The Secretary of the Interior authorized the Shoshone Project on February 10, 1904, under authority of the Reclamation Act of June 17, 1902.
Floodwaters of the Shoshone River are stored in Buffalo Bill Reservoir for later release for irrigation and power generation. Power is developed at the Shoshone, Heart Mountain, Buffalo Bill, and Spirit Mountain Powerplants. The system is interconnected with the West Division of the Pick-Sloan Missouri Basin Program.
Plan
The primary purpose of the Spirit Mountain Powerplant is to dissipate energy of the water from the pressurized supply conduit from Buffalo Bill Reservoir before it enters the unpressurized supply canal which feeds the Heart Mountain Powerplant and the Heart Mountain Canal. The secondary purpose of the powerplant is to produce electrical power. Spirit Mountain Powerplant consists of one 4,500-kilowatt generator. Operation of this plant began in October, 1994. This plant cannot operate unless the downstream Shoshone conduit is watered up. As a result of the modification of Buffalo Bill Dam, Buffalo Bill and Shoshone Powerplants were completed in 1992. Due to the Revised Instream Flow Agreement associated with the reconstruction of the dam, winter releases previously discharged from Heart Mountain Powerplant that would have passed through spirit Mountain Powerplant are now made through the two upstream facilities. As a result, Spirit Mountain Powerplant has been operated on a seasonal basis since its completion in 1995. Western Electricity Coordinating Council, Rocky Mountain Power Area Western Area Power Administration, Rocky Mountain Region Conventional Above Ground Francis 4,500 kW 4,500 kW 1994 19 years 16,136,200 kWh 2007 110 ft
General
NERC Region
Western Electricity Coordinating Council, Rocky Mountain Power Area
PMA Service Area
Western Area Power Administration, Rocky Mountain Region
Plant Type
Conventional
Powerhouse Type
Above Ground
Turbine Type
Francis
Original Nameplate Capacity
4,500 kW
Installed Capacity
4,500 kW
Year of Initial Operation
1994
Age
19 years
(Fiscal Year)
2007
Rated Head
110 ft
Plant Factor
41.6percent
Production Mode
Base Load, Seasonal
Remotely Operated
Yes
River
Shoshone River
Contact
Contact
Title: Facility Manager Organization: Big Horn Basin Field Office Address: #4 Reclamation Road City: Cody, WY 82414 Phone: 307-527-6256-(ext.-260)