7.3.2. Mandatory Policies

Topic
Previous Page Next Page

Previous and Next Page arrows

DEFENSE ACQUISITION GUIDEBOOK
Chapter 7 - Acquiring Information Technology

7.3.2. Mandatory Policies

7.3.2.1. DoD Directive 4630.05, "Interoperability and Supportability of Information Technology (IT) and National Security Systems (NSS)"

7.3.2.2. DoD Instruction 4630.8, "Procedures for Interoperability and Supportability of Information Technology (IT) and National Security Systems (NSS)"

7.3.2.3. DoD Directive 5000.01, "The Defense Acquisition System"

7.3.2.4. DoD Instruction 5000.02, "Operation of the Defense Acquisition System"

7.3.2.5. CJCS Instruction 6212.01, "Interoperability and Supportability of Information Technology and National Security Systems"

7.3.2.1. DoD Directive 4630.05, "Interoperability and Supportability of Information Technology (IT) and National Security Systems (NSS)"

  • Section 4.1 of this Directive requires IT and NSS employed by U.S. Forces to interoperate with existing and planned systems and equipment of joint, combined and coalition forces and with other U.S. Government Departments and Agencies, as appropriate (based on capability context).
  • Section 4.3 requires that IT and NSS interoperability and supportability needs, for a given capability, be identified through:
  • Section 4.5 provides that IT and NSS interoperability be verified early, and with sufficient frequency throughout a system's life, or upon changes affecting interoperability or supportability, to assess, evaluate, and certify its overall interoperability and supportability within a given capability. Joint interoperability certification testing shall be as comprehensive as possible, while still being cost effective, and shall be completed prior to fielding of a new IT and NSS capability or upgrade to existing IT and NSS.
  • Section 4.8 requires that interoperability and supportability needs be balanced with requirements for Information Assurance (IA).

7.3.2.2. DoD Instruction 4630.8, "Procedures for Interoperability and Supportability of Information Technology (IT) and National Security Systems (NSS)"

  • E3.1.5. A Net-Ready Key Performance Parameter (NR-KPP), consisting of verifiable performance measures and metrics, shall be used to assess information needs, information timeliness, IA, and net-ready attributes required for both the technical exchange of information and the end-to-end operational effectiveness of that exchange. A NR-KPP shall be defined for all IT and NSS defense acquisition and procurement programs and shall be specified to a level of detail that allows verification of interoperability throughout a system's life. The defined NR-KPP shall be developed so that it can be reliably measured, tested and evaluated.
  • E3.1.6. IT and NSS interoperability and supportability needs shall be managed, evaluated, and reported over the life of the system using an Information Support Plan (ISP). For all DoD ACAT programs and non-ACAT acquisitions and procurements, a ISP shall be produced and used to analyze interoperability and supportability requirements specified in the NR-KPP. . . .
  • 6.2.3.6.1. All IT and NSS, regardless of ACAT, must be tested for interoperability before fielding and the test results evaluated and systems certified by the DISA (JITC). IT and NSS interoperability test and evaluation shall be conducted throughout a system's life, and should be achieved as early as is practical to support scheduled acquisition or procurement decisions. Interoperability testing may be performed in conjunction with other testing (i.e., DT&E, OT&E, early-user test) whenever possible to conserve resources.
  • 6.2.3.6.2. IT and NSS interoperability testing can occur in multiple stages. Evolutionary acquisitions or procurements, and normal life-cycle modifications, result in a progressively more complete capability. Therefore, there may be instances when it is important to characterize a system's interoperability before all critical interface requirements have been tested and certified. However, all critical interfaces, identified in the NR-KPP, which have been tested, must be successfully certified for interoperability prior to fielding. When appropriate (e.g., between successful completion of OT and the fielding decision), the DISA (JITC) shall issue interim interoperability certification letters specifying which of the system's interoperability needs have been successfully met and which have not. The DISA (JITC) shall issue an overall system certification once the system successfully meets all requirements of the NR-KPP validated by the Chairman of the Joint Chiefs of Staff. The DISA (JITC) shall provide interoperability certification letters to the USD(AT&L), the USD(C)/CFO, the DoD CIO, the DPA&E (now DCAPE), the DOT&E, the Chairman of the Joint Chiefs of Staff, and the Commander, USJFCOM, as well as to the OTA and program manager, as applicable.

