Gavins Point Dam - Omaha District US Army Corps of Engineers

OMAHA DISTRICT

Home
Home > Missions > Regulatory Program > Nebraska > Public Notices

Public Notices

1 2 3


NWO-2015-01744-WEH - 1/13/2017: Saunders County SID #8 - The proposed river bank stabilization project is adjacent to the Woodcliff Lakefront Residential Development, also known as Sanitary Improvement District (SID) 8, and located approximately 3 miles downstream from Fremont, Nebraska. The project begins approximately 350 feet downstream from the Burlington Northern Santa Fe Railway Company’s (BNSF) Platte River bridge crossing, extending approximately 1.6 miles downstream along the south bank, and ends at the Woodcliff boat ramp. The applicant’s project will protect the SID’s perimeter access roadway embankment, adjacent utilities infrastructure, and protect the remaining riverine buffer between the road and the Platte River channel bank. The project will result in the total permanent discharge of fill material in waters of the U.S. (WOUS) totaling 1,491 linear feet (LF) (0.575 acre) of channel bank and 0.129 acre of PEMA/C riverine channel wetland impacts.
Expiration date: 2/3/2017

ATTACHMENTS:  


2017 NWPs Issuance and Reissuance of all 50 nationwide permits (NWPs) - 1/9/2017: On January 6, 2017, the U.S. Army Corps of Engineers (Corps) published the notice in the Federal Register announcing the reissuance of all 50 existing nationwide permits (NWPs), general conditions, and definitions with some modifications. The Corps also issued two new NWPs, one new general condition, and five new definitions. The 2017 NWPs will go into effect on March 19, 2017, and will expire on March 18, 2022.
Expiration date: 3/18/2022


NWO-2011-02364-WEH - 12/21/2016: GP 11-02 - General Public - This Regional General Permit (RGP) authorizes the following flood protection, reconstruction and repair work for flood damaged areas: (1) Repair and reconstruction of existing roads. (2) Construction of temporary roads. (3) Construction of temporary levees, dikes and berms. (4) Repair of levees including breach closures. (5) Protection (e.g. armoring) and/or repair of bridge and linear transportation embankments. (6) Protection and/or repair of utility structures. (7) Placement of suitable material for bank stabilization. (8) Construction of temporary drainage ditches to facilitate the removal of flood water, sheetwater or excess water. (9) Restoration of channels and ditches to pre-flooding alignment and capacity. (10) Protection and restoration of intake and outfall structures. (11) Removal of flood-deposited sediments and grading/restoration to pre-flood contours. The disposal of flood-deposited sediment should be performed within uplands. Flood-deposited sand/silt material from the Missouri River may be returned back into the Missouri River up to 100,000 cubic yards of material per activity. The authorization of in-stream disposal of flood-deposited sand/silt material back into other rivers will be determined on a case-by-case basis. Issues considered will include total and daily amounts of proposed disposal, method of disposal, location of disposal, concurrent disposal activities, time of year and flow rates.
Expiration date: 1/10/2017

ATTACHMENTS:  


1 2 3