REQUIREMENTS
|
SOURCE
|
WHEN REQUIRED
|
For Cost/Incentive Contracts1 ≥ $50 Million2
|
Part 7 of Reference (c)
This Instruction
|
|
- Compliance with EVM system guidelines in ANSI/EIA-7483
|
At contract award and throughout contract performance
|
- EVM system formally validated and accepted by cognizant contracting officer
|
At contract award and throughout contract performance
|
- Contract Performance Report
(DI-MGMT-81466A)
|
Monthly
|
- Integrated Master Schedule
(DI-MGMT-81650)
|
Monthly
|
- Integrated Baseline Reviews
|
Within 180 days after contract award, exercise of options, and major modifications
|
For Cost/Incentive Contracts1 ≥ $20 Million2 but < $50 Million2
|
Part 7 of Reference (c)
This Instruction
|
|
- Compliance with EVM system guidelines in ANSI/EIA-7483 (no formal EVM system validation)
|
At contract award and throughout contract performance
|
- Contract Performance Report (DI-MGMT-81466A) (tailoring recommended)
|
Monthly
|
- Integrated Master Schedule
(DI-MGMT-81650) (tailoring recommended)
|
Monthly
|
- Integrated Baseline Reviews
|
Within 180 days after contract award, exercise of options, and major modifications
|
For Cost/Incentive Contracts1 < $20 Million2
|
Part 7 of Reference (c)
This Instruction
|
At the discretion of the PM based on cost-benefit analysis
|
For Firm Fixed-Price Contracts1 regardless of dollar value
|
Part 7 of Reference (c)
This Instruction
|
Limited Use-must be approved by the MDA based on a business case analysis
|
Notes:
1. The term, "Contracts," includes contracts, subcontracts, intra-government work agreements, and other agreements. "Incentive" contracts include fixed-price incentive.
2. Application thresholds are in then-year dollars.
3. ANSI/EIA-748 = American National Standards Institute/Electronic Industries Alliance Standard 748, Earned Value Management Systems (Reference (av)).
|