4.2.10. System Requirements Review

Topic

Previous and Next Page arrows

DEFENSE ACQUISITION GUIDEBOOK
Chapter 4 -- Systems Engineering

4.2.10. System Requirements Review

4.2.10. System Requirements Review

The System Requirements Review (SRR) is a multi-disciplined technical review to ensure that the developer is ready to proceed with the initial system design. This review assesses whether the system requirements as captured in the system performance specification:

  • Are consistent with the preferred materiel solution (including its support concept) from the Materiel Solution Analysis (MSA) phase
  • Are consistent with available technologies resulting from the prototyping efforts
  • Adequately consider the maturity of interdependent systems

All system requirements and performance requirements derived from the Initial Capabilities Document (ICD) or draft Capability Development Document (CDD) should be defined and consistent with cost, schedule, risk, and other system constraints; and with end user expectations. Also important to this review is a mutual understanding (between the program office and the developer) of the technical risk inherent in the system performance specification.

For Major Defense Acquisition Programs (MDAPs), the PDUSD(AT&L) memorandum, “Improving Milestone Process Effectiveness” requires a Milestone A review before approving release of the final Request for Proposal (RFP) for the Technology Development (TD) phase; therefore, it is suggested that the program office perform a review similar to an SRR to assess readiness and risks of the technical content of the draft RFP(s) prior to Milestone A. This program office review most likely occurs after the Functional Capabilities Board (FCB) review of the AoA and other analytic results.

If the program’s Technology Development Strategy (TDS) includes competing contractual efforts during the TD phase, an SRR should be held with each participating developer to ensure the requirements are thoroughly and properly understood. This review also ensures that system of systems (SoS) requirements, in the form of logical and physical interfaces and desired performance outcomes, have been levied on the system to be procured and are consistent with the ICD and/or draft CDD. These requirements are documented in the system performance specification and managed through external communication and technical interfaces in accordance with the Systems Engineering Plan (SEP).

Roles and Responsibilities

The unique Program Manager responsibilities associated with an SRR include:

  • Approve, fund, and staff the SRR as planned in the SEP developed by the Systems Engineer
  • Manage and approve changes to the system performance specification
  • Establish the plan to SFR in applicable contract documents including the SE Master Plan, Integrated Master Schedule (IMS), and Integrated Master Plan (IMP)
  • Ensure the plan includes independent subject matter experts to participate in each review

The unique Systems Engineer responsibilities associated with an SRR include:

  • Ensure all performance requirements, both explicit and derived, are defined and traceable (both directions) between requirements in the draft CDD including Key Performance Parameters (KPPs), Key System Attributes (KSAs), other system attributes, and the system performance specification (see CJCSI 3170.01 JCIDS)
  • Ensure verification methods are identified for all system requirements
  • Ensure risk items associated with system requirements are identified and analyzed, and mitigation plans are in place
  • Ensure adequate plans are in place to complete the technical activities to proceed from SRR to the System Functional Review (SFR)
  • Ensure plans to proceed to SFR allow for contingencies

Inputs and Review Criteria

Figure 4.2.10.F1 provides the end-to-end perspective and the integration of SE technical reviews and audits across the acquisition life cycle. The SRR criteria are developed to best support the program’s technical scope and risk and are documented in the program’s SEP at Milestone A.

Figure 4.2.10.F1. Weapon System Development Life Cycle

Figure 4.2.10.F1. Weapon System Development Life Cycle

Table 4.2.10.T1 defines the suggested SRR products and associated review criteria. The review should not begin until these criteria are established, evidence has been received to support a case for success, and any prior technical review is completed and its action items closed. This is also an opportunity to assess whether technical requirements from all acquisition documentation (e.g., Program Protection Plan (PPP), Test and Evaluation Master Plan (TEMP), Reliability, Availability, Maintainability, and Cost Rationale (RAM-C) Report) are flowed to specifications. If the program’s TDS includes competing contractual efforts, an SRR should be held with each developer. A risk assessment tool for SRR preparation is the DoD SRR Checklist. This is a best practice review.

