4.2.6. Production and Deployment Phase

Topic

Previous and Next Page arrows

DEFENSE ACQUISITION GUIDEBOOK
Chapter 4 -- Systems Engineering

4.2.6. Production and Deployment Phase

4.2.6. Production and Deployment Phase

The objective of the Production and Deployment (P&D) phase is to validate the product design and to deliver the quantity of systems required for full operating capability, including all enabling system elements and supporting material and services. Systems engineering (SE) in P&D delivers the final product baseline as validated during operational testing, and supports deployment and transition of capability to all end users, the warfighters, and supporting organizations. SE activities, for example maintenance approach, training, and technical manuals, should be integrated with P&D phase-specific test and evaluation and logistics and sustainment activities identified in DAG Chapter 9 Test and Evaluation and Chapter 5 Life-Cycle Logistics, respectively. This phase typically has several major efforts as shown in Figure 4.2.6.F1: Low-Rate Initial Production (LRIP), Operational Test and Evaluation (OT&E), Full-Rate Production (FRP) and Full Deployment (FD), and deployment of capability in support of the Initial and Full Operational Capabilities. The Full-Rate Production Decision Review (FRP DR) and/or Full Deployment Decision Review (FD DR) serves as a key decision point between LRIP (and OT&E) and FRP/FD.

Figure 4.2.6.F1. Production and Deployment Phase

Figure 4.2.6.F1. Production and Deployment Phase

Manufacturing development should be complete at Milestone C, but improvements or redesigns may require unanticipated, additional manufacturing process development and additional testing (e.g., delta qualification or delta first article test). For example, it may be discovered that changing the product design may provide enhancements in manufacturing or other supporting processes. At the conclusion of LRIP, all manufacturing development should be completed, with no significant manufacturing risks carried into FRP. The dynamic nature of the varied production elements requires a proactive approach to mitigate emerging risks.

Readiness for OT&E is a significant assessment of a system’s maturity (see DAG Chapter 9 Test and Evaluation). The Systems Engineer plays a key role in ensuring systems are ready to enter OT&E. Scarce resources are wasted when an operational test is halted or terminated early because of technical problems that should have been resolved before the start of OT&E.

During deployment, units attain Initial Operational Capability (IOC), then Full Operational Capability (FOC).

Besides ensuring a successful FOC, the SE activities:

  • Mature manufacturing, production, and deployment procedures
  • Respond to deficiencies and develop corrective actions
  • Support validation of system performance associated with OT&E
  • Validate the production configuration prior to FRP / FD

Roles and Responsibilities

In addition to the general responsibilities identified in DAG section 4.1.4. Engineering Resources, the Program Manager focuses on the following P&D activities, which rely on and support SE efforts:

  • Conduct activities in support of the production contract award(s)
  • Resource and conduct event-driven technical reviews (including the Physical Configuration Audit (PCA), Post Implementation Review (PIR), and FRP and/or FD DR) and ensure that criteria are met
  • Manage and control the final product baseline
  • Manage risks, in particular the manufacturing, production, and deployment risks
  • Accept system deliveries (i.e., DD-250)

In addition to the general responsibilities identified in DAG section 4.1.4. Engineering Resources, the Systems Engineer is responsible to:

  • Analyze deficiencies discovered from OT&E, acceptance tests, production reports, and maintenance reports and provide correction actions
  • Conduct rigorous production risk assessments; plan and resource effective risk mitigation actions
  • Continue conducting producibility trade studies to determine the most cost-effective fabrication/manufacturing process
  • Develop approaches and plans to validate fabrication/manufacturing processes
  • Assess full-rate production feasibility within program constraints. This may include assessing contractor and principal subcontractor production experience and capability, new fabrication technology, special tooling, and production personnel training requirements
  • Identify long-lead items and critical materials; plan for obsolescence and implement DMSMS measures to mitigate impacts to production and sustainment
  • Update production costs as a part of life-cycle cost management
  • Support updates to the production schedules
  • Support technical reviews and production decisions
  • Support materiel readiness and logistical activities, including fielding and training
  • Continue to support the Configuration Management Board to control changes to the product baseline during test and fielding
  • Update and maintain system certifications and interfaces with external systems, as necessary

Inputs

Table 4.2.6.T1 summarizes the primary inputs associated with this systems acquisition part of the life cycle.

