New York District Header Image

NEW YORK DISTRICT

Home
Home > Media > Fact Sheets > Fact Sheet Article View

Hurricane and Storm Damage Reduction

Bookmark and Share Email Print

DESCRIPTION: The authorized project provides for hurricane protection and beach erosion control along five reaches of the south shore of Long Island between Fire Island Inlet and Montauk Point, a distance of approximately 83 miles. The project also authorizes Federal participation in periodic nourishment. The sponsor is the New York State Department of Environmental Conservation. In 1978, the Department of the Interior (DOI) supported by other agencies referred the Environmental Impact Statement (EIS) for the authorized project to the Council on Environmental Quality (CEQ) as unacceptable. In June 1978, CEQ recommended project reformulation to the Chief of Engineers, who in turn directed the District to reformulate the project. Reformulation was originally initiated in 1980; however, because of difficulties between the Federal, State and County in proceeding with the Westhampton reach, which at the time was the most vulnerable reach of the authorized project, the Reformulation was suspended. Based on letters of intent to support an interim plans, the Reformulation study was resumed in 1994. Work on the Reformulation study is currently ongoing, with several interim projects already constructed for critical vulnerable areas. 

AUTHORIZATION: The project was authorized by the Rivers and Harbors Act of 14 July 1960 in accordance with House Document 425 and subsequently modified by the River & Harbor Act of 1962, and the Water Resources Development Acts of 1974, 1986 and 1992. In response to the 2012 Sandy event, P.L. 113-2, The Disaster Relief Appropriations Act of 2013, will provide the required Federal funds to complete the reformulation study and to complete initial construction, including stabilization efforts, at 100% Federal cost. 

 

STATUS:

 

Previously completed work:  

MORICHES INLET TO SHINNECOCK INLET: 11 groins constructed in the Westhampton Beach area in 1965. Additional 4 groins with beach and dune fill placed west of the 11-groin field in 1969-1970. The Westhampton Interim Project, which included groin modification and beach fill within and west of the 15-groin field, was completed in December 1997. The West of Shinnecock Interim Project, which includes beach fill west of the Shinnecock navigation channel, was completed in March 2005. SOUTHAMPTON to BEACH HAMPTON: 2 groins constructed at Georgica Pond in 1965. 

 

Current ongoing study effort: 

REFORMULATION STUDY: The goal of the Reformulation Study is to identify storm damage risk reduction within the study area and to evaluate alternative methods of providing authorized beach erosion control and hurricane protection. A Design Agreement was executed with the State of New York in October 2002 in order to cost-share study costs at 75% Federal and 25% Non-Federal. Coordination is currently underway with all project sponsors, including the State of New York and the U.S. Department of Interior, on finalization of the Reformulation Study. This effort will be completed at 100% Federal expense. 

 

Interim and Stabilization Efforts:  

State, local and congressional interests requested that the Corps provide immediate remedial actions for critical vulnerable areas. These interim and stabilization actions will be modified, as necessary, based on the ultimate recommendations of the Reformulation Study.

 

BREACH CONTINGENCY PLAN: Provides a mechanism for rapid breach closure of the barrier islands through the 83-mile project area. A Breach Contingency Plan was approved in February 1996. Under the approved Project Cooperation Agreement, the Corps is authorized to execute specific PPA’s with the State of New York in order to close breaches immediately after coastal storms. The Sandy storm event of October 2012 resulted in damages to Long Island's barrier beaches. This event breached the barrier island in several locations on Long Island, specifically at Cupsogue County Park and Smith Point County Park, leaving the area vulnerable to significant damages. On November 2, 2012, the State of New York formally requested emergency assistance from the Corps to activate the Breach Contingency Plan. Emergency contract actions were issued for both areas. The Cupsogue breach was closed on November 27, 2012, and the Smith Point breach was closed on December 7, 2012. Sandy also caused a third breach within the Fire Island Wilderness Area (Old Inlet area). This breach is currently open, with ongoing monitoring by NPS and NYS underway to determine if the breach will close naturally or if it will be necessary to close the breach via a contract action. 