Table 4.2.10.T1. SRR Products and Criteria

Product

SRR Criteria

Cost Estimate

  • Preliminary Cost Analysis Requirements Description (CARD) is consistent with the approved system performance specification
  • Preliminary software development estimates established with effort, schedule, and cost analysis
  • Updated cost estimate fits within the existing budget

Risk Assessment

  • Technical risks are identified, and mitigation plans are in place
  • Risk Management Plan (RMP) is complete and adequate

System Performance Specification

  • Contractor clearly demonstrates an understanding of the system requirements consistent with the ICD and draft CDD
  • System requirements are sufficiently detailed and understood to enable system functional definition and functional decomposition
  • System requirements are assessed to be verifiable (see Chief Developmental Tester in DAG Chapter 9 Test and Evaluation)
  • Requirements can be met given the technology maturation achieved and evidence from competitive prototyping
  • External interfaces to the system have been documented in interface control documents
  • SoS technical interfaces are adequately defined, including interdependences associated with schedule, test, and configuration changes
  • Preliminary identification of all software components (tactical, support, deliverable, non-deliverable, etc.) are completed
  • Human Systems Integration (HSI) and sustainment requirements have been reviewed and included in the overall system design (see DAG section 4.3.18.10 and DAG Chapter 6 Human Systems Integration)
  • Contractor has adequately expanded the system specification to reflect tailored, derived, and correlated design requirements
  • Bidirectional requirements traceability between the draft CDD, the Statement of Work (SOW), and the System Specification has been documented
  • System performance specification is approved, including stakeholder concurrence, with sufficiently conservative requirements to allow for design trade space

Technical Plans

  • Contractor’s Systems Engineering Management Plan (SEMP) is complete and adequate
  • Cost and critical path drivers have been identified
  • The program schedule is executable with an acceptable level of technical and cost risk
  • Adequate processes and metrics are in place for the program to succeed
  • SE is properly staffed
  • Program is executable within the existing budget
  • Software functionality in the system specification is consistent with the software sizing estimates and the resource-loaded schedule
  • Programming languages and architectures, security requirements, and operational and support concepts have been identified
  • Hazards have been reviewed and mitigating courses of action have been allocated within the overall system design
  • Key technology elements have been identified, readiness assessed, and maturation plans developed
  • Software development strategy is complete and adequate
  • Program technical risks are adequately identified and documented such that there is a clear understanding regarding the contractor's ability to meet the specification requirements
  • Draft verification methodologies have been adequately defined for each specification requirement
  • Certifying agencies have been identified and certification requirements are understood
  • Draft test plans have been developed in support of the TD phase (See Chief Developmental Tester in DAG Chapter 9 Test and Evaluation)
  • Government and contractor configuration management (CM) strategies are complete and adequate
  • The Modeling and Simulation (M&S) Plan for life-cycle support (including life-cycle costs / total ownership costs (LCC/TOC), training devices, tactics, air vehicle, mission system etc.) is complete and adequate to support system design and operation
  • The manufacturing and production strategy is complete and adequate
  • Integrated Master Schedule (IMS) adequately identifies the critical path and is resourced at reasonable levels, based on realistic performance/efficiency expectations
  • Unique work requirements for competitive prototyping have been identified
  • Product support plan and sustainment concepts have been defined with the corresponding metrics

Output and Products

The Technical Review Chair determines when the review is complete. Once the products have been reviewed and approved in SRR, they provide a sound technical basis for proceeding with system functional definition and preliminary design.

Previous and Next Page arrows

Previous Page Next Page

List of All Contributions at This Location

No items found.