Table 4.2.6.T1. Inputs Associated with P&D Phase

Inputs for P&D Phase

Capability Production Document (CPD)

Acquisition Decision Memorandums (ADM) associated with Milestone C, LRIP, and FRP DR and FD DR

  • ADMs may contain additional direction
  • Milestone C may not coincide with LRIP
  • FRP DR and FD DR ADMs are issued during P&D phase

SEP

  • Updated functional, allocated, and product baselines; verified and validated production processes, and validation results / decisions
  • Updated technical products including associated design and management decisions
  • PDUSD(AT&L) memorandum, “Document Streamlining – Program Strategies and Systems Engineering Plan,” April 20, 2011
  • See DAG section 4.1.2 Systems Engineering Plan

Reliability, Availability, Maintainability, and Cost Rationale (RAM-C) Report

  • Attachment to SEP as directed by DTM 11-003

Reliability growth curves (RGCs)

  • Attachment to TEMP as directed by DTM 11-003

PPP

  • Updated at FRP DR and/or FD DR
  • PDUSD(AT&L) memorandum, “Document Streamlining - Program Protection Plan (PPP),” July 18, 2011
  • See DAG Chapter 13 Program Protection

Trade study results

  • Results could include knees-in-the-curves sensitivity analyses, product selections, etc.
  • P&D phase trade studies may support manufacturing or other system mods (technology insertion, technology refresh, etc.)

Assumptions and constraints

  • Rationale for all assumptions, constraints, and basis for trades

Environment, Safety, and Occupational Health (ESOH) analyses

  • Programmatic Environment, Safety, and Occupational Health Evaluation (PESHE) and NEPA/EO 12114 Compliance Schedule

Risk assessment

  • Risk mitigation plans
  • Acceptable risks for achieving Initial Operational Capability (IOC) and Full Operational Capability (FOC)
  • Updated Risk Management Plan to reflect change from acquisition to deployment and initiation of sustainment activities

Consideration of technology issues

Manufacturing readiness

  • Assessment of manufacturing readiness supports MS C and initiation of production

Interdependencies / interfaces / memoranda of agreement (MOAs)

  • Understanding of the unique program interdependencies, interfaces, and associated MOA

System performance specification (updated if necessary) including verification matrix

  • System element specifications (updated if necessary) including verification matrix

Manufacturing, performance and quality metrics critical to program success are identified and tracked

  • 30%, 60%, and 100% completed manufacturing drawings

Initial product baseline

Product acceptance test

Other technical information such as models and simulations generated during the EMD phase

Results of EMD prototyping activities

Manufacturing prototyping activities supporting P&D phase

System Threat Assessment Report (STAR)

Acquisition Program Baseline (APB)

Affordability Assessment

  • Affordability targets treated as KPPs
  • Should cost goals to achieve efficiencies and control unproductive expenses
  • Updated will cost values and affordability targets as documented in the Life-Cycle Sustainment Plan (LCSP), including informed advice to manpower estimates
  • Value engineering results, as appropriate (see DAG section 4.3.19.3. Value Engineering)
  • See DAG Chapter 3 Affordability and Life-Cycle Resource Estimates

Supply chain sources

Updated Manufacturing processes

Production budget/cost model validated and resources considered sufficient to support LRIP and FRP

Acquisition Strategy (AS)

LCSP

Human Systems Integration (HSI) analyses

  • Manpower, personnel, and training (MPT) requirement updates
  • Refinement of HSI inputs to specifications, human system interfaces design, multi-domain verification, testing, and usability evaluations
  • See DAG Chapter 6 Human Systems Integration

TEMP

Developmental test and evaluation (DT&E) assessments

Draft and final RFP

Security Classification Guide (SCG)

Information Support Plan (ISP) of Record

Other analyses

  • Other prior analytic, prototyping, and/or technology demonstration efforts completed by the science and technology (S&T) community; technology insertion/transition can occur at any point in the life cycle

Activities

The P&D phase SE activities begin when a favorable Milestone C decision has been made (see DAG section 4.2.5. Engineering and Manufacturing Development Phase) and end when FOC is achieved. Figure 4.2.6.F2 provides the end-to-end perspective and the integration of SE technical reviews and audits across the acquisition life cycle.

