Oil and Gas Well Drilling and Servicing eTool
Home | Site Preparation | Drilling | Well Completion | Servicing | Plug and Abandon Well | General Safety and Health
Site Map | Glossary of Terms | Illustrated Glossary
OSHA uses Safety and Health Regulations for Construction (29 CFR 1926) to assess safety compliance during this phase of the development of a drilling site.
Once the location for the site has been established, the area is prepared for drilling, with the following steps:
Site Preparation
Site preparation for an oil and gas well, in most instances, looks like any other construction site. Includes:
Conductor Hole, Rathole and Mousehole
Prior to commencing the rig-up process, the conductor, rathole and mousehole are completed.
Transporting Equipment
to the Site
Depending on the location of the well, access to the site may require preparation of a road bed.