Popular Tags

Browse

https://acc.dau.mil/UI/img/bo/minus.gifWelcome to the Defense Acquisition...
https://acc.dau.mil/UI/img/bo/plus.gifForeword
https://acc.dau.mil/UI/img/bo/plus.gifChapter 1 -- Department of Defense...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 2 -- Program Strategies
https://acc.dau.mil/UI/img/bo/plus.gif2.0 Overview
https://acc.dau.mil/UI/img/bo/plus.gif2.1. Program Strategies—General
https://acc.dau.mil/UI/img/bo/plus.gif2.2. Program Strategy Document...
https://acc.dau.mil/UI/img/bo/plus.gif2.3. Program Strategy Relationship to...
https://acc.dau.mil/UI/img/bo/plus.gif2.4. Relationship to Request for...
https://acc.dau.mil/UI/img/bo/plus.gif2.5. Program Strategy Classification...
https://acc.dau.mil/UI/img/bo/plus.gif2.6. Program Strategy Document Approval...
https://acc.dau.mil/UI/img/bo/plus.gif2.7. Acquisition Strategy versus...
https://acc.dau.mil/UI/img/bo/plus.gif2.8. Technology Development...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 3 -- Affordability and...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 4 -- Systems Engineering
https://acc.dau.mil/UI/img/bo/minus.gif4.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif4.1. Introduction
https://acc.dau.mil/UI/img/bo/minus.gif4.2. Systems Engineering Activities in...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.1. Life-Cycle Expectations
https://acc.dau.mil/UI/img/bo/plus.gif4.2.2. Pre-Materiel Development Decision
https://acc.dau.mil/UI/img/bo/plus.gif4.2.3. Materiel Solution Analysis Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.4. Technology Development Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.5. Engineering and Manufacturing...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.6. Production and Deployment Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.7. Operations and Support Phase
https://acc.dau.mil/UI/img/bo/plus.gif4.2.8. Technical Reviews and Audits...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.9. Alternative Systems Review
https://acc.dau.mil/UI/img/bo/minus.gif4.2.10. System Requirements Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.11. System Functional Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.12. Preliminary Design Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.13. Critical Design Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.14. System Verification...
https://acc.dau.mil/UI/img/bo/plus.gif4.2.15. Production Readiness Review
https://acc.dau.mil/UI/img/bo/plus.gif4.2.16. Physical Configuration Audit
https://acc.dau.mil/UI/img/bo/plus.gif4.2.17. In-Service Review
https://acc.dau.mil/UI/img/bo/minus.gif4.3. Systems Engineering Processes
https://acc.dau.mil/UI/img/bo/plus.gif4.3.2. Technical Planning Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.3. Decision Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.4. Technical Assessment Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.5. Requirements Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.6. Risk Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.7. Configuration Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.8. Technical Data Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.9. Interface Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.10. Stakeholder Requirements...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.11. Requirements Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.12. Architecture Design Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.13. Implementation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.14. Integration Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.15. Verification Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.16. Validation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.17. Transition Process
https://acc.dau.mil/UI/img/bo/minus.gif4.3.18. Design Considerations
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.1. Accessibility (Section 508...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.2. Affordability – Systems...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.3. Anti-Counterfeiting
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.4. Commercial-Off-the-Shelf