Figure 4.2.6.F2. Weapon System Development Life Cycle

Figure 4.2.6.F2. Weapon System Development Life Cycle

SE activities that occur throughout the P&D phase include:

  • Provide technical support to prepare for the Operations and Sustainment (O&S) phase, reviewing and providing inputs on the maintenance approach, acquisition strategy, training, and technical manuals
  • Determine root cause of problems, identify corrective actions, and manage to completion
  • Analyze system deficiencies generated during OT&E, acceptance testing, production, and deployment
  • Address problem/failure reports through the use of a comprehensive data collection approach like a Failure Reporting, Analysis and Corrective Action System (FRACAS)
  • Manage and control of configuration updates (hardware, software, and specifications) to the product baseline
  • Re-verify and validate production configuration

SE provides inputs to OT&E readiness assessments including:

  • Results of prior DT&E
  • Analysis of the system's progress in achieving performance metrics (see DAG section 4.3.4. Technical Assessment Process)
  • Assessment on satisfaction of approved OT&E entrance criteria
  • Assessment of technical risk
  • Assessment of software maturity and status of software trouble reports
  • Identification of any potential design constraints affecting the system's expected performance during OT&E

In both the Production and Deployment and O&S phases the Systems Engineer should identify and plan for potential obsolescence impacts (i.e., Diminishing Manufacturing Sources and Material Shortages (DMSMS)). DMSMS problems are an increasing concern as the service lives of DoD weapon systems are extended and the product life cycle for high-technology system elements decreases.

The PCA is a SE audit typically conducted in the P&D phase (see DAG section 4.2.16. Physical Configuration Audit for additional information regarding the PCA).

Test activities during the P&D phase that depend on SE support and involvement include the Assessment of Operational Test Readiness (AOTR) for MDAPs, Operational Test Readiness Reviews (OTRRs), initial and follow-on OT&E (IOT&E and FOT&E), and live-fire test and evaluations (LFT&E), as appropriate (see DAG Chapter 9 Test and Evaluation). In addition, any corrective actions or design changes implemented in response to test identified deficiencies require additional regression testing.

The Systems Engineer, in collaboration with the Chief Developmental Tester, should identify technical support needed for operational assessments and document in the Test and Evaluation Master Plan (TEMP). Associated SE activities and plans should be in the SEP (see DAG section 4.1.2. Systems Engineering Plan, 4.2.8. Technical Reviews and Audits Overview, and DAG Chapter 9 Test and Evaluation).

Outputs and Products

The technical outputs and products from the P&D phase identified in Table 4.2.6.T2 are some of the inputs necessary to support SE processes in the O&S phase. They should support the program’s transition into full operations and sustainment. Technical outputs associated with technical reviews in this phase are addressed later in this chapter.

Table 4.2.6.T2. Technical Outputs Associated with P&D Phase

Technical Outputs from P&D Phase

Informed advice to CPD Update

  • CPD may be updated to justify system enhancements and modifications from the P&D phase

Informed advice to ADM

Updated IMP, IMS, and MOAs/MOUs

Validated system

  • Updated functional, allocated, and product baselines; verified and validated production processes, and validation results / decisions
  • Associated technical products including associated design and management decisions

PPP (updated)

  • Updated at FRP DR and/or FD DR
  • PDUSD(AT&L) memorandum, “Document Streamlining - Program Protection Plan (PPP),” July 18, 2011
  • See DAG Chapter 13 Program Protection

Trade study results

  • P&D Phase trade studies may support manufacturing or other system mods (technology insertion, technology refresh, etc.)

