19. Reliability and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.20. Spectrum Management
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.21. Standardization
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.22. Supportability
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.23. Survivability and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.24. System Security Engineering
https://acc.dau.mil/UI/img/bo/plus.gif4.3.19. Tools Techniques and Lessons...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 5 -- Life-Cycle Logistics
https://acc.dau.mil/UI/img/bo/plus.gifChapter 6 -- Human Systems Integration...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 7 -- Acquiring Information...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 8 -- Intelligence Analysis...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 9 -- Test and Evaluation (T&E)
https://acc.dau.mil/UI/img/bo/plus.gifChapter 10 -- Decisions Assessments and...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 11 -- Program Management...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 12 - Defense Business System...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 13 -- Program Protection
https://acc.dau.mil/UI/img/bo/plus.gifChapter 14 -- Acquisition of Services
https://acc.dau.mil/UI/img/bo/plus.gifDoD Directive 5000.01
https://acc.dau.mil/UI/img/bo/plus.gifDoD Instruction 5000.02
https://acc.dau.mil/UI/img/bo/plus.gifRecent Policy and Guidance
https://acc.dau.mil/UI/img/bo/plus.gifCurrent JCIDS Manual and CJCSI 3170.01 I
https://acc.dau.mil/UI/img/bo/plus.gifDefense Acquisition Guidebook Key...
ACC Practice Center Version 3.2
  • Application Build 3.2.9
  • Database Version 3.2.9