Project Name Location
Developer
|
Technology
|
Potential Output (MW)
|
BLM Acreage
|
Peak Jobs
|
Approval Date
|
Status
|
Anticipate Operational Date
|
Soda Mtn Solar Project
|
PV
|
287
|
0 (connected action)
|
4,179
|
|
Approved
|
2018
|
Blythe Mesa Solar Project Riverside County, CA
RRG Renewables
|
PV
|
485
|
0 (connected action)
|
2,800
|
8/18/2015
|
Approved
|
2016
|
Luning Solar Mineral County, NV
Invenergy Solar
|
PV
|
50
|
560
|
|
6/30/15
|
Under construction
|
2016
|
Dry Lake Solar Energy Center Dry Lake Solar Energy Zone Clark County, NV
NV Energy
|
PV
|
130
|
660
|
400
|
5/27/15
|
Approved
|
2016
|
Dry lake Solar Energy Zone Project Dry Lake Solar Energy Zone Clark County, NV
Playa I & Playa II
|
PV
|
200
|
1,710
|
1,200
|
5/27/15
|
Under construction
|
2016
|
Harry Allen Solar Energy Center Dry Lake Solar Energy Zone Clark County, NV
Invenergy
|
PV
|
112
|
594
|
350
|
5/27/15
|
Approved
|
2016
|
Moapa Solar (BIA) Clark County, NV
RES America
|
PV/CSP
|
200
|
0 (850 acres of Tribal land)
|
500
|
5/1/14
|
Approved
|
2015
|
Ocotillo Sol Solar Imperial County, CA
San Diego Gas and Electric
|
PV
|
20
|
100
|
120
|
4/7/14
|
Approved
|
2015
|
Silver State Solar South Clark County, NV
First Solar
|
PV
|
250
|
2,400
|
350
|
2/14/14
|
Completing construction
|
Partially operational 2015
|
Stateline Solar San Bernadino County, CA
First Solar
|
PV
|
300
|
1,685
|
400
|
2/14/14
|
Initial construction
|
2015
|
Midland Solar Clark County, NV
Boulder Solar Power
|
PV
|
350
|
0 (connected action)
|
350
|
5/30/13
|
Approved
|
2015
|
Quartzite Solar La Paz County, AZ
Quartzite Solar Energy.
|
Power tower
|
100
|
1,675
|
438
|
5/30/13
|
Approved
|
2017
|
Boulder Power Solar Clark County, NV
Techren
|
PV
|
300
|
0 (connected action)
|
375
|
3/21/13
|
Under Construction
|
2016
|
McCoy Solar Project Riverside East SEZ Riverside County, CA
NextEra
|
PV
|
750
|
7,700
|
503
|
3/13/13
|
Initial construction
|
2017
|
Desert Harvest Solar Project Riverside East SEZ, Riverside County, CA
EDF Renewable
|
PV
|
150
|
1,208
|
250
|
3/13/13
|
Approved
|
2015
|
Mountain View Solar Project Clark County, NV
NextEra
|
PV
|
20
|
0 (connected action)
|
|
2/14/13
|
In operation
|
Operations began 2015
|
Copper Mountain Solar III Project Clark County, NV
Sempra
|
PV
|
220
|
0 (connected action)
|
|
2/14/13
|
In operation
|
Operations began 2015
|
Campo Verde Solar Project Imperial County, CA
Campo Verde Solar, LLC
|
PV
|
139
|
0 (connected action)
|
250
|
9/26/12
|
In operation
|
Operations began in October 2013
|
Moapa Solar Project Clark County, NV
Southern Paiute
|
PV
|
350
|
0 (2,000 acres of Tribal land)
|
400
|
6/21/12
|
Under construction
|
2016
|
Centinela Solar Energy Project Imperial County, CA
Centinela Solar Energy, LLC
|
PV
|
275
|
0 (connected action)
|
367
|
12/28/11
|
In operation
|
Online August 2014
|
Sonoran Solar Project Maricopa County, AZ
NextEra Energy Resources, LLC
|
PV
|
300
|
4,000
|
374
|
12/20/11
|
Approved
|
Pending power purchase agreement
|
Rice Solar Energy Riverside County, CA
​​​​​​​Rice Solar Energy, LLC
|
Power tower
|
150
|
0 (connected action)
|
500
|
12/8/11
|
Authorization terminated
|
NA
|
C Solar West Imperial County, CA
​​​​​​​LightSource Renewables
|
Thin film PV
|
250
|
0 (connected action)
|
290
|
8/23/11
|
Approved
|
2016
|
Desert Sunlight Solar Farm Riverside County, CA
​​​​​​​First Solar Development, Inc.
|
Thin film PV
|
550
|
4,165
|
645
|
8/9/11
|
In operation
|
Operations began in November 2013
|
Imperial Solar Energy Center (CSolar) South Imperial County, CA
LightSource Renewables
|
Thin film PV
|
200
|
0 (connected action)
|
255
|
7/14/11
|
In operation
|
Operations began in November 2013
|
Abengoa Mojave Solar Riverside County, CA
​​​​​​​Mojave Solar
|
Parabolic trough
|
250
|
0 (connected action)
|
890
|
7/11/11
|
In operation
|
Operations began in 2016
|
Crescent Dunes Solar Project Nye County, NV
​​​​​​​SolarReserve, LLC
|
Power tower
|
110
|
1,600
|
550
|
12/20/10
|
In operation
|
Operations began in 2015
|
Amargosa Farm Road Solar Project Nye County, NV
​​​​​​​Solar Millenium, LLC
|
Parabolic trough
|
464
|
4,350
|
1,370
|
11/15/10
|
Authorization terminated at request of developer
|
N/A
|
Genesis Solar Energy Project Riverside County, CA
Solar Millenium, LLC
|
Parabolic trough
|
250 |
4,640 |
1,135 |
11/4/10 |
In operation |
Operations began in November 2013 |
Blythe Solar Power Project Riverside County, CA
Solar Millenium, LLC
|
PV (amended from parabolic trough)
|
Original: 1,000
Amended: 485
|
Original: 6,831
Amended: 4,138
|
Original: 1,361
Amended: 620
|
Original: 10/22/10
Amended: 8/1/2014
|
Approved as amended for technology change
|
2016
|
Calico Solar Energy project San Bernadino County, CA
Acquired by K Road Power
|
Originally solar dish; changing to PV
|
663.5
|
4,604
|
536
|
10/20/10
|
Authorization terminated at request of developer
|
N/A
|
Ivanpah Solar Electric Generating System (SEGS) San Bernadino County, CA
​​​​​​​BrightSource Energy
|
Power tower
|
370
|
3,472
|
2,100
|
10/17/10
|
In operation
|
Operations began in December 2013
|
Silver State Solar Energy Project (North) Clark County, NV
​​​​​​​First Solar, Inc.
|
Thin film PV
|
50
|
618
|
310
|
10/12/10
|
In operation
|
Operation began in May 2012
|
Lucerne Valley Solar Project San Bernadino County, CA
Chevron Energy Solutions
|
Thin film PV
|
45
|
516
|
48
|
10/5/10
|
Terminated effective 12/31/2012
|
N/A
|
Imperial Valley Solar Project Imperial County, CA
Tessera Solar North America
|
Originally planned as solar engine
|
709
|
6,360
|
N/A
|
10/5/10
|
Authorization terminated at request of developer
|
N/A
|