Assumptions and constraints

  • Rationale for all assumptions, constraints, and basis for trades

ESOH analyses

  • Updated Programmatic Environment, Safety, and Occupational Health Evaluation (PESHE) and NEPA/EO 12114 Compliance Schedule

Assessment of technical risk (updated)

  • Risk assessment identifying mitigation plans, acceptable risks for achieving FOC
  • Updated Risk Management Plan (RMP) to reflect change from acquisition to sustainment

Interdependencies / interfaces / memoranda of agreement (MOAs)

  • Understanding of the unique program interdependencies, interfaces, and associated MOA

System performance specification (updated if necessary) including verification matrix;

system element specifications (updated if necessary) including verification matrix

Manufacturing and production metrics

PCA results and an updated product baseline

Acceptance test data to assess product conformance and to support DD250 of end items

Other technical information such as models and simulations generated during the P&D phase

Technical information that is the basis of the updates to the Cost Analysis Requirements Description (CARD) and manpower estimates

Industrial base capabilities; updated manufacturing processes and supply chain sources

Informed advice to Life-Cycle Sustainment Plan (LCSP)

  • Updated at FRP DR and/or FDDR
  • Updated will cost values and affordability targets as documented in the LCSP, including informed advice to manpower estimates
  • Value engineering results, as appropriate (see DAG section 4.3.19.3. Value Engineering)
  • PDUSD(AT&L) memorandum, “Document Streamlining – Life-Cycle Sustainment Plan (LCSP),” September 14, 2011
  • See DAG Chapter 5 Life-cycle Logistics

Human Systems Integration (HSI) analyses

Informed advice to TEMP (updated)

Operational Test and Evaluation (OT&E) Assessments/Reports

Draft and final RFP(s) for production and SE support to O&S activities

Previous and Next Page arrows

Previous Page Next Page

List of All Contributions at This Location

No items found.