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.5. Corrosion Prevention and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.6. Critical Safety Item
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.7. Demilitarization and Disposal
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.8. Diminishing Manufacturing...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.9. Environment Safety and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.10. Human Systems Integration
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.11. Insensitive Munitions
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.12. Intelligence (Life-Cycle...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.13. Interoperability and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.14. Item Unique Identification
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.15. Open Systems Architecture
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.16. Operational Energy
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.17. Packaging Handling Storage...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.18. Producibility Quality and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.19. Reliability and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.20. Spectrum Management
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.21. Standardization
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.22. Supportability
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.23. Survivability and...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18.24. System Security Engineering
https://acc.dau.mil/UI/img/bo/plus.gif4.3.19. Tools Techniques and Lessons...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 5 -- Life-Cycle Logistics
https://acc.dau.mil/UI/img/bo/minus.gifChapter 6 -- Human Systems Integration...
https://acc.dau.mil/UI/img/bo/plus.gif6.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif6.1. Total System Approach
https://acc.dau.mil/UI/img/bo/plus.gif6.2 HSI - Integration Focus
https://acc.dau.mil/UI/img/bo/plus.gif6.3. Human Systems Integration Domains
https://acc.dau.mil/UI/img/bo/plus.gif6.4. Human Systems Integration (HSI)...
https://acc.dau.mil/UI/img/bo/plus.gif6.5. Manpower Estimates
https://acc.dau.mil/UI/img/bo/plus.gif6.6. Additional References
https://acc.dau.mil/UI/img/bo/minus.gifChapter 7 -- Acquiring Information...
https://acc.dau.mil/UI/img/bo/plus.gif7.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif7.1. Introduction
https://acc.dau.mil/UI/img/bo/plus.gif7.2. DoD Information Enterprise
https://acc.dau.mil/UI/img/bo/plus.gif7.3. Interoperability and Supportability...
https://acc.dau.mil/UI/img/bo/plus.gif7.4. Sharing Data, Information, and...
https://acc.dau.mil/UI/img/bo/plus.gif7.5. Information Assurance (IA)
https://acc.dau.mil/UI/img/bo/plus.gif7.6. Electromagnetic Spectrum
https://acc.dau.mil/UI/img/bo/plus.gif7.7. Accessibility of Electronic and...
https://acc.dau.mil/UI/img/bo/plus.gif7.8. The Clinger-Cohen Act (CCA) --...
https://acc.dau.mil/UI/img/bo/plus.gif7.9. Post-Implementation Review (PIR)
https://acc.dau.mil/UI/img/bo/plus.gif7.10. Commercial Off-the-Shelf (COTS)...
https://acc.dau.mil/UI/img/bo/plus.gif7.11. Space Mission Architectures
https://acc.dau.mil/UI/img/bo/minus.gifChapter 8 -- Intelligence Analysis...
https://acc.dau.mil/UI/img/bo/plus.gif8.0. Introduction
https://acc.dau.mil/UI/img/bo/plus.gif8.1. Threat Intelligence Support
https://acc.dau.mil/UI/img/bo/plus.gif8.2. Signature and other Intelligence...
https://acc.dau.mil/UI/img/bo/plus.gif8.3. Support to the Intelligence...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 9 -- Test and Evaluation (T&E)
https://acc.dau.mil/UI/img/bo/minus.gifChapter 10 -- Decisions Assessments and...
https://acc.dau.mil/UI/img/bo/plus.gif10.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif10.1. Decision Points
https://acc.dau.mil/UI/img/bo/plus.gif10.2. Executive Review Forums
https://acc.dau.mil/UI/img/bo/plus.gif10.3. Integrated Product and Process...
https://acc.dau.mil/UI/img/bo/plus.gif10.4. Role of Exit Criteria
https://acc.dau.mil/UI/img/bo/plus.gif10.5. Role of Independent Assessments
https://acc.dau.mil/UI/img/bo/plus.gif10.5.3. Preliminary Design Review (PDR)...