7.3.2.3. DoD Directive 5000.01, "The Defense Acquisition System"

  • Paragraph E1.1.10 establishes the requirement to acquire systems and families of systems that are interoperable with other U.S forces.
  • Paragraph E1.1.11 states the requirement that test and evaluation shall assess interoperability.
  • Paragraph E1.1.16 cites the need to maximize interoperability as a primary reason for acquisition managers to consider and use performance-based strategies for acquiring and sustaining products and services.

7.3.2.4. DoD Instruction 5000.02, "Operation of the Defense Acquisition System"

  • Enclosure 6, paragraph 2.c.(8) states: Interoperability Testing: All DoD MDAPs, programs on the OSD T&E Oversight list, post-acquisition (legacy) systems, and all programs and systems that must interoperate, are subject to interoperability evaluations throughout their life cycles to validate their ability to support mission accomplishment. For IT systems (including NSS) with interoperability requirements, the Joint Interoperability Test Command (JITC), regardless of ACAT, shall provide system interoperability test certification memorandums to the Deputy Under Secretary of Defense (Acquisition and Technology) (DUSD(A&T)), the DoD CIO, and the Director, Joint Staff J-6, throughout the system life-cycle.
  • Enclosure 6, paragraph 3 states: During DT&E, the materiel developer shall:
    • d. Assess technical progress and maturity against critical technical parameters, to include interoperability, documented in the TEMP; and
    • h. In the case of IT systems, including NSS, support the DoD Information Assurance Certification and Accreditation Process and Joint Interoperability Certification process; . . .

7.3.2.5. CJCS Instruction 6212.01, "Net Ready Key Performance Parameter (NR KPP)"

This publication provides instruction to develop a NR KPP.

1.a. Defines responsibilities and establishes policy and procedures to develop the NR KPP and NR KPP certification requirement for all information technology (IT) and national security systems (NSS) that contain joint interfaces or joint information exchanges.

Previous and Next Page arrows

List of All Contributions at This Location

No items found.