 

WESTHAMPTON INTERIM PROJECT: Provides interim protection to the Westhampton Beach area west of Groin 15 and affected mainland communities north of Moriches Bay. The project provides for a protective beach berm and dune, tapering of existing groins 14 & 15, and construction of an intermediate groin (14a). The project also includes periodic nourishment as necessary to ensure the integrity of the project design, for up to 30 years (thru 2027). Beachfill for this interim project also includes placement within the existing groin field to fill the groin compartments and encourage sand transport to the areas west of groin 15. Initial construction was completed in December 1997 at an approximate cost of $20 million. The project has performed better than anticipated in terms of anticipated cost, project performance and beneficial environmental impacts. The first renourishment effort was completed in February 2001 at an approximate cost of $5 million. The second renourishment effort was completed in December 2004 at an approximate cost of $4.5 million. A portion of the third renourishment effort was completed in February 2009 at an approximate cost of $9.5 million. In response to 2012 Sandy damages, P.L. 113-2, the Disaster Relief Appropriations Act of 2013 funded the restoration of this project to its original design template at 100% Federal cost. This construction contract was completed October 2015. Required coastal and environmental monitoring efforts continue every year within the Westhampton project area.  

 

WEST OF SHINNECOCK INTERIM PROJECT: Provided interim protection to the area immediately west of Shinnecock Inlet up to 4,000 feet westerly, which is a potential breach area. The project was intended to provide protection until implementation of Reformulation Study recommendations. This interim project consisted of initial beachfill placement, with 2 anticipated renourishments, for a period not to exceed 6 years (thru 2011). The placement of sand in this area enabled future maintenance dredging of Shinnecock Inlet to bypass sand past the influence of the inlet. Initial beach fill placement was completed in March 2005 at an approximate cost of $4.3 million. No renourishment efforts were ever completed due to lack of funds. This Interim project is considered complete, until a new recommendation is made by the Reformulation Study, or a new decision document is prepared which would approve the extension of interim nourishment efforts. An emergency contract for P.L. 84-99 rehabilitation of this project, which was damaged by both the Irene and Sandy events, was completed by the Corps in January 2013, placing approximately 300k cy of sand west of the inlet to repair the project to pre-storm conditions. In conjunction with this contract, a Memorandum of Agreement was executed between the Corps and NYS for placement of an additional 124k cy of material at Tiana beach. In response to 2012 Sandy damages, P.L. 113-2, the Disaster Relief Appropriations Act of 2013 funded the restoration of this project to its original design template at 100% Federal cost. This work was completed March 2014, placing an additional 450k cy of sand in the project area.  

 

POST-SANDY ONE-TIME STABILIZATION EFFORTS: The Corps, State of New York and U.S. Department of Interior have developed a mutually acceptable one-time stabilization plan along the Fire Island barrier island to provide protection until implementation of the recommendations of the overall Reformulation Study.  These stabilization efforts are one-time placement projects and include no nourishment cycles. The efforts are meant to provide protection until the implementation and construction of final recommendations of the overall Reformulation Study.  

 

FIRE ISLAND STABILIZATION:  The Fire Island Stabilization Project consists of a one-time sand placement along Fire Island. The Fire Island Stabilization HSLRR and EA were approved July 2014, with a Project Partnership Agreement executed with the State of New York in August 2014.  Award of the first construction contract at Smith Point County Park occurred in October 2014, with all construction work completed April 2016.  Award of the second construction contract at Robert Moses State Park thru Saltaire occurred in January 2015, with all construction work anticipated to be completed by Fall 2016.  Award of the third construction contract at Robert Moses State Park and from Fair Harbor thru Seaview occurred in August 2016, with construction completion anticipated for mid-2017. Award of the next set of construction contracts for the various remaining Fire Island communities are expected late 2016/early 2017 (Ocean Bay Park thru Davis Park), after acquisition of the required real estate is completed by the project sponsor.  

 

DOWNTOWN MONTAUK:  An additional stabilization project was approved for Downtown Montauk. The Downtown Montauk Stabilization HSLRR and EA were approved in November 2014.  A Project Partnership Agreement was executed with the State of New York in March 2015. Contract Award occurred in March 2015, with all construction completed in July 2016.  

 

 

CONTACT:

 

  

For questions on the FIRE ISLAND TO MONTAUK POINT, NY - REFORMULATION STUDY

 

Mr. Mark Lulka,

 Project Manager  

 U.S. Army Corps of Engineers, New York District  

 Phone: (917) 790-8205 

 E-mail: Mark.F.Lulka@usace.army.mil 

Programs and Project Management Division

 26 Federal Plaza,

 New York, NY 10278

 

For questions on the all other FIRE ISLAND TO MONTAUK POINT, NY construction activities

 

 Mr. Frank Verga,  

 Project Manager  

 U.S. Army Corps of Engineers, New York District  

 Phone: (917) 790-8212  

 E-mail: frank.verga@usace.army.mil  

 Programs and Project Management Division

 26 Federal Plaza,

 New York, NY 10278

 

 

CONGRESSIONAL DISTRICTS: NY-1, NY-2

 

Current as of August 2016