Title:
San Luis & Delta-Mendota Water Authority 2015 Delta-Mendota Canal Reverse Flow Project
Site:
Summary:
Reclamation proposes to approve the installation of a 75 cfs temporary pumping plant at MP 54.41 on the Delta-Mendota Canal (Check Structure No. 10) in order to reverse flow CVP and non-CVP water previously stored in San Luis Reservoir to Byron-Bethany Irrigation District, Banta-Carbona Irrigation District, City of Tracy, Del Puerto Water District, Patterson Irrigation District, West Stanislaus Irrigation District, San Luis Water District, and Central California Irrigation District.

Status:
05/28/2015:
EA completed and FONSI signed on May 28, 2015. Draft EA was available for review May 18 - May 22, 2015.

Contacts:
Rain Emerson
Phone: 559-487-5196
Fax:

List of Available Reports
 
Report Title
File Ext
File Size
File with .pdf extension Completed EA and Signed FONSI, San Luis & Delta-Mendota Water Authority 2015 Delta-Mendota Canal Reverse Flow Project .pdf 1,231.15KB 
File with .pdf extension Draft EA, San Luis & Delta-Mendota Water Authority 2015 Delta-Mendota Canal Reverse Flow Project .pdf 1,256.15KB