Popular Tags

Browse

https://acc.dau.mil/UI/img/bo/minus.gifWelcome to the Defense Acquisition...
https://acc.dau.mil/UI/img/bo/plus.gifForeword
https://acc.dau.mil/UI/img/bo/minus.gifChapter 1 -- Department of Defense...
https://acc.dau.mil/UI/img/bo/minus.gif1.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif1.1. Integration of the DoD Decision...
https://acc.dau.mil/UI/img/bo/plus.gif1.2. Planning Programming Budgeting and...
https://acc.dau.mil/UI/img/bo/plus.gif1.3. Joint Capabilities Integration and...
https://acc.dau.mil/UI/img/bo/plus.gif1.4. Defense Acquisition System
https://acc.dau.mil/UI/img/bo/minus.gifChapter 2 -- Program Strategies
https://acc.dau.mil/UI/img/bo/plus.gif2.0 Overview
https://acc.dau.mil/UI/img/bo/plus.gif2.1. Program Strategies—General
https://acc.dau.mil/UI/img/bo/plus.gif2.2. Program Strategy Document...
https://acc.dau.mil/UI/img/bo/minus.gif2.3. Program Strategy Relationship to...
https://acc.dau.mil/UI/img/bo/minus.gif2.4. Relationship to Request for...
https://acc.dau.mil/UI/img/bo/minus.gif2.5. Program Strategy Classification...
https://acc.dau.mil/UI/img/bo/plus.gif2.6. Program Strategy Document Approval...
https://acc.dau.mil/UI/img/bo/plus.gif2.7. Acquisition Strategy versus...
https://acc.dau.mil/UI/img/bo/plus.gif2.8. Technology Development...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 3 -- Affordability and...
https://acc.dau.mil/UI/img/bo/plus.gif3.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif3.1. Life-Cycle Costs/Total Ownership...
https://acc.dau.mil/UI/img/bo/plus.gif3.2. Affordability
https://acc.dau.mil/UI/img/bo/minus.gif3.3. Analysis of Alternatives
https://acc.dau.mil/UI/img/bo/plus.gif3.4. Cost Estimation for Major Defense...
https://acc.dau.mil/UI/img/bo/plus.gif3.5. Manpower Estimates
https://acc.dau.mil/UI/img/bo/plus.gif3.6. Major Automated Information Systems...
https://acc.dau.mil/UI/img/bo/minus.gif3.7. Principles for Life-Cycle Cost...
https://acc.dau.mil/UI/img/bo/plus.gif3.7.4. Further Information and Training
https://acc.dau.mil/UI/img/bo/minus.gifChapter 4 -- Systems Engineering
https://acc.dau.mil/UI/img/bo/plus.gif4.0. Overview
https://acc.dau.mil/UI/img/bo/minus.gif4.1. Introduction
https://acc.dau.mil/UI/img/bo/plus.gif4.1.1. Systems Engineering Policy and...
https://acc.dau.mil/UI/img/bo/plus.gif4.1.2. Systems Engineering Plan
https://acc.dau.mil/UI/img/bo/plus.gif4.1.3. Systems Level Considerations
https://acc.dau.mil/UI/img/bo/plus.gif4.1.4. Engineering Resources
https://acc.dau.mil/UI/img/bo/plus.gif4.1.5. Certifications
https://acc.dau.mil/UI/img/bo/plus.gif4.1.6. Systems Engineering Role in...
https://acc.dau.mil/UI/img/bo/plus.gif4.2. Systems Engineering Activities in...
https://acc.dau.mil/UI/img/bo/minus.gif4.3. Systems Engineering Processes
https://acc.dau.mil/UI/img/bo/plus.gif4.3.2. Technical Planning Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.3. Decision Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.4. Technical Assessment Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.5. Requirements Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.6. Risk Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.7. Configuration Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.8. Technical Data Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.9. Interface Management Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.10. Stakeholder Requirements...
https://acc.dau.mil/UI/img/bo/plus.gif4.3.11. Requirements Analysis Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.12. Architecture Design Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.13. Implementation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.14. Integration Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.15. Verification Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.16. Validation Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.17. Transition Process
https://acc.dau.mil/UI/img/bo/plus.gif4.3.18. Design Considerations
https://acc.dau.mil/UI/img/bo/plus.gif4.3.19. Tools Techniques and Lessons...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 5 -- Life-Cycle Logistics
https://acc.dau.mil/UI/img/bo/minus.gifChapter 6 -- Human Systems Integration...
https://acc.dau.mil/UI/img/bo/minus.gif6.0. Overview
https://acc.dau.mil/UI/img/bo/minus.gif6.1. Total System Approach
