December FERC addresses compliance filing and requires further compliance filings, December 17, 2009, Decision
FERC denies Rehearing Request of its Sept. 30, 2009 Order, December 17, 2009, Decision
FERC issues Order No. 730 regarding mandatory reliability standards, December 17, 2009, Order No. 730
November
October FERC approves order revising reliability standards for critical infrastructure protection and requires compliance filing, October 8, 2009, Decision
September
FERC approves order revising reliability standards for critical infrastructure protection and requires compliance filing, September 30, 2009, Decision
June
FERC denies rehearing on Mandatory Reliability Standards for Critical Infrastructure Protection, June 18, 2009, Order No. 706-C
FERC seeks comments on revised mandatory reliability standards for interchange scheduling and coordination (INT), June 18, 2009, NOPR
May
FERC seeks comment on NERC's Reliability Standard-Transmission Relay Loadability, May 21, 2009, NOPR
FERC approves WECC Regional Reliability Standard on Regarding Automatic Time Error Control, May 21, 2009, Order No. 723
FERC rules on NERC's interpretation of specific requirements of frequency response and bias and voltage and reactive control reliability standards, May 21, 2009, Order No. 724
March
FERC approves three revised Reliability Standards developed by the North American Electric Reliability Corporation (NERC). The three revised Reliability Standards, set requirements for the development and communication of system operating limits of the Bulk-Power System for use in the planning and operation horizons. In addition, the Commission approves, with modifications, the violation severity levels for the three Reliability Standards, March 20, 2009, Order No. 722
FERC issues a supplemental final rule that approves a Reliability Standard which addresses transmission loading relief requirements. The modified Reliability Standard includes changes directed by the Commission related to the appropriateness of using the Transmission Loading Relief procedure to mitigate a violation of an interconnection reliability operating limit, March 19, 2009, Order No. 713-A
NOPR to approve six Modeling, Data, and Analysis Reliability Standards submitted to the Commission for approval by the North American Electric Reliability Corporation. The proposed Reliability Standards require certain users, owners, and operators of the Bulk-Power System to develop consistent methodologies for the calculation of available transfer capability or available flowgate capability, March 19, 2009, NOPR
NOPR to include certain business practice standards adopted by the Wholesale Electric Quadrant of the North American Energy Standards Board (NAESB) into FERC regulations. NAESB's Version 002.1 Standards mainly modify NAESB's Version 001 Standards in response to Order Nos. 890, 890-A, and 890-B, March 19, 2009. NOPR
January
FERC clarifies October 16, 2008 Budget Order at NERC’s request, January 15, 2009, Decision
FERC audit recommends changes to improve SPP independence, SPP agrees FERC also gives guidance on reliability compliance audits, January 15, 2009, News Release
| Decisions: E-1 and E-21 |
|
|
December
FERC accepts compliance filings, subject to conditions from the North American Electric Reliability Corporation, December 19, 2008 Decision
FERC orders submission of data from the North American Electric Reliability Corporation (NERC) and Northeast Power Coordinating Council, Inc. (NPCC), December 19, 2008, Decision
November
October
September
July
April
Modification of Interchange and Transmission Loading Relief Reliability Standards; and Electric Reliability Organization Interpretation of Specific Requirements of Four Reliability Standards, April 21, 2008, NOPR
Statement of administrative policy on processing reliability notices of penalty and order revising statement in Order No. 672, April 17, 2008, Administrative Policy
March
FERC joins investigation into Florida blackout, March 19, 2008, News Release | Order
Mandatory Reliability Standard for Nuclear Plant Interface Coordination (NOPR), March 20, 2008, NOPR
Order providing guidance on recovery of reliability penalty costs by regional transmission organizations, March 20, 2008, Decision
February
FERC conditionally approves amended Rules of Procedures for NERC, February 21, 2008 - The Order approves a new section 1600, which would establish a process for NERC or a Regional Entity to issue requests for data or information. The order conditionally approves section 1600 of NERC's Rules of Procedure and directs NERC to make a compliance filing within 90 days of issuance of this order Decision E-12
FERC denies rehearing of its November 15, 2007 Order, February 21, 2008 - In the November 15 Order, the Commission affirmed NERC's determination that the Florida Reliability Coordinating Council (FRCC), a NERC Regional Entity, had properly registered Lee County, Florida (Lee County) as a generator owner and had registered Covanta Lee, Inc. (Covanta), a contractor operating the Lee County generating facility, as a generator operator. Further, the November 15 Order affirmed NERC's determination that FRCC had properly registered the Solid Waste Authority of Palm Beach County, Florida (SWA) as a generator owner and generator operator. Decision E-11