https://acc.dau.mil/UI/img/bo/plus.gif10.6. Information Sharing and DoD...
https://acc.dau.mil/UI/img/bo/plus.gif10.7. Management Control
https://acc.dau.mil/UI/img/bo/plus.gif10.8. Program Plans
https://acc.dau.mil/UI/img/bo/plus.gif10.9. Acquisition Program Baseline (APB)
https://acc.dau.mil/UI/img/bo/plus.gif10.10. Periodic Reports
https://acc.dau.mil/UI/img/bo/plus.gif10.11. Major Automated Information...
https://acc.dau.mil/UI/img/bo/plus.gif10.12. Defense Acquisition Executive...
https://acc.dau.mil/UI/img/bo/plus.gif10.13. Acquisition Visibility
https://acc.dau.mil/UI/img/bo/plus.gif10.14. Special Interest Programs
https://acc.dau.mil/UI/img/bo/plus.gif10.15. Relationship of Affordability and...
https://acc.dau.mil/UI/img/bo/plus.gif10.16. Acquisition Program Transition...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 11 -- Program Management...
https://acc.dau.mil/UI/img/bo/plus.gif11.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif11.1. Joint Programs
https://acc.dau.mil/UI/img/bo/plus.gif11.2. International Programs
https://acc.dau.mil/UI/img/bo/plus.gif11.3. Integrated Program Management
https://acc.dau.mil/UI/img/bo/plus.gif11.4. Knowledge-Based Acquisition
https://acc.dau.mil/UI/img/bo/plus.gif11.5. Technical Representatives at...
https://acc.dau.mil/UI/img/bo/plus.gif11.6. Contractor Councils
https://acc.dau.mil/UI/img/bo/plus.gif11.7 Property
https://acc.dau.mil/UI/img/bo/plus.gif11.8. Modeling and Simulation (M&S)...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 12 - Defense Business System...
https://acc.dau.mil/UI/img/bo/plus.gif12.0 Overview
https://acc.dau.mil/UI/img/bo/plus.gif12.1 Business Capability Definition...
https://acc.dau.mil/UI/img/bo/plus.gif12.2 Investment Management (IM) Phase
https://acc.dau.mil/UI/img/bo/plus.gif12.3 Execution
https://acc.dau.mil/UI/img/bo/plus.gif12.4 DBS-specific Criteria
https://acc.dau.mil/UI/img/bo/plus.gif12.5 Tools and Methods
https://acc.dau.mil/UI/img/bo/plus.gifChapter 13 -- Program Protection
https://acc.dau.mil/UI/img/bo/minus.gifChapter 14 -- Acquisition of Services
https://acc.dau.mil/UI/img/bo/plus.gif14.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif14.1. Introduction to the Acquisition of...
https://acc.dau.mil/UI/img/bo/plus.gif14.2. The Planning Phase
https://acc.dau.mil/UI/img/bo/plus.gif14.3. The Development Phase
https://acc.dau.mil/UI/img/bo/plus.gif14.4. The Execution Phase
https://acc.dau.mil/UI/img/bo/plus.gifAppendix A -- REQUIREMENTS ROADMAP...
https://acc.dau.mil/UI/img/bo/plus.gifAppendix B -- SERVICE ACQUISITION...
https://acc.dau.mil/UI/img/bo/plus.gifAppendix C -- SERVICE ACQUISITION MALL...
https://acc.dau.mil/UI/img/bo/plus.gifAppendix D -- MARKET RESEARCH RESOURCES
https://acc.dau.mil/UI/img/bo/plus.gifAppendix E -- GLOSSARY
https://acc.dau.mil/UI/img/bo/plus.gifDoD Directive 5000.01
https://acc.dau.mil/UI/img/bo/minus.gifDoD Instruction 5000.02
https://acc.dau.mil/UI/img/bo/plus.gifTABLE OF CONTENTS
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 1 -- References
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 2 -- Procedures
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 3 -- Acquisition Category...
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 4 -- Statutory and Regulatory...
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 5 -- IT Considerations
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 6 -- Integrated T&E
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 7 -- Resource Estimation
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 8 -- Human Systems Integration...
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 9 -- Acquisition of Services
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 10 -- Program Management
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 11 -- Management of Defense...
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 12 -- Systems Engineering
https://acc.dau.mil/UI/img/bo/plus.gifRecent Policy and Guidance
https://acc.dau.mil/UI/img/bo/plus.gifCurrent JCIDS Manual and CJCSI 3170.01 I
https://acc.dau.mil/UI/img/bo/plus.gifDefense Acquisition Guidebook Key...
ACC Practice Center Version 3.2
  • Application Build 3.2.9
  • Database Version 3.2.9