https://acc.dau.mil/UI/img/bo/minus.gif6.2 HSI - Integration Focus
https://acc.dau.mil/UI/img/bo/minus.gif6.3. Human Systems Integration Domains
https://acc.dau.mil/UI/img/bo/plus.gif6.3.4. Human Factors Engineering (HFE)
https://acc.dau.mil/UI/img/bo/minus.gif6.4. Human Systems Integration (HSI)...
https://acc.dau.mil/UI/img/bo/plus.gif6.5. Manpower Estimates
https://acc.dau.mil/UI/img/bo/plus.gif6.6. Additional References
https://acc.dau.mil/UI/img/bo/minus.gifChapter 7 -- Acquiring Information...
https://acc.dau.mil/UI/img/bo/plus.gif7.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif7.1. Introduction
https://acc.dau.mil/UI/img/bo/minus.gif7.2. DoD Information Enterprise
https://acc.dau.mil/UI/img/bo/minus.gif7.2.2. Mandatory Policies
https://acc.dau.mil/UI/img/bo/minus.gif7.2.3. The Use of Architecture
https://acc.dau.mil/UI/img/bo/minus.gif7.2.4. Integration into the Acquisition...
https://acc.dau.mil/UI/img/bo/minus.gif7.2.5. DoD Enterprise...
https://acc.dau.mil/UI/img/bo/minus.gif7.3. Interoperability and Supportability...
https://acc.dau.mil/UI/img/bo/minus.gif7.3.2. Mandatory Policies
https://acc.dau.mil/UI/img/bo/plus.gif7.3.3. Interoperability and...
https://acc.dau.mil/UI/img/bo/plus.gif7.3.4. Net-Ready Key Performance...
https://acc.dau.mil/UI/img/bo/plus.gif7.3.5. Net-Ready Key Performance...
https://acc.dau.mil/UI/img/bo/plus.gif7.3.6. Information Support Plan (ISP)...
https://acc.dau.mil/UI/img/bo/plus.gif7.4. Sharing Data, Information, and...
https://acc.dau.mil/UI/img/bo/plus.gif7.5. Information Assurance (IA)
https://acc.dau.mil/UI/img/bo/minus.gif7.6. Electromagnetic Spectrum
https://acc.dau.mil/UI/img/bo/plus.gif7.6.2. Mandatory Policies
https://acc.dau.mil/UI/img/bo/plus.gif7.6.3. Spectrum Management and E3 in the...
https://acc.dau.mil/UI/img/bo/plus.gif7.6.4. Spectrum Supportability Risk...
https://acc.dau.mil/UI/img/bo/plus.gif7.7. Accessibility of Electronic and...
https://acc.dau.mil/UI/img/bo/minus.gif7.8. The Clinger-Cohen Act (CCA) --...
https://acc.dau.mil/UI/img/bo/plus.gif7.8.4. Title 40/Clinger-Cohen Act (CCA)...
https://acc.dau.mil/UI/img/bo/plus.gif7.8.5. Other Title 40/Clinger-Cohen Act...
https://acc.dau.mil/UI/img/bo/plus.gif7.8.6. Title 40 Subtitle...
https://acc.dau.mil/UI/img/bo/plus.gif7.8.7. Procedure for Risk-Based...
https://acc.dau.mil/UI/img/bo/plus.gif7.9. Post-Implementation Review (PIR)
https://acc.dau.mil/UI/img/bo/plus.gif7.10. Commercial Off-the-Shelf (COTS)...
https://acc.dau.mil/UI/img/bo/minus.gif7.11. Space Mission Architectures
https://acc.dau.mil/UI/img/bo/plus.gifChapter 8 -- Intelligence Analysis...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 9 -- Test and Evaluation (T&E)
https://acc.dau.mil/UI/img/bo/plus.gif9.0 Overview
https://acc.dau.mil/UI/img/bo/plus.gif9.1 OSD T&E Organization
https://acc.dau.mil/UI/img/bo/plus.gif9.2 Service-Level T&E Management
https://acc.dau.mil/UI/img/bo/plus.gif9.3 Test and Evaluation
https://acc.dau.mil/UI/img/bo/plus.gif9.4 Integrated Test and Evaluation
https://acc.dau.mil/UI/img/bo/plus.gif9.5 Test and Evaluation Planning
https://acc.dau.mil/UI/img/bo/plus.gif9.6 T&E Reporting
https://acc.dau.mil/UI/img/bo/plus.gif9.7 Special Topics
https://acc.dau.mil/UI/img/bo/plus.gif9.8. Best Practices
https://acc.dau.mil/UI/img/bo/plus.gif9.9. Prioritizing Use of Government Test...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 10 -- Decisions Assessments and...
https://acc.dau.mil/UI/img/bo/plus.gif10.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif10.1. Decision Points
https://acc.dau.mil/UI/img/bo/plus.gif10.2. Executive Review Forums
https://acc.dau.mil/UI/img/bo/plus.gif10.3. Integrated Product and Process...
https://acc.dau.mil/UI/img/bo/plus.gif10.4. Role of Exit Criteria
https://acc.dau.mil/UI/img/bo/plus.gif10.5. Role of Independent Assessments
https://acc.dau.mil/UI/img/bo/plus.gif10.5.3. Preliminary Design Review (PDR)...
https://acc.dau.mil/UI/img/bo/plus.gif10.6. Information Sharing and DoD...
https://acc.dau.mil/UI/img/bo/plus.gif10.7. Management Control
https://acc.dau.mil/UI/img/bo/plus.gif10.8. Program Plans
https://acc.dau.mil/UI/img/bo/plus.gif10.9. Acquisition Program Baseline (APB)
https://acc.dau.mil/UI/img/bo/plus.gif10.10. Periodic Reports
https://acc.dau.mil/UI/img/bo/plus.gif10.11. Major Automated Information...
https://acc.dau.mil/UI/img/bo/plus.gif10.12. Defense Acquisition Executive...