Popular Tags

Browse

https://acc.dau.mil/UI/img/bo/minus.gifWelcome to the Defense Acquisition...
https://acc.dau.mil/UI/img/bo/plus.gifForeword
https://acc.dau.mil/UI/img/bo/minus.gifChapter 1 -- Department of Defense...
https://acc.dau.mil/UI/img/bo/plus.gif1.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif1.1. Integration of the DoD Decision...
https://acc.dau.mil/UI/img/bo/plus.gif1.2. Planning Programming Budgeting and...
https://acc.dau.mil/UI/img/bo/plus.gif1.3. Joint Capabilities Integration and...
https://acc.dau.mil/UI/img/bo/plus.gif1.4. Defense Acquisition System
https://acc.dau.mil/UI/img/bo/plus.gifChapter 2 -- Program Strategies
https://acc.dau.mil/UI/img/bo/minus.gifChapter 3 -- Affordability and...
https://acc.dau.mil/UI/img/bo/plus.gif3.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif3.1. Life-Cycle Costs/Total Ownership...
https://acc.dau.mil/UI/img/bo/plus.gif3.2. Affordability
https://acc.dau.mil/UI/img/bo/plus.gif3.3. Analysis of Alternatives
https://acc.dau.mil/UI/img/bo/plus.gif3.4. Cost Estimation for Major Defense...
https://acc.dau.mil/UI/img/bo/plus.gif3.5. Manpower Estimates
https://acc.dau.mil/UI/img/bo/plus.gif3.6. Major Automated Information Systems...
https://acc.dau.mil/UI/img/bo/plus.gif3.7. Principles for Life-Cycle Cost...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 4 -- Systems Engineering
https://acc.dau.mil/UI/img/bo/plus.gif4.0. Overview
https://acc.dau.mil/UI/img/bo/minus.gif4.1. Introduction
https://acc.dau.mil/UI/img/bo/minus.gif4.1.1. Systems Engineering Policy and...
https://acc.dau.mil/UI/img/bo/minus.gif4.1.2. Systems Engineering Plan
https://acc.dau.mil/UI/img/bo/minus.gif4.1.3. Systems Level Considerations
https://acc.dau.mil/UI/img/bo/plus.gif4.1.3.1. Software
https://acc.dau.mil/UI/img/bo/minus.gif4.1.4. Engineering Resources
https://acc.dau.mil/UI/img/bo/minus.gif4.1.5. Certifications
https://acc.dau.mil/UI/img/bo/minus.gif4.1.6. Systems Engineering Role in...
https://acc.dau.mil/UI/img/bo/minus.gif4.2. Systems Engineering Activities in...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.1. Life-Cycle Expectations
https://acc.dau.mil/UI/img/bo/plus.gif4.2.2. Pre-Materiel Development Decision
https://acc.dau.mil/UI/img/bo/plus.gif4.2.3. Materiel Solution Analysis Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.4. Technology Development Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.5. Engineering and Manufacturing...
https://acc.dau.mil/UI/img/bo/minus.gif4.2.6. Production and Deployment Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.7. Operations and Support Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.8. Technical Reviews and Audits...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.9. Alternative Systems Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.10. System Requirements Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.11. System Functional Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.12. Preliminary Design Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.13. Critical Design Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.14. System Verification...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.15. Production Readiness Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.16. Physical Configuration Audit
https://acc.dau.mil/UI/img/bo/plus.gif4.2.17. In-Service Review
https://acc.dau.mil/UI/img/bo/minus.gif4.3. Systems Engineering Processes
https://acc.dau.mil/UI/img/bo/plus.gif4.3.2. Technical Planning Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.3. Decision Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.4. Technical Assessment Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.5. Requirements Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.6. Risk Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.7. Configuration Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.8. Technical Data Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.9. Interface Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.10. Stakeholder Requirements...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.11. Requirements Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.12. Architecture Design Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.13. Implementation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.14. Integration Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.15. Verification Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.16. Validation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.17. Transition Process
https://acc.dau.mil/UI/img/bo/minus.gif4.3.18. Design Considerations
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.1. Accessibility (Section 508...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.2. Affordability – Systems...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.3. Anti-Counterfeiting
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.4. Commercial-Off-the-Shelf
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.5. Corrosion Prevention and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.6. Critical Safety Item
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.7. Demilitarization and Disposal
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.8. Diminishing Manufacturing...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.9. Environment Safety and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.10. Human Systems Integration
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.11. Insensitive Munitions
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.12. Intelligence (Life-Cycle...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.13. Interoperability and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.14. Item Unique Identification
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.15. Open Systems Architecture
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.16. Operational Energy
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.17. Packaging Handling Storage...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.18. Producibility Quality and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.19. Reliability and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.20. Spectrum Management
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.21. Standardization
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.22. Supportability
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.23. Survivability and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.24. System Security Engineering
https://acc.dau.mil/UI/img/bo/plus.gif4.3.19. Tools Techniques and Lessons...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 5 -- Life-Cycle Logistics
https://acc.dau.mil/UI/img/bo/plus.gifChapter 6 -- Human Systems Integration...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 7 -- Acquiring Information...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 8 -- Intelligence Analysis...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 9 -- Test and Evaluation (T&E)
https://acc.dau.mil/UI/img/bo/plus.gifChapter 10 -- Decisions Assessments and...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 11 -- Program Management...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 12 - Defense Business System...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 13 -- Program Protection
https://acc.dau.mil/UI/img/bo/plus.gifChapter 14 -- Acquisition of Services
https://acc.dau.mil/UI/img/bo/minus.gifDoD Directive 5000.01
https://acc.dau.mil/UI/img/bo/plus.gifENCLOSURE 1 ADDITIONAL POLICY
https://acc.dau.mil/UI/img/bo/plus.gifDoD Instruction 5000.02
https://acc.dau.mil/UI/img/bo/plus.gifRecent Policy and Guidance
https://acc.dau.mil/UI/img/bo/minus.gifCurrent JCIDS Manual and CJCSI 3170.01 I
https://acc.dau.mil/UI/img/bo/minus.gifDefense Acquisition Guidebook Key...
ACC Practice Center Version 3.2
  • Application Build 3.2.9
  • Database Version 3.2.9