PGDP Deactivation Project scope major activities:
Site Optimization Studies include: |
---|
- Steam, Air, Nitrogen and Chilled Water Optimization Study |
- Water Treatment Facility Optimization Study |
- C-100 Optimization Study |
- Sewer Evaluation Study |
Facility Stabilization
- Preparation and/or removal of nuclear materials and contaminants from facilities.
- Stabilization activities are performed during early stages of facility deactivation.
Facility Deactivation
- Removal of radioactive and hazardous materials
- Shut down facility systems
- De-energize equipment in preparation for long-term maintenance and cleanup
Infrastructure Optimization
- Scale down and optimization of utilities including water, sewage treatment, and steam to meet the needs of the project
Scope and Timeline:
Period 1 Task Order Implementation – implementation, mobilization and planning from Notice to Proceed through 90 days; concluded October 20, 2014
Period 2 De-Lease Planning and Transfer – preparation of facility transfer and planning of facility modifications; turnover occurred October 21, 2014
Period 3 Facility Deactivation & Infrastructure Optimization – provide utility service, complete Stabilization and Deactivation, perform Surveillance and Maintenance, and implement planned modifications; continues through the end of the Deactivation Task Order
Period 4 Post-GDP Shutdown Environmental Services – transfer and execution of Environmental Services & Waste Management Activities; begins 90 days prior to the end of the Remediation Contract in July 2015 and continues through the end of the Task Order
Period 5 Project Support – activities and resources throughout the performance of the Task Order