https://acc.dau.mil/UI/img/bo/plus.gif10.13. Acquisition Visibility
https://acc.dau.mil/UI/img/bo/plus.gif10.14. Special Interest Programs
https://acc.dau.mil/UI/img/bo/plus.gif10.15. Relationship of Affordability and...
https://acc.dau.mil/UI/img/bo/plus.gif10.16. Acquisition Program Transition...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 11 -- Program Management...
https://acc.dau.mil/UI/img/bo/plus.gif11.0. Overview
https://acc.dau.mil/UI/img/bo/plus.gif11.1. Joint Programs
https://acc.dau.mil/UI/img/bo/plus.gif11.2. International Programs
https://acc.dau.mil/UI/img/bo/plus.gif11.3. Integrated Program Management
https://acc.dau.mil/UI/img/bo/plus.gif11.4. Knowledge-Based Acquisition
https://acc.dau.mil/UI/img/bo/plus.gif11.5. Technical Representatives at...
https://acc.dau.mil/UI/img/bo/plus.gif11.6. Contractor Councils
https://acc.dau.mil/UI/img/bo/plus.gif11.7 Property
https://acc.dau.mil/UI/img/bo/plus.gif11.8. Modeling and Simulation (M&S)...
https://acc.dau.mil/UI/img/bo/minus.gifChapter 12 - Defense Business System...
https://acc.dau.mil/UI/img/bo/plus.gif12.0 Overview
https://acc.dau.mil/UI/img/bo/plus.gif12.1 Business Capability Definition...
https://acc.dau.mil/UI/img/bo/plus.gif12.2 Investment Management (IM) Phase
https://acc.dau.mil/UI/img/bo/plus.gif12.3 Execution
https://acc.dau.mil/UI/img/bo/plus.gif12.4 DBS-specific Criteria
https://acc.dau.mil/UI/img/bo/plus.gif12.5 Tools and Methods
https://acc.dau.mil/UI/img/bo/minus.gifChapter 13 -- Program Protection
https://acc.dau.mil/UI/img/bo/plus.gif13.0 Overview
https://acc.dau.mil/UI/img/bo/plus.gif13.1 The Program Protection Process
https://acc.dau.mil/UI/img/bo/plus.gif13.2 The Program Protection Plan (PPP)
https://acc.dau.mil/UI/img/bo/plus.gif13.3 Critical Program Information (CPI)...
https://acc.dau.mil/UI/img/bo/plus.gif13.4. Intelligence and...
https://acc.dau.mil/UI/img/bo/plus.gif13.5. Vulnerability Assessment
https://acc.dau.mil/UI/img/bo/plus.gif13.6. Risk Assessment
https://acc.dau.mil/UI/img/bo/plus.gif13.7. Countermeasures
https://acc.dau.mil/UI/img/bo/plus.gif13.8. Horizontal Protection
https://acc.dau.mil/UI/img/bo/plus.gif13.9. Foreign Involvement
https://acc.dau.mil/UI/img/bo/plus.gif13.10. Managing and Implementing PPPs
https://acc.dau.mil/UI/img/bo/plus.gif13.11. Compromises
https://acc.dau.mil/UI/img/bo/plus.gif13.12. Costs
https://acc.dau.mil/UI/img/bo/plus.gif13.13. Contracting
https://acc.dau.mil/UI/img/bo/plus.gif13.14. Detailed System Security...
https://acc.dau.mil/UI/img/bo/plus.gif13.15. Program Protection Plan (PPP)...
https://acc.dau.mil/UI/img/bo/plus.gif13.16. Program Protection Plan (PPP)...
https://acc.dau.mil/UI/img/bo/plus.gifChapter 14 -- Acquisition of Services
https://acc.dau.mil/UI/img/bo/minus.gifDoD Directive 5000.01
https://acc.dau.mil/UI/img/bo/plus.gifENCLOSURE 1 ADDITIONAL POLICY
https://acc.dau.mil/UI/img/bo/minus.gifDoD Instruction 5000.02
https://acc.dau.mil/UI/img/bo/plus.gifTABLE OF CONTENTS
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 1 -- References
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 2 -- Procedures
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 3 -- Acquisition Category...
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 4 -- Statutory and Regulatory...
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 5 -- IT Considerations
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 6 -- Integrated T&E
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 7 -- Resource Estimation
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 8 -- Human Systems Integration...
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 9 -- Acquisition of Services
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 10 -- Program Management
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 11 -- Management of Defense...
https://acc.dau.mil/UI/img/bo/plus.gifEnclosure 12 -- Systems Engineering
https://acc.dau.mil/UI/img/bo/minus.gifRecent Policy and Guidance
https://acc.dau.mil/UI/img/bo/plus.gifDownload the Defense Acquisition...
https://acc.dau.mil/UI/img/bo/plus.gifWeapon Systems Acquisition Reform Act of...
https://acc.dau.mil/UI/img/bo/plus.gifCurrent JCIDS Manual and CJCSI 3170.01 I
https://acc.dau.mil/UI/img/bo/minus.gifDefense Acquisition Guidebook Key...
ACC Practice Center Version 3.2
  • Application Build 3.2.9
  • Database Version 3.2.9