FERC remands proceeding to Electric Reliability Organization, February 21, 2008 - FERC remands to the North American Electric Reliability Corporation (NERC), a decision in which NERC found that the Southeastern Power Administration (SEPA) was properly included on the NERC compliance registry as a transmission operator and resource planner, and thus subject to mandatory and enforceable Reliability Standards applicable to those functions. SERC Reliability Corporation (SERC), a NERC Regional Entity, registered SEPA as a transmission operator and resource planner. SEPA sought NERC review of SERC's decision and, after affirmation by NERC, appealed to the Commission to reverse the NERC determination. The Commission remands this proceeding to NERC for further consideration and to submit, within 60 days of the date of this order, a revised registration determination that addresses the Commission's concerns Decision E-10 |
|
|
December Commission approves Reliability Standards, December 27, 2007, Order No. 705
Commission rules on electric reliability organization registry determinations for Direct Energy Services, LLC, Sempra Energy Solutions LLC and Strategic Energy, L.L.C., December 20, 2007, Decision
November
Commission approves modified Violation Risk Factors submitted by NERC, November 16, 2007, Decision
Commission affirms electric reliability organization compliance registry determinations for Lee County, Florida, November 15, 2007, Decision
October
Commission increases funding for grid reliability organizations, October 18, 2007, News Release | Decisions E-2 and E-14
September
Commission directs staff to convene a technical conference to further explore the registration of retail power marketers in the Reliability First region as Load Serving Entities, September 26, 2007, Decision
FERC clarifies earlier decision and directs NERC to clarify some of its rules, September 20, 2007, News Release | Decision E-1
August
Commission proposes to approve three planning and operating reliability standards, August 13, 2007, Decision
July
Commission proposes adoption of new reliability standards for cyber security in the bulk power system: a set of reliability standards to help safeguard the nation's bulk electric power supply system against potential disruptions from cyber attacks. The NOPR also calls for NERC to develop modifications to address specific concerns identified by the Commission, July 19, 2007, News Release | Decision E-5 | NOPR | Order 693-A
June
Commission approves 22 Violation Risk Factors associated with Commission-approved Reliability Standards, June 26, 2007, Decision
Commission approves eight regional Reliability Standards for the Western Interconnection, June 8, 2007, Decision
May
April
Commission accepts NERC's regional reliability entity delegation agreements; additional WECC funding approved. Third in a series of orders designed to establish a new regime to ensure reliability for the nation's bulk electric power system, laying the foundation for mandatory, enforceable power-system reliability standards to be in place in time for this summer's peak electricity demand season, April 19, 2007, News Release | Decision E-19 | Decision E-2
March
February
WECC's Reliability Coordinator Activities Conference Ordered: Commission staff to convene a technical conference to discuss the issues raised concerning WECC’s reliability coordinator activities, February 15, 2007, Decision |
|
|
October Inquiry into Gas-Electric Coordination Issues: Scheduling practices of ISOs and RTOs;
et al.), October 25, 2006, Decision
Notice of Proposed Rulemaking on Proposed Reliability Standards: Proposed rule would approve
83 NERC reliability standards; Funding for statutory activities
through ERO approved, October 19, 2006, News Release | NOPR | Decision E-3 September
Approval of EEI's Spare Transformer Equipment Program: Commission acts to improve security of Nation's power grid, September 21, 2006, News Release | Decision
July
ERO Certification and WIRAB Approval: NERC certified as Electric Reliability Organization; Western Governors’ Reliability Advisory body accepted, July 20, 2006, News Release | Decisions E-5 and E-6 May
April
April 18, 2006 - Initiation of Reliability Standards Rulemaking: Commission announces rulemaking for processing Reliability Standards pending ERO certification News Release | Notice
March
February
January
Reliability in Washington, DC: Pepco, PJM directed to develop plan to assure reliability in Washington, DC region, January 9, 2006, News Release | Decision |
|
|
September
August June
North America Cooperation: States and Canada Agencies cooperate to ensure electric reliability in North America, June 30, 2005, News Release | Terms of Reference
Support of Formation of Independent Transmission Companies: New policy removes barriers to
formation of independent transmission companies, June 27, 2005, News Release | Policy
Statement |
|
|
December
May
General Reliability Compensation Policy: Commission announced a general
Reliability Compensation Policy in the PJM Order, May 6, 2004, Docket
No. EL03-236-000
April
Blackout Task Force recommendation: FERC takes prompt action in
response to Blackout Task Force recommendations; outlines power
reliability policy, April 14, 2004, News Release | Presentations Event Details | Policy Statement (PL04-5) | Order (EL04-52) |
|
|
December
Independent Study of the Ohio's Power Grid: The Commission has ordered
FirstEnergy Corp. to pay for an independent study of the state's
power grid, where the massive August blackout started. They have
120 days to study the stability of the power grid, December 24, 2003, Read
More
FERC to Require Reporting of Power-Grid Reliability Violations: The Commission directed
staff to develop an order that will require transmission
system operators to report violations of the industry’s power-grid
reliability standards, December 17, 2003 |
|